ML20045E628

From kanterella
Jump to navigation Jump to search
Insp Repts 50-324/93-25 & 50-325/93-25 on 930517-21. Violations Noted.Major Areas Inspected:Miscellaneous Structural Steel Verification Program,Repairs to Unit 1 Drywell Liner Plate
ML20045E628
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 06/14/1993
From: Blake J, Chou R, Lenahan J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20045E566 List:
References
50-324-93-25, 50-325-93-25, NUDOCS 9307020255
Download: ML20045E628 (14)


See also: IR 05000324/1993025

Text

~.

. . .

~

-

,

.

+

.

.

M# N ,fg

4

UGitTED STATES .

..

NUCLEAR REGULATORY COMMISSION

je

..A

'

o

REGION il

h

$

101 MARIETT A STREET, N.W.

.

!o

'*

. ATLANTA, GEORGIA 30323

%. . . pf

'

~ Report Nos.:

50-325/93-25 and 50-324/93-25

Licensee: Carolina Power and Light Company

P. O. Box 1551

Raleigh, NC 27602-

j

Docket Nos.:

50-325 and 50-324

License Nos.: DPR-71 and DPR-62

.

Facility Name: Brunswick 1 and 2

Inspection Conducted: iiay 17-21, 1993

'

~.

[0

'l

3-

Inspect 9r

9.J J/ Lenahan

Date Signed

dff / 3

,

<R

.' Chou

Date Signed

,

Approved by: - /

(c'

V 1

J/A Blake, Chief

Date Slgned

J4terials and Processes Section

/E'ngineering Branch

Division of Reactor Safety

SUMMARY

Scope:

This special, announced inspection was conducted .in the areas of the~

miscellaneous structural steel verification program, repairs to the-Unit I

drywell liner plate, a licensee identified item, and licensee action on

previous inspection findings.

Results:

A violation was identified pertaining to failure of the Nuclear Engineering

Department (NED) to-comply with document control procedures - paragraph 5.c.

A deviation was_ identified regarding failure of the' licensee to implement

corrective actions per their commitment to NRC - paragraph-4.

,

Weaknesses were identified in NED pertaining to failure to conduct self-

assessments, continued use of Draft documents in design, lack of timely

corrective actions, and failure of NED_ personnel to pay attention to~ details -

paragraph 5.c.

9307020255 930618

PDR

ADOCK 05000324

O

PDR

-

..

..

..

-

'

6

REPORT DETAILS

1.

Persons Contacted

Licensee Employees'

  • R. Anderson, Vice-President, Brunswick Nuclear Plant
  • W. Biggs, Supervisor, Corrosion Section, Nuclear Engineering

Department-(NED)

.

  • M. Bradley, Manager, On Site Nuclear Assessment Department, (NAD)
  • M. Brown, Unit 1 Plant Manager
  • J. Casteen, Document Control Supervisor
  • T. Jones, Senior Specialist, Regulatory Compliance

R. Knott, Principal Engineer, (NED)

  • J. Leininger, Onsite Manager, (NED)
  • W. Levis, Manager Regulatory Compliance

C. Lewis, Site Document Control Unit 1 Supervisor

  • G. Miller, Manager, Technical Support
  • C. Schacher, Supervisor, (NAD)

R. Stewart, Supervisor, (NAD)

.

G. Thearling, Senior Specialist, Regulatory Compliance

  • J. Titrington, Unit 2 Operations Manager

_

'

  • S. Vann, NED Project Manager, Miscellaneous Steel Verification ' Program
  • G. Warriner, Manager, Control and Administration
  • C. Warren, Unit 2 Plant Manager
  • K. Williamson, Supervisor,' Onsite NED Mechanical- Electrical Group

Other licensee employees contacted _during this inspection included

engineers, technicians, and administrative personnel.

'

Other Organizations

  • R. Bizzak, Civil / Structural .Consn1 tant, Tennera
  • P. Dadlanni, Site QA Manager, Bechtel
  • R. Gallager, Project Manager, Bechtel

NRC Resident Inspectors

  • R. Prevatte, Senior Resident Inspector

P. Byron, Resident Inspector

  • Attended Exit Interview

2.

