ML20059C982

From kanterella
Jump to navigation Jump to search
Forwards Schedule for Approval of TS Changes Necessary to Support Facility Restart,As Requested
ML20059C982
Person / Time
Site: Browns Ferry Tennessee Valley Authority icon.png
Issue date: 12/23/1993
From: Salas P
TENNESSEE VALLEY AUTHORITY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9401060287
Download: ML20059C982 (9)


Text

-)

. -e TUA lennessee Valley Authority Post Othc.e Box 2000. Decahr. Alabama 35609 l

i DEC 2 31993 U.S.

Nuclear Regulatory Commission ATTN:

Document Control Desk Washington, D.C.

20555 i

Gentlemen:

In the Matter Of

)

Docket No. 50-296 Tennessee Valley Authority

)

BROWNS FERRY NUCLEAR PLANT (BFN) UNIT 3 - TECHNICAL SPECIFICATION (TS) APPROVAL SCHEDULE TO SUPPORT UNIT 3 RESTART I

l As you requested, we are providing in this letter the schedule for approval of TS changes necessary to support Unit 3 restart.

To date, we have submitted to NRC'nine of the fourteen changes.

We expect to submit the remaining five' within the next six months.

These TS changes require NRC

+

approval to support system return to service and other major plant milestones.

The enclosure to this letter provides a schedule for each major plant milestone depicting the date NRC approval is needed for each TS change.. The NRC: approval need date for each change is based on the.affected system's return'to service date and plant milestone date.

The dates provided are the "early-finish" dates from the current Unit 3 restart schedule.

That is, they reflect the most optimistic schedule.

In probabilistic terms, they represent milestone dates with a 10 percent confidence level.that can be achieved.

We note that each of those milestones also has a completion date with a 90 percent confidence level that'is seventeen weeks later than the "carly-finish" date.

t 5

940106d28Y)933223 PDR ADOCK 05000296'-

fy Odf.

J P

PDR 091 a-.

~

I U.S. Nuclear Regulatory. Commission-

}

Page 2

.j DEC 2 31993 e

We will keep you informed'of any.significant changes to.the enclosed schedule through our. regular communication with the Staff's Project Managers _for BFN._ If you have.any questions regarding this submittal; please.callJme.at (205)-.'729-2636'.-

t Sincer ly,

/

d Salas Manager of Site Licensing.

]

l l

Enclosure j

l cc:

See page 3 l

l 5

I I

l l

+

- h i

g l- $

-i f

l E

i i

f l

~i

t 9

l U.S. Nuclear Regulatory Commission Page 3 DEC 2 31993 Enclosure cc (Enclosure):

i i

Mr. R. V. Crlenjak, Project Chief l

U.S. Nuclear Regulatory Commission Region II _

Suite 2900 i

101-Marietta Street,_NW, l

l Atlanta, Georgia. 30323 f

Regional Administrator U.S. Nuclear Regulatory Commission Region II 101 Marietta' Street, NW, Suite 2900 Atlanta, Georgia 30323 NRC Resident Inspector Browns Ferry Nuclear Plant he s 11 b m 35611 j

Mr. D.

C. Trimble, Project Manager U.S. Nuclear Regulatory ~ Commission One White Flint, North 11555 Rockville Pike Rockville, Maiyland 20852 Mr. J.

F. Williams, Project Manager l

U.S. Nuclear Regulatory Commission One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852 l

I q

l l

J i

4.

[

U.S. Nuclear Regulatory Commission-Page 4 DEC 2 31993 TEA:SAW:MTN cc (Enclosure) :

D. L. Brannen, C18 ATH3-BFN q

E.

S. Christenbury, ET 11H-K j

W. R. Cobean, Jr.,.LP 3B-C i

i L. M. Cuoco, BR 4G-C R. M. Eytchison, LP 3B-C

]

R. W. Huston,'Rockville Licensing Office-C

]

T. J.'McGrath, LP 3B-C i

T. W.

Overlid, LP 4E-C R. D. Machon, PSB 1K-BFN

]

D. E. Nunn, LP 3B-C C. M. Root, PAB 1G-BFN

]

j J. R. Rupert, MOD 2C-BFN' B.

