Text
8 005239 EFF EasTON EENsON COMPANY a:Ns=A6 orriCe5 soo movtSTON afma:T S O S t o N. M ASSACNdSETTS o3199 G. CAnk ANOOGNeNg SuptelNTENOGNT NUCL&Am OpSAA?80NS OtramTesENT May 14, 1980 EECo Letter #80-85
- 'r. Thomas A.
Ippolito, Chief Operating Reactors Branch #3 Division of Operating Reactors Of fice of Nuclear Reactor Regulation U.S. ?aclesr Regulatory Commission
'asshington, DC 20555 License No. DPR-35 Document No. 50-293 COMPLETl0N DATES OF FlRE PROTECTION MODIFICATIONS Ref erences:
(a) NRC letter (Elsenhut to Andognin!) dated August 28, 1979.
(b)
Safety Evaluation Report to Amendment No. 35 to Facility Operating License No. DPR-35.
(c) SECo letter (Andognini to Ippolito) dated 11/6/79, File Reference #79-230.
(d) BECo letter (Andognini te lppoltto) dated 3/30/79, File Reference #79-61.
(e)
EECo Letter (AndogcIni to Ippolito) dated 2/6/79, File Reference #79-130 (f)
EECo letter (Andognini to Ippolito) dated 2/29/80, File Reference #80-38.
(g) Yankee Atomic Electric Company letter (Moody to Ziemann) dated 10/3/79, File Reference WYR 79-113, Docket No. 50-29.
Dear Sir:
e in acccrdance with the requirements of Reference (a) and the implementation schedule in Table 3.1 (Imclementation Date for Licensee Procosed Modifications) of Reference (b), we wish to document the status and/or completion of the following fire protection ~odifications at Pilgrim Station, Unit #1:
1 l
l p._
e SQ] TON ECCCN CZMPANY TABLE 3.1 Comoletion Date item Subiect SER/NRC Revised Actual Excocted 3.1.1 Fire Detection System 8/15/80 3.1.2 Water Suppression Systems and Ecot.
II/l/7s 6/1/80 7/01/80 3.1.3 Gas Fire Suporession System (Halon) 5/1/79 8/l/79 8/01/79 3.1.7 Fire Doors 8/l/79 4/1/80 3/15/80 3.1.17 Communication Systems 3/1/80 3/7/80 3/20/80 3.1.18 Alternate Shutdown Capability 10/1/79 6/1/80 6/01/80 Additional Information concerning specific items is as follows:
Item 3.1.1 - Fire Detection Systems
- Installation of the fire aetection systems ras postponed in anticipation of a response from the staff on the results of in-situ smoke detector tests which were conducted by NUTEC for BECo and four other electric utilities. The test results were submitted for staf f review by Reference (g).
Subsequently, we informed you in Reference (f) that further action on this task was con-tingent upon a response from the staff. However, installation could not be delayed indefinitely if this task was to be completed by the final commit-ment date of 10/1/80. Accordingly, the decision was made to proceed with the installation based on available fire protection code requirements and engineering judgment.
The fire detection systems will be installed in two phases. Phase I will involve installing 142 detectors (109 photo-electric and 33 Ionization types) in the areas stipulated in item 3.1.1 of the SER except for the Reactor Building at El. 235-0" and in the Reactor Building quadrants.
Installation of approximately 170 detectors (89 photo-electric and 81 Ionization types) in these areas will be accomplished as Phase 11.
Work for Phase I is approximately ten percent complete and the projected completion date is 6/15/80. Construction for Phase 11 will commence on 6/7/80 and the projected completion date is 8/15/80.
Item 3.1.2 - Water Suopression Systems and Eculoment We notified you in Reference (d) that our anticipated completion date of this
_ item would be 6/l/80. After re-evaluating our implementation schedule, we voluntarily advanced the completion date of this item to 3/31/80 and informed j
you of this fact in Reference (e).
Unfortunately, a variety of problems I
(scarcity.of manpower, turnover of manoower, material shortages, etc.) were encountered which resulted in slippage of the com.Djetion date. We now anti-cipate that all work associated with this task will be completed by 7/1/80.
-l
$0; TON Ell!CN COMPANY ltem 3.1.2 - Water Suppression Systems and Equiement (centinued)
At the present time, ten of the thirteen additional hose stations teve been Installed. The remaining three will be installed by 5/31/80. Thren of the six additional sprinklers have been Installed and the percentage of completed work on the remaining three varies f rom 5 to 80 percer,t. All of the sprinklers, including extension of the interior fire main loop, will be functional by 5/31/80. Delivery of some fire orotection equipment, such as ultra-violet smoke detectors for the Diesel Generator Rooms, cannot be accelerated any sooner than 6/15/80 Item 3.1.3 - Gas Fire Suppression System (Halon)
We informed you in Reference (f) that a discharge test of tha Halon system would be conducted during March 1980 to demonstrate system operability and effectiveness. This test was successfully conducted on 5/2/80.
Item 3.1.7 - Fire Doors We informed you in Reference (f) that the anticipated completion date for this item was 3/7/80; the actual completion date was 3/20/80.
Item 3.1.18 - Alternate Shutdown Caoability We anticipate that the Alternate Shutdown System, in the event of the loss of the Cable Spreading Rcom, will be functional pi ior to plant start-up.
{
{
if you have any questions concerning the information presented herein, please do not hesitate to call us.