Miscellaneous Structural Steel Evaluation Program, Unit 1 (37700)

a.

Background

-

l

Miscellaneous structural steel consists of platforms and-other

beams / columns which provide personnel access and/or support for

piping, electrical raceways and conduits, HVAC ducts,

.

instrumentation, and other equipment not supported from the main-

'

building structures.

Numerous deficiencies in miscellaneous steel

had been identified by either the licensee or NRC, including lack

of design calculations, lack of as-built drawings, missing bolts

,

s

--

x

~+~

aman

a

ws

-

m

4

2

,

and welds, incorrect size members, undersized welds, missing

members, and other construction deficiencies. The licensee

retained Bechtel Power Corporation to perform walkdown

inspections, prepare as-built drawings, and perform design

calculations to qualify the miscellaneous steel.

The Bechtel structural steel verification program, which is called

the Miscellaneous Steel Verification Program (MSVP), is a two

phase project with the purpose of establishing a high confidence

that the miscellaneous steel is adequate for operation. The Phase

I program was a walkdown inspection- to identify and evaluate any

irregularities which could affect the integrity of the structures.

The Phase II program involved obtaining detailed field

measurements to update design documents, prepare as-built

drawings, performance of a detailed structural analysis, and

preparation of a load tracking program to identify the magnitude

and location of loads.

The licensee has completed the Phase II program in the Unit 1

drywell.

The Phase I program was completed for the remaining

miscellaneous steel-in the Unit I reactor building. The results

of inspection of the miscellaneous steel program for Unit 2

restart is summarized in NRC Inspection report numbers 50-325/93-

15 and 50-324/93-15.

b.

Review of Bechtel Structural Steel Verification Program Procedures

!

The inspector examined the Bechtel procedures which control the

Phase I and Phase II walkdown and evaluation of identified

irregularities.

Procedures examined were as follows:

- Procedure No. WDP-001, Phase I Engineering Walkdown

Procedure for Reactor Building Miscellaneous Steel,

Revision 2.

-

Procedure No. WDP-002, Phase II Walkdown Procedure for

Reactor Building Miscellaneous Steel and Drywell Platform

Steel, Revision 4.

Procedure No. EDPI 4.90.03, Hiscellaneous Steel

-

-

Verification Program, Unit 1 Restart, Revision 1.

- Civil Design Criteria MSVP-C-001, Civil Design Criteria

for-Irregularity Evaluation-for the Miscellaneous Steel

Verification Program, Units 1 and 2, Revision 4.

Procedure WDP-001 specifies the criteria for performance of

engineering walkdowns using experienced civil / structural engineers

to identify and classify physical irregularities in the structural

steel.

,

.

.

.

3-

Procedure WDP-002 establishes the methods for conducting and

documenting walkdowns performed to obtain existing as-built

j

information on the structural steel. The existing design drawings

i

are used in the Phase II walkdown and differences between field

conditions and the design drawings are recorded in the Phase II

walkdown documentation.

Irregularities are identified and

recorded during the Phase II walkdowns. The Phase II walkdowns

include weld verification.

Procedure 4.90-03 describes the process by which irregularities

identified during the Phase I and Phase II walkdowns are evaluated

and resolved.

Design Criteria MSVP-C-001 is the basis for

evaluating irregularities in accordance with FSAR criteria, as

supplemented by CP&L submittals to NRC.

c.

Review of Phase I Walkdown Documentation

As stated above, the purpose of the Phase I walkdowns is to

identify and classify physical irregularities in the structural

steel construction.

The Phase I walkdowns are conducted by

experienced civil / structural engineers. The qualifications of the

Phase I walkdown personnel were reviewed during an inspection

documented in NRC Inspection Report numbers 50-325,324/92-23.

In

accordance with Procedure WDP-001, the irregularities are

classified in accordance with Table I.

TABLE 1

Structural

Steel Physical Irregularities

CODE

ACTION

A.

No Irregularities Noted

B.

Irregularities Noted:

No Modification Necessary

C.

Irregularities Noted:

Modification Recommended

D.

Further Evaluation Required

E.

Inaccessible: Observation Not

-Possible (Note Area Hot Viewed In

Remarks)

F.