S.

Schofield, BR 4G-C l

0. J.

Zeringue, PAB 1E-BFN j

RIMS, CST 13B-C i

ns\\ subs \\U3sched.ts I

.s t

t j

l l

i l

I ENCLOSURE i

TENNESSEE VALLEY AUTHORITY l

BROWNS FERRY NUCLEAR PLANT UNIT,3 i

TECHNICAL SPECIFICATION (TS) APPROVAL SCHEDULE TO SUPPORT UNIT 3 RESTART' 6

l t

b i

e b

i i

f i

?

I i

)

5 l

1 l

j l

l

]

m....

BROWNS FERRY UNIT 3 TECHNICAL SPECIFICATION (TS) APPROVAL SCHEDULE TO SUPPORT UNIT 3 RESTART PAGE 1 - TS CHANGES NEEDED FOR REACTOR PRESSURE VESSEL (RPV) FLOODUP Early 1994 1995 Task Name Firnsh Jan lFeb l Mar l Apr } May !Jun l Jul l Aug } sep l Oct I Nov l Dec Jan l Fee l Mar l Apr l May fJun l Jul l Aug TS420

SUMMARY

6/13/95

~ ~ ~

~~~

^ ~ ~ ~

~

NRC APPROVAL 5/ 3/95 IMPLEMENTATION 6/ 2/95 RX WATER CLEANUP SYSTEM SPOC 6/14/95 0

RPV FLOODUP 6/14/95 0

REMOVE FUEL POOL GATES 6/15/95 0

COMMENCE FUEL LOAD 6/17/95 o

COMMENCE ILRT 7/25/95 o

COMMENCE RDV HYDRO 6/2,95 0

INITIAL CRITICALITY B/15/95 o

Baseline Actual Milestone ll ll

-a I

I

  • ~

=

=

o l

0 9

sa l

m o

9 0

0 0

0 l

0 e

0 m

5 n

99 l

1 as m l

a.

l l

TR ll A

TS ce E

D R S l

3 3 E T

T I

A N G m

U L T O l

R O e

OP M

no P

r ts L

P E l

e a

U U T

O l m.

l M

S F

=+

3OF T

m I

E L NL A

= _

U V

=

UD O l

E M

Y H E

RC R

RS R

4 EL O 9I 9

F A A

V F 1

SOD e

R E N

P D I

l WP E

a A E r

u O) N ea tc t

ST S A

RB( E I m N G m

ON ae

~

I A

TA H

~

I C

l

'~

C

~

F S m -

I T

u C

E l

S E a _

2 P

L G F

C P l

A A I

e N

= _

le in HC s

E aB T

5 5

5 5 4 5

5 5

5 4

5 5

5 5

4 5

5 5

5 5

5 5

5 5

5 5

5 5

5 5

M 9

9 9

9 9, 9

/

/

0,

/8 e

"J T

9 g

9 9

  • 9 9,

9, 9.

/9 9

9, 9 9

9 9

t 7!

7/

9

/

M.

9 9

9 9

9 9

/

y B

7/

7 7

/

5 7

5

/

5 9

9

/

0 G

1 8

7 7

t a

7 7

7

/

/

E 2

9 1

T T

/

r 1

3

/

l 2

  • 2 T

7 T

"2, 2

/

/

7 l

2

/

/

1 1

2

'1 h

4 S

/

4 4

S 8

e

/

4 S

8 8

4 5"

8 8

8

/

B Wi 4

A E

4 A

E 8

8 s

5 5

aE in F

C C

C C

O C

O O

O P

O P

P P

S P

S S

S S

M M

M S

e M

E M

E E

E m

E T

E T

T T

a T

S T

S S

A D

O N

S Y

S Y

Y G

A A

k Y

S Y

S S

C L

O D

a N

S N

L N

S N

G N

G N

O O

L Y

s H

Y Y

L L

O A

Y L

L O

N Y

L L

0 N

Y L

I R

A T

T L

O L

I 1

I O

N Y

L O

P O

L f

I A

I C

R A

A T

O R

A A

T R

R A

T I

S P

E T

V f

A T

C A

A A

T l

U R.

P A

R A

