ML20029D921

From kanterella
Jump to navigation Jump to search
Responds to NRC Re Violations Noted in Insp Rept 50-382/94-05.Corrective Action:Performed Seismic Evaluation to Determine If Lead Sheets Affected Seismic Integrity of Safety Related Components
ML20029D921
Person / Time
Site: Waterford Entergy icon.png
Issue date: 05/11/1994
From: Burski R
ENTERGY OPERATIONS, INC.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
W3F1-94-0047, W3F1-94-47, NUDOCS 9405130001
Download: ML20029D921 (4)


Text

,._

)-

Entergy Operations,Inc.

- ENTERGY-mmo m u mm 1

T i:-N 739 0774 1

R. F. Durskt Dz. w u m snn

?m e a d,,

{

W3F1-94-0047 A4.05 PR i

1 i

i May 11, 1994 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555

Subject:

Waterford 3 SES

)

Docket No. 50-382 License No. NPF-38 NRC Inspection Report 94-05 Reply to Notice of Violation Gentlemen:

In accordance with 10CFR2.201, Entergy Operations, Inc. hereby submits in, the response to the violation identified in Appendix A of the subject Inspection Report.

If you have any questions concerning these responses, please contact C.J. Thomas at (504) 739-6531.

Very truly yours, l

f N

S ski

)

ir or Nuclear Safety RFB/CJT/tjs Attachment cc:

L.J. Callan (NRC Region IV), D.L. Wigginton (NRC-NRR),

R.B. McGehee, N.S. Reynolds, NRC Resident Inspectors Office (WADM526) 9405130001 940512 0

PDR ADOCK 0500 2

gi -

o

I ATTACHMENT T0 f

W3F1-94-0047 PAGE 1 0F 3 ATTACHMENT 1 ENTERGY OPERATIONS. INC. RESPONSE TO THE VIOLATION IDENTIFIED IN APPENDIX A 0F INSPECTION REPORT 94-05 l

VIOLATION N0. 94-05-01 l

Criterion V of Appendix B to 10 CFR Part 50 requires that activities affecting quality be prescribed by documented instructions or procedures of a type appropriate to the circumstances and that the instructions or procedures include appropriate quantitative or qualitative acceptance criteria for determining that important activities have been satisfactorily accomplished.

l l

Administrative Procedure HP-001-ll4, Revision 4, " Installation of Temporary Lead Shielding," provided instructions for the installation of temporary shielding.

Contrary to the above, on January 26, 1994, Procedure HP-001-ll4 was not appropriate in that the procedure did not include adequate acceptance criteria. As a result, temporary lead shielding structures were found to be contacting safety-related pipe support electrical conduit and a safety-related snubber.

l l

RESPONSE

(1)

Reason for the Violation Entergy Operations, Inc. admits this violation and believes that the l

root cause was an inadequate procedure in that Revision 4 of HP-001-l 114 did not include adequate acceptance criteria.

Revision 4 of the procedure required caution when placing temporary shielding to assure that snubber operation, valve operation, equipment access or i

equipment operability is not interfered with.

However, the procedure did not specifically require that adequate separation be maintained between shielding and safety-related equipment. Additionally, the procedure did not require examinations of installed shielding to l

identify and eliminate interference or contact with plant equipment l

or structures.

l

.~.

ATTACHMENT TO W3F1-94-0047 PAGE 2 0F 3 The temporary shielding structures consisted of scaffold frames supporting lead sheets with grommets. The lead sheets were manufactured by DA Flex and designed to hang from scaffold frames by

'S' shaped hooks. Additionally, Number 9 wire and Ty-raps were used to secure the sheets to prevent interferer.ce with plant equipment or structures.

It should be noted that this was the first time that DA Flex lead sheets were used at Waterford 3.

During construction of the temporary shielding structures, the NRC inspectors noted two conditions.where lead sheets were contacting safety-related equipment. A lead sheet near Component Cooling Water (CCW) Return Header Containment Isolation Valve CC-713 was contacting the electrical conduit for the valve's solenoid. Also noted was a lead sheet contacting High Pressure Safety Injection Line Snubber SIRR-1055.

In both cases, adequate separation was not maintained between lead sheets and safety-related equipment.

If Revision 4 of HP-001-114 had incorporated adequate acceptance criteria, then those conditions may have been prevented.

(2)

Corrective Steos That Have Pqt1 Taken and the Results Achieved Personnel from Design Engineering and Radiation Protection (RP) inspected the temporary shielding structures on January 26, 1994.

In addition to the conditions identified by the NRC inspectors, two lead sheets were identified within I inch of electrical conduit 30715K-SA.

Also, those personnel involved with the shielding installation were informed of the discrepant conditions and of the precautions that need to be taken when installing shielding near safety-related equipment. These actions were completed on the same day the NRC inspectors communicated the event to Waterford 3 personnel.

On January 27, 1994, the discrepant lead sheets were repositioned and secured such that adequate separation was maintained between the sheets and safety-related equipment.

Condition Report (CR)94-067 was written to determine the root cause and necessary corrective actions. As part of the corrective actions for that CR, Design Engineering performed a seismic evaluation to determine if the lead sheets affected the ' seismic integrity of the safety-related components. The evaluation concluded that the conditions would not have prevented the safety-related equipment from performing its safety function, m

w

)

ATTACHMENT TO W3F1-94-0047 PAGE 3 0F 3 l

l (3)

Corrective Steos Which Will Be Taken to Avoid Further Violations 1

Discussions were held with RP personnel to accentuate this event and the need to maintain adequate separation between shielding and l

4 safety-related equipment. Additionally, RP personnel were required to review CR 94-067. The discussions and review were completed by March 29, 1994.

Revision 5 to HP-001-114 was implemented on Marcn 31, 1994.

Revision i

5 incorporates four enhancements that were lacking in Revision 4.

First, Revision 5 specifically addresses the installation of DA Flex lead shielding.

Second, Revision 5 requires that temporary shielding be maintained 1 inch or greater from safety-related equipment.

If 1 inch or greater cannot be maintained, an approved Engineering Evaluation is required. Third, Revision 5 requires that temporary shielding be secured in cases where shielding installations are delayed for extended periods.

Finally, the acceptance criteria were expanded to require that the ALARA Coordinator / Designee perform an inspection of completed shielding installations.

The inspection is conducted to ensure that shielding is secure and maintained 1 inch or greater from safety-related equipment.

If an exception to that distance is identified, then the ALARA Coordinator / Designee must verify that an approved Engineering Evaluation has been completed.

(4)

Date When Full Comaliance Will Be Achieved Full compliance was achieved on March 31, 1994.

,