Forwards IE Insp Repts 50-518/81-08,50-519/81-08, 50-520/81-08 & 50-521/81-08 on 810512-15 & Notice of Violation
ML20009G766
Person / Time
Site: Hartsville  Tennessee Valley Authority icon.png
Issue date: 06/04/1981
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parris H
TENNESSEE VALLEY AUTHORITY
Shared Package
ML20009G748 List:
References
NUDOCS 8108040638
Download: ML20009G766 (2)


See also: IR 05000518/1981008

Text

l

t

' -j -

p*"%g

OFFICIAL COPY

-

c

UNITED STATES

+!"',

NUCLEAR REGULATORY COMMISSION

Y

"g

g

- -

.c

REGION 11

  • [

o

101 MARIETTA ST., N.W.. SUITE 3100

,

g

ATLANTA, G EORGIA 30303

~

Jun 0 41981

Tennessee Valley Authority

ATTN: Mr. H. G. Parris

Manager of Power

500A Chestnut Street Tower II

Chattanooga, TN 37401

I

Gentlemen:

Subject: Report Nos. 50-518/81-08, 50-519/81-08, 50-520/81-08 & 50-521/81-08

This refers to the routine inspection conducted by Mr. J. R. Harris of this

)

office on May 12-15, 1981, of activities authorized by NRC Construction Permit

Nos. CPPR-150, CPPR-151, CPPR-152, and CPPR-153 for the Hartsville facility. Our

preliminary findings were discussed with Mr. R. T. Hathcote, Project Manager, at

the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report.

Within these arcas, the inspection consisted of

selective examinatior.s of procedures and representative records, interviews with

personnel, and observations by the inspector.

During the inspection, it was found that certain activities under your license

appear to violate NRC requirements.

This item and references to pertinent

requirements are listed in the Notice of Violation enclosed herewith as Appen-

dix A.

Elements to be included in your response are delineated in Appendix A.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this

letter and the enclosed report will be placed in the NRC's Public Document Room.

If the report contains any information that you believe to be exempt from disclo-

sure under 10 CFR 9.5(a)(4), it is necesst.ry that you: (a) notify this office by

telephone within ten days from the date of this letter of your intention to file

a request for withholding; and (b) submit within twenty-five days from the date

of this letter . written application to this office to withhold such information.

If your receipt of this letter has been delayed such that less than seven days

are available for your review, please notify this office promptly so that a new

due date may be established. Consistent with section 2.790(b)(1), such applica-

tion must be accompanied by an affidavit executed by the owner of the information

which identifies the document or part thereof sought to be withheld, and a full

statement of the reasons on the basis of which it is claimed that the information

should be withheld from public disclosure.

This section further requires the

statement to address with speci ficity the considerations listed in 10 CFR 2.790(b)(4). The information sought to be withheld shall be incorporated as far

as possible into a separate part of the affidavit.

If we do not hear from you in

this regard within the specified periods noted above, the report will be placed

in the Public Document Room.

8108040630

0

PDR ADOCK 0

PDR

G

-.

-

. - . -_

. , ~

.

- -

. - .

9

e'

Tennessee Valley Authority

2

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

Sincerely,

'

,ff.t:.

R

C.

sis, Acting Director

Division of Resident and

Reactor Project Inspection

Enclosures:

1.

Appendix A, Notice of Violation

2.

Inspection Report Nos. 50-518/81-08,

50-519/81-08, 50-520/81-08 and 50-521/81-08

cc w/ encl:

H. J. Green, Division Director

R. T. Hathcote, Project Manager

J. F. Cox, Supervisor, Nuclear

Licensing Section

J. E. Wills, Project Engineer

H. N. Culver, Chief

Nuclear Safety Review Staff