T V

A T

A T

V A

O A

V A

N C

M M

H N

E M

Mi R N

I M

N I

?" W I

M I W I

A O

A M

L F

R A

C A

T A

u T

R M

T T

M T

v T

C M

T J

T T

M T

T T

E E

  • M H

N T

N T

U E

E E

TI v

E C

M M

U O

P E

N E

N E

S F

C C

C u

m E

EL U

0 v

E T

r M E

U B

r M O

S U

P M

O U

M O

A E

M 9

r M Y

E N

N N

F L

S U

E S

"J A

E R

S A

E M

S A

E S

V E

E E

C A

E E

0 S

A E

5 P

V 4

A C

L V

8 L

P D

1 A

F 2

3 C

L D

1 C

L R

O M

M M

L 4

C L

A 3

V A

P 0

1 A

C P

2 A

C L

A M

V A

P X

3 A

3 A

3 A

P H

M M

M M

N MI o

S T

N M

8 3

V F

k I

4 S

T N

I R

S T

N M

R S

N M

R S

N M R

E O

O O

IT T

T T

i T

I T

I R

C C

C N

Il lll1

BROWNS FERRY UNIT 3 TECHNICAL SPECIFICATION (TS) APPROVAL SCHEDULE TO SUPPORT UNIT 3 RESTART PAGE 3 - TS CHANGES NEEDED FOR FUEL LOAD Early 1994 l

1995 l Fee l uar I ace l usy Iwlu l Aug l seal oct l Nov l oec l Jan l ret, l Mar l Ape l uey l Jun } Jue I Aug Task Name Finish Jan

-n.-,---.-,

. m x-


a,,

3 gy NRC APPROVAL 5/ 3/95 IMPLEMENTATION 6/ PN_

NEUTRON MONITORING SYSTEM SPOC 6/.

i o

TS439

SUMMARY

6/13/95 TVA SUBMITTAL 4/20/94 NRC APPROVAL 5/3/95

~

IMPLtEMENTATION 6/ 2/95 NEUTRON MONITORING SYSTEM SPOC 6/14/95 o

TS-337

SUMMARY

6/16/95 NRC APPROVAL 5/17/95

~

(MPLEMENTATION 6/16/?S COMMENCE FUEL LOAD 6/17/95 o

COMMENCE ILRT 7/25/95 o

COMMENCE RPV HYDRO 8/ 2/95 o

INITIAL CRITICAUTY 8/15/95 o

Baseline Actual Milestone ll ll M'

l

BROWNS FERRY UNIT 3 4

TECHNICAL SPECIFICATION (TS) APPROVAL SCHEDULE TO SUPPORT UNIT 3 RESTART PAGE 4 - TS CHANGES NEEDED FOR INTEGRATED LEAK RATE TESTING Early 1994 l

1995 l Feo l Mar I Apr { uay l Jun lM I Auo I so i oct ! Now l DE l Jag lFeb l Mar l Apr l May lJun lM l Aug

  • Task Name Finish Jaa TS-302

SUMMARY

6/ 6/95

~~ ' "

i NRC APPROVAL 4/26/95 IMPLEMENTATION 5/26/95

'~

SAMPUNG SYSTEM SPOC 6/ 7/95 o

TS419

SUMMARY

7/10/95 TVA SUBMITTAL 4/20/94 NRC APPROVAL 5/29/95

~~

IMPLEMENTATlON 6/28/95 RCIC SYSTEM SPOC 7/ 5/95, o

HPCI SYSTEM SPOC 7/11/95 o

TS-308

SUMMARY

7/24/95 NRC APPROVAL 6/12/95 IMPLEMENTATION 7/12/95 MAIN STEAM SYSTEM SPOC 7/25/95 o

TS426

SUMMARY

7/2d/95 NRC APPROVAL 6/12/95 IMPLEMENTATION 7/17q MAIN STEAM SYSTEM SPOC 70 }

o COMMENCE ILRT 7/25/95 o

COMMENCE RPV HYDRO 8/ 2/95 o

l INITIAL CRITICALITY 8/15/95 o

Baseline Actual Milestone l!

ll WO l

A"

-