Unacceptable: Restore to Original

Design Requirements

.

.

.

.

.

.

.

,

4

The procedure also specifies a numerical code, which identifies

the type of irregularity, e.g., weld missing, number 1, bolt

missing, number 4, connection member missing, number 12, etc.

The inspector randomly selected the completed reactor building

Phase I inspection packages listed below, reviewed them for

content and completeness, and reviewed the type and number of

irregularities identified.

Phase I documentation packages

reviewed were as follows:

1-RB-B-El (-) 00-9, P-S/2R-4R

l-RB-B-El (-) 04-1, P-S/2R-4R

l-RB-B-El (-) 04-1, S-T/2R-3R

l-RB-B-El (-) 04-1, S-T/3R-4R

<

l-RB-B-El (-) 07-9, R-T/2R-4R

l-RB-B-El

06-0, P-S/2R-3R

l-RB-B-El

10-6, P-S/2R-4R

l-RB-D-El (-) 04-1, P-S/6R-8R

1-RB-D-El (-) 04-1, S-T/6R-7R

l-RB-D-El (-) 11-4, S-T/5R-6R

l-RB-D-El

10-7, P-S/6R-8R

The inspector concluded that the Phase I walkdown inspection

results were properly documented.

d.

Review of Calculations - Unit 1

During the irregularity evaluation of the MSVP for Unit 2, Bechtel

engineers evaluated each individual irregularity and determined if

the irregularities affected the structural integrity of'the

miscellaneous steel platforms. The final disposition for each

irregularity were either use as is, rework, or modify.

For the

irregularity evaluations for Unit 1, Bechtel engineers summarized

and categorized some of the common irregularities into several

standard calculations based on the Unit 2 experience. The

standard calculations evaluated the common irregularities and set

forth the acceptance criteria.

If-the irregularities were beyond

tne acceptance criteria, additional calculations are required to

evaluate these irregularities.

Bechtel engineers generated 14

standard calculations. The inspectors reviewed 13 of them. One

Unit 2 calculation for clip Angle Evaluation was also reviewed and

this one is included in the table listed below since it will be

used for Unit 1 evaluations. The standard calculations reviewed

-are listed below in Table 2.

-

.

. .

. - -

- .

_ _ _ .

. _ _ _ _ _

._

_

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

.

.

,

l

5

>

Table 2

Standard Calculations for Common Irregularities

Calculation

Revision

Calculation Title

No.

No.

1RB1-1105

2

Guidelines for Screening Unit

1 Irregularities

IRB1-1106

1

Generic Cope Evaluation Based

on Unit 2 Experience

IRB1-1107

1

Generic Beam Setback

Evaluation Based on Unit.2.

Experience

IRB1-1108

1

Generic Saw Overcut Evaluation

Based on Unit 2 Experience

IRB1-1109

1

Generic Minimum Edge Distance

Evaluation Based on Unit 2

Experience

IRB1-1110

0

Generic. Corrosion Evaluation

Based on Unit 2 Experience

IRB1-1111

1

Generic Bolting Evaluation

Based on Unit 2-Experience

IRB1-1112

1

Generic Partial Penetration

Weld Evaluation Based on Unit

2 Experience

IRB1-1113

1

Generic Abandoned Hole

. Evaluation Based on Unit 2

Experience

IRB1-1114

1

Connection Weld Analysis

IRB1-1115

1

Generic Connection Angle

Dimension Evaluation Based on

'

Unit 2 Experience

.

-i

i

._

.

.

.

.

.

6

1RB1-ll24

0

Design Aids for Screening Unit

1 Irregularities

IRB1-1125

0

Generic Operability

2RB2-1220

0

Fabricated Clip Angle

Evaluation by Random Sample

(Unit 2)

The above calculations were reviewed for completeness, accuracy,

adherence to design criteria and procedural requirements, acceptability

of calculation methods with American Institute of Steel Construction

(AISC) code criteria, and good engineering practices.

All the standard

calculations reviewed were determined to be acceptable although the

inspectors found some minor discrepancies which would not affect

operability for restart.

