GNF-A Written Follow-up Report - NPDES Bypass
ML19312B487
Person / Time
Site: 07001113
Issue date: 11/08/2019
From: Murray S
Global Nuclear Fuel
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards
References
54267, M190200
Download: ML19312B487 (3)


Text

GNii=

Global Nuclear Fuel M190200 November 8, 2019 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555-0001

Subject:

GNF-A Written Follow-up Report - NPDES Bypass

References:

1) NRC License SNM-1097, Docket 70-1113
2) GNF-A Event Report 54267, 9/11/2019

Dear Sir or Madam:

Global Nuclear Fuel Scott P. Murray Manager, Facility Licensing 3901 Castle Hayne Road P.O. Box 780 Wilmington, NC 28402 USA T (910) 819-5950 Scott.mu rray@ge.com In accordance with 10 CFR 70.74(b), Global Nuclear Fuel-Americas, LLC (GNF-A) hereby submits a written follow-up report for Event Notification 54267 that was provided to NRC on September 11, 2019 (Reference 2).

Event54267 As discussed in the initial event report, GNF-A reported a National Pollutant Discharge Elimination System (NPDES) permit nonconformance. Consistent with 10 CFR 70, Appendix A(c), a concurrent report was provided to NRC and is included as Attachment 1 to this letter.

Additional information is provided as follows:

Event Details and Safety Significance On September 3, 2019, in preparation for Hurricane Dorian, the Waste Treatment Operator in Responsible Charge (ORC) decided to lower the level in the Waste Treatment Central Lagoon by treating and transferring water to the Process Lagoons. Piping was damaged and not noticed during a walkdown prior to pumping from Waste treatment to the Process Lagoons. This resulted in water being discharged to the soil. After discussing the event with State authorities, due to the potential severe weather impacts, the North Carolina Division of Water Resources (NC DWR) 5-day bypass report was allowed to be submitted on September 11, 2019.

Immediate Corrective Actions Taken Upon discovery, the water was contained and sampled. Sample results were all below regulatory limits and the pipe was repaired. The NPDES permit requires a report to NC DWR.

This report was made at 10:01 am on September 11, 2019. Because NC DWR was notified, a concurrent notification to the NRC Operations Center was made per 1 O CFR 70, Appendix A(c)..

US NRC M190200 November 8, 2019 Page 2 Probable Cause of Event The cause of the cut to the lay flat hose is unknown but suspected to be lawn mowing equipment. The hose was not marked for protection in its routing along the ground. The line is typically not pressurized so any damage was not immediately noticeable.

Short Term Corrective Actions

1) The water was contained and sampled. Sample results were all below regulatory limits.

Completed September 3, 2019

2) Repaired cut bypass hose Completed September 3, 2019 Longer Term Corrective Action
1) Install and commission a new permanent line and discontinue use and dispose of the temporary bypass hose Scheduled completion: January 17, 2020.

If you have any questions regarding this matter, please contact me at (910) 819-5950.

Sincerely,

!lu~lfbw~

Facility Licensing ty' Attachments: 1) Event 54267 Notification Description cc: NRC Region II Administrator, Atlanta, GA M. Ruffin, NRC RII Atlanta. GA M. Bartlett, NRC NMSS, Washington, DC SPM 19-030

US NRC M190200 November 8, 2019 Page 3 Event 54267 Notification Description In preparation for Hurricane Dorian, the Waste Treatment Operator in Responsible Charge (ORC) decided to lower the level in the Waste Treatment Central Lagoon by treating and transferring to Process Lagoons. Piping was damaged and not noticed during a walkdown prior to pumping from waste treatment to the process lagoons. This resulted in water being discharged to the soil.

Upon discovery, the water was contained and sampled. Sample results were all below regulatory limits. The pipe was repaired. The NPDES permit requires a report to North Carolina Division of Water Resources (NC DWR). This report was made at 10:01 am on 9/11/2019.

Because NC DWR was notified, a concurrent notification to the NRC Operations Center is being made per 10 CFR 70, Appendix A(c).

Phillip Ollis, Facility Licensing 14:04 9/11/2019