| From: | Long F NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | John Miller GEORGIA POWER CO. |
| Shared Package | |
| ML19289D017 | List: |
| References | |
| NUDOCS 7901290124 | |
| Download: ML19289D024 (2) | |
See also: IR 05000366/1978044
Text
'
,
-
.
g>* 884
UNITED STATES
9
,
jo
NUCLEAR REGULATORY COMMISSION
g
o
REGloN ll
.g ,
$
101 MARIETTA STREET. N.W.
0
M
.'#
ATLANTA, GEORGIA 3o303
%*****/
DEC 8
1978
In Reply Refer To:
RII:HDJ
50-366/78-44
Georgia Power Company
-
Attn: Mr. J. H. Miller, Jr.
Executive Vice President
270 Peachtree Street, N. W.
Atlanta, Georgia
30303
Gentlemen:
This refers to the inspection conducted by Mr. H. D. Jenkins and ot' cts of
this office on October 23-27, 1978, of activities authorized by NRC >perating
License No. NPF-5 for the Hatch Nuclear Plant Unit No. 2, Baxley, Georgia,
and Georgia Power Company, Atlanta, Georgia and to the discussion of our
findings held with Mr. M. Manry on site and Mr. R. W. Staffa at the Corporate
Office at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report. Within these areas, the inspection consisted
of selective examinations of procedures and representative records, inter-
views with personnel, and observations by the inspector.
Thirteen new unresolved items resulted from this inspection and are discussed
in the enclosed report. These items will be examined during subsequent
inspections.
During the inspection, it was found that certain activities under your
license appear to be in noncompliance with NRC requirements. These items
and references to pertinent requirements are listed in the Notice of Viola-
tion enclosed herewith as Appendix A.
This notice is sent to you pursuant
to the provisions of Section 2.201 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations.
Section 2.201 requires you to
submit to this office, within 20 days of your receipt of this notice, a
written statement or explanation in reply including: (1) corrective steps
which have been taken by you and the results achieved; (2) corrective steps
which will be taken to avoid further noncompliance; and (3) the date when
full compliance will be achieved.
With respect to Item A in Appendix A, your immediate corrective actions
were completed and verified by our inspector prior to completion of the
inspection.
Therefore, your response for this item need only address
action and schedule to prevent recurrence.
790129ofp
.
.
..
-
.
Georgia Power Company
-2-
g
g7g
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Room. If this
report contains any information that you (or your contractor) believe to be
proprietary, it is necessary that you make a written application within 20
days to this office to withhold such information from public disclosure.
Any such application must include a full statement of the reasons on the
basis of which it is claimed that the information is proprietary, and should
be prepared so that proprietary information identified in the application is
contained in a separate part of the document. If we do not hear from you in
this regard within the specified period, the report will be placed in the
Public Document Room.
Should you have any questions concercing this letter, we will be glad to dis-
cuss them with you.
Sincerely,
c-
-
-_
N-
F. J. Long, Chie
Reactor Operations and
Nuclear Support Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Inspection Report No. 50-366/78-44
cc w/ enc 1:
Mr. M. Manry, Plant Manager
Plant E. I. Hatch
P. O. Box 442