All components categorized as C, D, or E irregularities in the Phase I

walkdowns have been evaluated for plant restart concerns as addressed in

Exhibit A, Plant Restart Evaluation Methodology, using the Civil' Design

Criteria for the MSVP, Project approved generic calculations and

guidelines, design aids, simple computations, the judgement of the

reviewers, and 'the data obtained from the walkdowns. The evaluation of

structural components categorized as C, D, or E were assessed through a .

screening process consisting of an : initial screening,~ Level 1, secondary

screening, Level 2, and final review.

In the Level 1 screening, two experienced structural engineers used the

guidelines of standard calculation IRB1-1105 and screened each component

classified as category C, D, or E for structural acceptability in each

walkdcwn package.

Each component was determined to be one of the

following types:

Type 1: Accept As Is

Type 2:

Restore to Design Requirements

Type 3: Modification Required

Type 4:

Further Evaluation Required

Each component identified as "Further Evaluation Required" (Type 4) from

the initial screening above were evaluated by two engineering

specialists in the secondary screening.

The engineering specialist

evaluated components categorized as "Further Evaluation Required" and

reclassified them as one of the above four types.

If the component

after-re-classification, was still considered to be Type 4, "Further

Evaluation Required", the component was listed-as requiring further

evaluation in an irregularity calculation.

If the component was out of

scope, it was referred to CP&L for disposition. During the screening

and review process, the level 2 screeners performed sample reviews on

level 1 disposition.

Level 2 screeners can over-ride the level 1

disposition. With the same authority, the final reviewer can override

the levels 1 and 2 screeners' disposition. The inspectors also reviewed

the calculations listed in Table 3, below. These calculations were for

.

.

-

,

.

.-

.

,

7

three platforms. The irregularities identified on these platforms were

compared to the irregularities addressed in the generic calculations.

Irregularities which were determined to be non-generic, required further

review.

Table 3

Calculations Reviewed for Individual Platforms

Calculation

Rev. Walkdown

Types of

No.

No.

Package No.

Irreaularities

IRB1-Il62

0

1-RB-D-EL37'-10"

Missing welds

(S-T/6R-8R)

Insufficient welds

1RB1-1088

0

1-RB-C-EL.10'- 0"

No engineering

(CK-L/7R-8R)

drawing for the

platform

1 RIP-1088

0

1-DW-E-EL.17'-10 1/4"

Slip critical

(58 - 81 )

connection

Missing weld

Insufficient welds

.

The above calculations were determined to be acceptable.

The requirements for the Level 1 and 2 screeners are specified in

procedure EDPI-4.90-03. Minimum requirements are.as follows:

Level 1 screening engineers shall be experienced, degreed

.

Civil / Structural Engineers with previous experience in design or

evaluation of structural steel and be approved by the Chief Civil

Engineer.

Level 2 screening engineers, Engineering Specialists, shall

be experienced, degreed Civil / Structural Engineers, with extensive

experience (15 years or more) in the field of design.and analysis of

structures, with emphasis in structural steel, ten years on Nuclear

Power Projects, and a registered Professional Engineer.

The inspector reviewed the resumes of the Level 1 and 2 screeners and

,

verified that the experience and qualifications of these personnel met

the procedure requirements.

Violations or deviations were not identified.

.

.

3.

Repairs to the Unit 1 Drywell Liner

During the inspection documented in NRC Inspection Report numbers

50-325,.324/93-02, the inspector identified a problem with corrosion of

the drywell liner plate at the intersection of the liner with the

elevation 5 concrete floor, around the entire circumference of the

drywell. A violation, item No. 325,324/93-02-01, was identified

-

. _ _

-

.

.

.

,

8

regarding failure of the-licensee to measure and evaluate the corrosion.

After the corrosion problem was identified by the inspector, the

,

licensee performed extensive inspections and repairs of the corrosion in

the Unit 2 drywell . This work was examined by the inspector during the-

inspection documented in NRC Inspection Reports Numbers 50-325,324/93-

02 and 93-15. During the current inspection, the.. inspector reviewed

special procedure OSP-93-010, Revision 2, dated May 3,- 1993, Drywell

Liner Corrosion Examination.

