Forwards Final Deficiency Rept Re Vertical Fire Dampers Furnished by Ruskin Mfg Co
ML19296C306
Person / Time
Site: Wolf Creek, Callaway  Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 02/15/1980
From: Petrick N
STANDARDIZED NUCLEAR UNIT POWER PLANT SYSTEM
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML19296C308 List:
References
SLNRC-80-8, NUDOCS 8002250552
Download: ML19296C306 (1)


Text

.

SNUPPS Standardized Nuclear Urut Power Plant Systern 5 Choke Cherry Road Nicholas A. Petrick Rockville, Maryland 20850 Executive Director (301) 869 8010 February 15, 1980 SLNRC 80- 8 FILE: 0491.10.2/M-627B SUBJ:

Ruskin Manufacturing Co. Fire Dampers: SNUPPS Units 1 (Wolf Creek) and 2 (Callaway 1)

Mr. Boyce Grier Director, Region I Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, Pennsylvania 19406

Reference:

STN 50-482 STN 50-483 STN 50-486

Dear Mr. Grier:

On January 18, 1980, the Nuclear Regulatory Comission IE Region I was in-formed by SNUPPS of deficiencies in vertical fire dampers furnished by Ruskin Manufacturing Company to Callaway and Wolf Creek job sites. These deficien-cies were reported by telecon to Mr. Wm. Bateman of Region I pursuant to re-quirements of 10CFR50.55(e). These deficiencies are considered to be generic in nature and are judged to be applicable to all SNUPPS units.

Enclosed with this letter is a report of the defective fire dampers. This report summarizes the safety implications associated with these items, pro-vides a brief chronology of events related thereto, and indicates follow up corrective actions taken and/or planned. All fire damper units, including those on site as well as those yet to ho delivered, will be modified as indi-cated in the enclosed report and oper

, ally cycled prior to or during in-stallation.

In view of the generic r of these deficiencies the vendor, Ruskin Manufacturing Company, has bee

,ised of the need for notifying other nuclear power plant facilities, as a: apriate, and the need for follow up modification. We understand that Russin has also independently notified the NRC of this matter.

Very truly yours,

(".h-<\\C'

%/9 Nicholas A. Petrick g

SJS:dck

Enclosure:

Final Report on Vertical Fire Dampers

///

cc: Mr. James A. Keppler, Director, Region III, USNRC

\\ r KTrl Seyfrit, Director, Region IV, USNRC Mr M

Victor Stello, Jr., Director, Office of Inspection and Enforcement, USNRC, Washington, D.C.

8002250 552