Provides Update on Progress of Review of Differing Prof Opinion Concerning Fuel Load Readiness & SALP Rept
ML20011F400
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 12/18/1989
From: Murley T
Office of Nuclear Reactor Regulation
To: Taylor J
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO)
Shared Package
ML20011D121 List:
References
NUDOCS 9003050286
Download: ML20011F400 (2)


Text

-l

~

'h~

j" p'

  • g%,

UNITED ST ATEs

~

G /s T.

jfi NUCLEAR REGULATORY COMMISSION-

~y 1

WASHWGT ON, D. C. 20555 O

4 f./ -

t

?%' '

./

Dil 2 d E n U 87 MEMORANDUM FOR: James M. Taylor Executive Director for Operations FRON:

Thomas E. Murley, Director Office of Nuclear Reactor Regulation

SUBJECT:

DIFFERING PROFESSIONAL OPINION CONCERNING COMANCHE PEAK'S-F'll LOAD READINESS AND SALP REPORT

References:

(1) Unsigned Anonymous Memorandum to the Chairmen dtd October 4, 1989 e

(2)= Memo Thomas E. Murley to James M. Taylor, dtd October 10, 1989 (3) Letter Billie Garde to James M. Taylor, dtd November 20, 1989

.c In my October 10, 1989 memorandum (Reference 2) I advised you of mj actions regarding the anonymous memorandum to the Chairman regarding Comanche Peak's fuel load readiness and the SALP Report.

Since that time, you received the November 20 letter from Ms. Billie Garde.

I This is to update you on our pro raised in. references (1) and (3)gress for review of the issues which were Regarding fuel load readiness, the staff is continuing to make orderly progress in evaluating the licensee's readiness. The Operational Readiness Assessment Team (0 RAT) conducted an inspection in October and concluded that the licensee had to complete many open items before a low power license could be granted.

On December 18, 1989, the ORAT Team Leader is going to the site to determine the appropriate time for the ORAT to continue its inspection.

I anticipate-the inspection will likely resume in mid-January.

The DP0 Panel has met on three occasions to monitor the progress of the various activities to review and resolve the SALP issue. The Panel expects to utilize-the input from (1) B111 Travers' and Ralph Architzel's independent review of the draft and final SALP reports, (2) discussions with the SALP Board Chainnan, A/D for Comanche Peak Inspection Programs, and lead operations inspector and lead construction inspector at Comanche Peak, (3) surveys of the inspectors and consultants associated with Comanche Peak and (4) an analysis of references (1) and (3)-to arrive at a recommendation to me.

I expect to provide you with a final report by January 26, 1990.

The-details of the schedule follow:

December 20, 1989 Inspector / Consultant Survey completed and provided to DP0 Panel Q30502es900229

y ADOCK 03 coo 443 g;

o 4

Pro gl

F James M. Taylor 2-r December 22, 1989 Travers /Architzel report to Jim Sniezek completed and provided to DP0 Panel January 4, 1990 DP0 Panel meets w

.h sal.P Board Chairman, A/D for Com6nche Peak 4 'spection Programs, and lead inspectors January 17, 1990 DP0 Panel provides report and recommendations to Director NRR J6nuary 26,1990 Report to EDO

-If you have any questions, do not hesitate to contact Jim Sniezek or me.

, v.. > H m;.i ty f ;>raev Thomas E. Murley, Director Office of Nuclear Reactor Regulation Distribution:

TEMurley JHSnierek Central file

)FC - lNR IDDI

N hDs J

. K.......:............:............:............:............:.........

IM4E :JHSnierek

E surley

)ATEz:12/15/89

12/

89 OFFICIAL RECORD COPY