The inspector, accompanied by a licensee engineer, walked down the Unit'

I drywell and examined the liner plate corrosion. The licensee was in

the process of sand blasting the liner to remove the corrosion and

deteriorated coatings. The inspector noted that the corrosion was

concentrated in the expansion joint area, below the' concrete floor

elevation. The licensee had performed measurements of some of the

corrosion area to determine the depth of the corrosion and pitting below

the surface of the steel liner plate.

However, the orientation of the

liner plate and the width af the expansion joint made the cleaning'and

inspection process. difficult.

The inspector met with licensee engineers

and discussed the need to remove some of the concrete floor slab

adjacent to the liner plate and expansion joint to be able to thoroughly

clean the corrosion area and properly inspect the liner plate. This

will also be necessary to make any required weld repairs and for

recoating of the liner plate.

Licensee engineers stated that removal of-

some of the concrete slab would be considered after . sand blasting and

the initial inspections were completed. The repairs to-the Unit 1

,

drywell liner will be inspected in future inspections.

Violations or deviations were not identified.

4.

Licensee Event Report (LER)

(0 pen) LER 2-92-006,: Control Drive System Scram Discharge Volume

Instrument Line Pipe Supports Were Found Missing

The licensee's corrective actions for their LER are summarized in an

attachment to CP&L letter, serial:

BSEP-92-0019, dated September 21,

1992, Subject:

Licensee Event Report 2-92-006.

s

The inspecter examined the licensee's corrective actions for this LER

during inspections documented in NRC Inspection Report numbers 50-325,.

324/93-15 and 93-20. This LER was left open pending NRC review of the

licensee's corrective actions pertaining to procedure revisions. The

inspector verified-that all-hardware-deficiencies had either been

corrected or had been evaluated under the short term structural

integrity program prior to restart of Unit 2.

The licensee committed to

add procedural control enhancements to a procedure which was being

developed to cover the temporary removal of existing equipment

interferences. The licensee committed to have this procedure, number

MAP-004, Modification Work Control Procedure, approved, issued, and in

place by March 31, 1993.

.

..

-

,

-

.

-

.

.

_

9

During the current inspection, the inspector requested a copy of-

procedure MAP-004 for review. The inspector was informed by document

control personnel that procedure MAP-004 had not.yet been issued.

Discussions with Regulatory Compliance personnel disclosed that

procedure MAP-004 will not be issued since it was superseded by

procedure PLP-24. However, the procedural control enhancements for

temporary removal of equipment were not included in procedure PLP-24.

l

'

These enhancements will be included in procedure MAP-005, Application of

Nuclear Plant Modification Program, which is scheduled to be approved-

on/or about May 31, 1993, with an effective date in June, 1993. The

inspector discussed with the licensee the failure to approve, issue and

implement the procedural control enhancements covering temporary removal

of equipment during plant modification projects in accordance with their

commitment to NRC.

The failure to issue a procedure covering their

commitment was identified to the licensee as Deviation items 325,

324/93-25-01, Failure to Implement corrective Action in Accordance with

Commitment to NRC.

5.

Action on Previous Inspection Findings

t

a.

(Closed) Inspection Followup Item 325,324/93-02-02, Corrosion of

Nelson Studs on Embedded Plates

During implementation of Plant Modification 92-092, the licensee

discovered that seven of eight Nelson studs on service water pump

2B pedestal were severely corroded and were no longer-attached to

.i

the embedded plate which the Nelson studs anchored to the

concrete. This problem was documented on Minor Adverse ~ Condition

Report Number 93-065.

Prior to restart of Unit 2, corrective

actions for this problem were examined by the inspector during an

inspection documented in NRC Inspection Report numbers 50-325,

324/93-20.

During the current inspection, the inspector reviewed

documentation pertaining to the licensee's close out of MAC

93-065. This included a summary of the corrective action taken,

the completed minor adverse condition report, and the field

inspection data. The field inspection data included the results

of Ultrasonic Testing (UT) performed on various embedded plates to

determine if the Nelson studs were still attached to the plates.

The embed plates selected for testing were those which showed

indications of possible corrosion which potentially may have

affected the Nelson studs. The ultrasonic test-data indicated

that- the Nelson studs were-still attached-to the-embed plate.

