I
p ggg.
UNITED STATES
o
NUCLEAR REGULATORY COMMISSION
' ' ,
!T( , [ t,
REGION I
i
sai ,AnnAvcNuc
s*
Ai
f
KING OF PRUS$1 A, PENNSYLVANIA f $406
Q&]
.....
Docket Nos. 50-443
g)V05 M
50-444
Public Service Company of New Hampshire
ATTN: Mr. W. C. Tallman
President
1000 Elm Street
Manchester, New Hampshire 03105
Centlemen:
Subject: Combined Inspection 50-443/79-08 and 50-444/79-08
This refers to the inspection condu:ted by Mr. J. MaWa of this office on
September 4-7, 1979 at the Seabrook Station, Units 1 and 2, Seabrook, New Hampshire,
and the Yankee Atomic Electric Cor.pany office at Westborough, Massachusetts of
activities authorized by NRC License Nos. CPPR-135 and CPPR-136 and to the
discussions of our findings held by Mr. Mattia with Mr. B. Beckley and Mr. W.
Miller of your staff at the conclusion of the inspection.
Areas examined during this inspection are described in the Office of Inspection
and Enforcement Inspection Report which is enclosed with this letter.
Within
these areas, the inspection consisted of selective examinations of procedures
and representative records, interviews with personnel, and observations by the
inspector.
Based on the results of this inspection, it appears that certain of your activi-
ties were not conducted in full compliance with NRC requirements, as set forth
in the Notice of Violation, enclosed herewith as Appendix A.
These items of
noncompliance have been categorized into the levels as described in our corres-
pondence to you dated December 31, 1974. This notice is sent to you pursuant to
the provisions of Section 2.201 of the NRC's " Rules of Practice," Part 2, Title
10, Code of Federal Regulations.
Section 2.2C1 requires you to submit to this
office, within thirty (30) days of your receipt of this notice, a written state-
ment or explanation in reply including:
(1) corrective steps which have been
taken by you and the results achieved; (2) corrective steps which will be taken
to avoid further items of noncompliance; and (3) the date when full compliance
will be achieved.
In addition to the need for corrective action regarding these
specific items of noncompliance, we are concerned about the implementation of
your quality assurance program that permitted them to occur.
Consequently, in
your reply, you should describe in particular, those actions taken or planned to
improve the effectiveness of your quality assurance program.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title
10, Code of Federal Regulations, a copy of this letter and the enclosures will
be placed in the NRC's Public Document Room.
If this report contains any infor-
mation that you (or your contractor) believe to be proprietary, it is necessary
that you make a written application within 20 days to this office to withhold
8 002 M
.
.
Public Service Company of
2
such information from public disclosure. Any such application must be accompanied
by an affidavit executed by the owner of the information, which identifies the
document or part sought to be withheld, and which contains a statement of reasons
which addresses with specificity the items which will be considered by the
Comission as listed ir subparagraph (b) (4) of Section 2.790.
The information
sought to be withheld shall be incorporated as far as possible into a separate
part of the affidavit.
If we do not hear from you in this regard within the
specified period, the traort will be placed in the Public Document Room.
Should you have any questions concerning this inspection, we will be pleased to
discuss then with you.
Sincerely,
/
f
w
Ro ert T. Carlson, Chief
Reactor Construction and Engineering
Support Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Office of Inspection and Enforcement Combined Inspection
Report Numbers 50-443/79-08 and 50-444/79-08