Based on the test data, the licensee concluded that the corrosion

of the Nelson studs identified on the service water pump 28

pedestal was an isolated occurrence. The inspector concurred.

b.

(Closed) Inspection Followup Item 325,324/93-20-01, Revision to

DG 11.20 to Incorporate Transient Loading and Delete Tested

Mechanical Properties

.

,

e-r-

- _ _ _ _ _ _

_ _ _ -

,

.

10

The inspector reviewed Revision 5 of Design Guide (DG) II.20,

Civil / Structural Operability Reviews which was approved on May 11,

1993. The inspector verified that DG 11.20 had been revised to

delete the option of using tested mechanical properties as

allowable stress values when they exceeded code minimum values,

and that applicable transient loads are included in piping

analysis equations. These revisions were in accordance with the

licensee's commitments to NRC contained in their April 19, 1993

letter, Serial: NLS-93-106, Subject:

Response to NRC Questions

from April 1, 1993, Meeting.

c.

(Closed) Unresolved Item 325,324/93-20-03, Questionable Control

for NED Design Procedures

This unresolved item concerned numerous problems identified by the

inspector regarding document control in the onsite Nuclear

Engineering Department. The particular issues identified by the

inspector concerned apparent use of uncontrolled procedures as

references in design calculation, apparent failure to distinguish

controlled documents from uncontrolled documents, and failure to

issue revisions to controlled documents to the Brunswick site TAC

library. During the current inspection, the inspector verified

that these problems were in violation of NED 3.5, Handling of

Controlled Documents. The specific procedural violation involving

four examples were as follows:

1.

The calculations for short term structural. integrity

evaluations of over spanned conduits, which is a

portion of calculation number OSEIS-1005, referenced

Structural Design Guides (SDGs). These SDGs were not

controlled documents, and in fact, there were no

controlled copies of SDGs available onsite.

This was

contrary to the requirements of paragraph 3.5.3.2 of

NED procedure 3.5 which states that uncontrolled

copies of procedures shall not be used when' designing

changes to systems, structures and components.

2.

On April 20, 1993, the inspector determined that

various copies of NED documents, including procedures,

i

SDGs, and Mechanical Design Guides (MDGs) retained by

NED personnel in their work areas and in the NED

l

library were not distinguishable from controlled

copies. This was contrary to the requirement of

paragraph-3.5.3.2 of NED procedures 3.5 which states

that uncontrolled copies of controlled documents be

clearly distinguishable from controlled copies.

3.

On April 20, 1993, the inspector identified various

superseded copies of drawings, procedures, and

specifications which were being retained by NED

personnel in their work areas and in the NED library.

The copies were not marked " Superseded." This was

- _ _ _ _ _ _

,

.

.

.

P

11

contrary to the requirements of paragraph 3.5.3.2. of.

NED procedure 3.5 which states that superseded

.

revisions of controlled documents which are~ retained

by NED personnel for reference must clearly be marked

as " Superseded".

4.

On April- 19, 1993, the inspector identified that

Revision 3 of Design Guide III.16 had not been issued

to the Brunswick site TAC library (NED Control' Copy

No. 367). Discussion with the librarian in the TAC-

library disclosed that for some reason, Revision 3 was-

not sent to the TAC library when it was issued. This.

was contrary to the requirements of Paragraph II.A of.

Attachment 2 of NED procedure 3.5 which states that

NED controlled documents be serialized and issued to

specific individuals.

The procedure requires a

receipt system be utilized to verify receipt .of the

controlled document and each revision thereto by the

person to where the document or revision was issued.

The receipt system had not been utilized to verify

distribution and determine that Revision 3 of DGIII.16

had not been issued to the TAC library.

The above four examples of failure to comply with the requirements

of NED procedure 3.5 were identified to the licensee as a

violation of 10 CFR 50, Appendix B, Criterion ~ V. Unresolved item

325,324/93-20-03 is closed and upgraded to violation item 325,

,

324/93-25-02, Failure to Follow Document Control Procedures in

-

NED.

.

Subsequent to the inspection documented in NRC Inspection Report

numbers 50-325,324/93-20, the licensee initiated an indepth audit

and review of controlled documents in use by the onsite NED group.

A review was also conducted in the corporate NED office. These

reviews disclosed numerous problems with control. of documents

within NED. These included missing copies of controlled-

procedures, out of date copies of vendor drawings in the Brunswick

site library, and extensive use by NED personnel of uncontrolled'

copies within NED of various other types of controlled documents.

The licensee took some.immediate corrective actions to address

these problems; these included:

- Closing of the Brunswick site NED library for a

--detailed' audit of- documents-contained within. This

audit involved-3 to 5 document control personnel

and required more than.one month to complete.

- Training of NED personnel on document control

procedures.

,

- .

.

- - - - - - .

- - - -

- -

. - - . -

-

.

- - -

- - -

- .

.

. -

. . -

.

.

,

12

- Review of controlled documents issued to individuals to

determine _the status of these controlled documents.

Identified deficiencies' were resolved.

- Review of documents held by all NED personnel to

verify that copies in their possession complied -

with document control requirements specified in NED

procedure 3.5

Walkthroughs of work areas by supervisory personnel

-

to ensure document control procedures are being

met.

The inspector concluded that these corrective actions will

contribute to resolution of document control problems within NED.

However, further review is required to determine if other

,

corrective actions are required to resolve the' document control

problems within NED.

In addition to the document control review discussed above, the

licensee's Nuclear Assessment Department (NAD) performed an.

assessment of engineering documentation at the Brunswick site from

April 26-30, 1993.

Their-assessment was initiated because of the

document control problems found by the inspector during inspection'

number 93-20. The inspector discussed the assessment finding with

NAD personnel and reviewed a draft copy of the NAD Assessment

Report. The assessment identified, additional document control

problems similar to those identified by the inspector. However, a

problem was also identified with the licensee's NRCS system which

is discussed below.

The assessment also identified other issues

including failure to pay attention to details, weakness in

procedures used to prepare design change packages, use of " Draft"

documents as references in design calculations, and failure of NED

to perform self assessment. The use of draft 1 documents in NED

has been a continuing problem which was previously identified by-

NRC.

This problem was highlighted to licensee management in the

,

letter dated October 26, 1992, which transmitted NRC' Inspection

'

Report 50-325, 324/92-27 to CP&L.

The particular problem

identified by NAD involved a non-safety related piece of

equipment. This was calculation ODG-0016, Revision 1, for

operable Mod 93-010 which was approved February 25, 1993. The

calculation referenced a Draft of Revision 3 of Desicn Guide DG

VIII.50. However, Revision 3 of DG VIII.50 had not been issued as

j

c

'

-of tiay 21,1993. - A violation was- not-identified by the ' inspector.

regarding this finding since it involved Quality Class B, a non-

,

'

safety related piece of hardware.

Problems have been identified in the NRCS, which is the acronym

i

for the Nuclear Records Control System, during the most recent

l

assessment and during previous NAD assessraents.

The NRCS system

is the system personnel onsite use to verify that the documents

they are using are the most current revisions.

The-licensee's

,

'

,

_

,

.

..

,

13

corrective actions to . resolve problems they self-identified with

the NRCS system will be evaluated as part of the followup to

violation item 325,324/93-25-02.

The failure of NED personnel to identify the problems identified

by the inspector and NAD through self-assessments was identified

to the licensee as a weakness. The requirements for self-

assessments are covered in NED procedure 2.17, Nuclear Engineering

Department Self-Assessments. Other issues identified as

weaknesses are continued use of draft documents when performing

design work, lack of timely corrective actions to respond to NAD

assessment findings and failure of NED personnel to pay attention

to details.

,

6.

Exit Interview

The inspection scope and results were summarized on May 21, 1993 with-

those persons indicated in paragraph 1.

The inspector described the

areas inspected and discussed in detail the inspection results listed

below.

Proprietary information is not contained in this report.

Dissenting comments were not received from the licensee.

Deviation Item 325,324/93-25-01, Failure to Implement Corrective Action

in Accordance with Commitment to NRC.

Violation Item 325,324/93-25-02, Failure to Follow Document Control

Procedures in NED.