IR 05000254/2019011

From kanterella
(Redirected from ML19140A084)
Jump to navigation Jump to search
NRC Temporary Instruction 2515/191 and 2515/193 Inspection Report 05000254/2019011 and 05000265/2019011
ML19140A084
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 05/17/2019
From: Ann Marie Stone
NRC/RGN-III/DRP/TSS
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
IR 2019011
Download: ML19140A084 (12)


Text

May 17, 2019 Mr. Bryan Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2NRC TEMPORARY INSTRUCTION 2515/191, MITIGATION STRATEGIES, SPENT FUEL POOL INSTRUMENTATION AND EMERGENCY PREPAREDNESS AND TEMPORARY INSTRUCTION 2515/193, IMPLEMENTATION OF RELIABLE HARDENED CONTAINMENT VENTS INSPECTION REPORT 05000254/2019011 AND 05000265/2019011

Dear Mr. Hanson:

On April 26, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Quad Cities Nuclear Power Station, Units 1 and 2 and discussed the results of this inspection with Mr. K. Ohr and other members of your staff. The results of this inspection are documented in the enclosed report.

The NRC inspectors did not identify any finding or violation of more than minor significance.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Ann Marie J. Stone, Team Leader Technical Support Staff Division of Reactor Projects

Docket Nos.: 05000254; 05000265 License Nos.: DPR-29; DPR-30

Enclosure:

IR 05000254/2019011; 05000265/2019011

Inspection Report

Docket Numbers:

05000254 and 05000265

License Numbers:

DPR-29 and DPR-30

Report Numbers:

05000254/2019011 and 05000265/2019011

Enterprise Identifier: I-2019-011-0031

Licensee:

Exelon Generation Company, LLC

Facility:

Quad Cities Nuclear Power Station, Units 1 and 2

Location:

Cordova, IL

Inspection Dates:

April 22, 2019 to April 26, 2019

Inspectors:

J. Benjamin, Senior Reactor Inspector

J. Gilliam, Reactor Inspector

G. O'Dwyer, Reactor Engineer

S. Sheldon, Project Engineer

D. Tesar, Resident Inspector

Approved By:

Ann Marie J. Stone, Team Leader

Technical Support Staff

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Temporary Instruction 2515/191, Mitigation Strategies, Spent Fuel Pool Instrumentation and Emergency Preparedness and Temporary Instruction 2515/193,

Implementation of Reliable Hardened Containment Vents inspection at Quad Cities Nuclear Power Station, Units 1 and 2 in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. Findings and violations being considered in the NRCs assessment are summarized in the table below.

List of Findings and Violations

No findings or violations were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

2515/191 - Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012

The inspectors verified plans for complying with NRC Orders EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML12056A045) and EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (ML12054A679) are in place and are being implemented by the licensee. Additionally, the inspection verified implementation of staffing and communications information provided in response to the March 12, 2012, request for information letter (ML12053A340) and multiunit dose assessment information provided per COMSECY-13-0010, Schedule and Plans for Tier 2 Order on Emergency Preparedness for Japan Lessons Learned, dated March 27, 2013 (ML12339A262).

Inspection of Licensee Responses (3 Samples)

(1) Based on samples selected for review, the inspectors verified that the licensee satisfactorily implemented appropriate elements of the Diverse and Flexible Coping Strategies (FLEX) as described in the plant specific submittals and the associated safety evaluation (ML18333A016) and determined that the licensee is in compliance with NRC Order EA-12-049. The inspectors verified the licensee satisfactorily:
  • developed and issued FLEX Support Guidelines (FSGs) to implement the FLEX strategies for postulated external events;
  • integrated their FSGs into their existing plant procedures such that entry into and departure from the FSGs were clear when using existing plant procedures;
  • protected FLEX equipment from site-specific hazards;
  • developed and implemented adequate testing and maintenance of FLEX equipment to ensure their availability and capability;
  • trained their staff to assure personnel proficiency in the mitigation of beyond-design basis events; and
  • developed the means to ensure the necessary off-site FLEX equipment would be available from off-site locations.
(2) Based on samples selected for review, the inspectors verified that the licensee satisfactorily implemented appropriate elements of the FLEX strategy as described in the plant specific submittals and the associated safety evaluation and determined that the licensee is in compliance with NRC Order NRC Order EA-12-051. The inspectors verified the licensee satisfactorily:
  • installed the spent fuel pool (SFP) instrumentation sensors, cabling and power supplies to provide physical and electrical separation as described in the plant specific submittals and safety evaluation;
  • installed the SFP instrumentation display in the location, environmental conditions and accessibility as described in the plant specific submittals;
  • trained their staff to assure personnel proficiency with the maintenance, testing, and use of the SFP instrumentation; and
  • developed and issued procedures for maintenance, testing and use of the reliable SFP instrumentation.
(3) The inspectors reviewed information provided in the licensees multi-unit dose submittal and in response to the NRCs March 12, 2012, request for information letter, and verified that the licensee satisfactorily implemented enhancements pertaining to Near-Term Task Force (NTTF) Recommendation 9.3 response to a large scale natural emergency event that results in an extended loss of all ac power to all site units and impedes access to the site. The inspectors verified the following:
  • the licensee satisfactorily implemented required staffing changes to support a multi-unit extended loss of alternating current
(ac) power (ELAP) scenario;
  • the licensee implemented multi-unit dose assessment capabilities (including releases from spent fuel pools) using the licensees site-specific dose assessment software and approach.

2515/193 - Inspection of the Implementation of EA-13-109: Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions

The inspectors verified plans for complying with NRC Order EA-13-109, Order Modifying Licenses with regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions, (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13143A321) are in place and are being implemented by the licensee.

Inspection of the Implementation of EA-13-109 (1 Sample)

Based on samples selected for review, the inspectors verified that the licensee satisfactorily implemented appropriate elements of the reliable hardened containment wetwell vent as described in the plant specific submittals and the associated safety evaluation (ADAMS Accession No. ML18348B251) and determined that the licensee is in compliance with NRC Order EA-13-109 Phase 1, Reliable, Severe Accident Capable Wetwell Venting System.

The inspectors verified that the licensee satisfactorily:

  • Installed the hardened containment vent system (HCVS) to meet the performance objectives outlined in Section A.1.1 of Attachment 2 to the Order EA-13-109;
  • Installed the HCVS system with the design features specified in Section A.1.2 of 2 to the Order EA-13-109;
  • Designed the HCVS to meet the quality standards described in Section A.2 of 2 to the Order EA-13-109;
  • Developed and implemented adequate maintenance and testing of HCVS equipment to ensure their availability and capability;
  • Developed and issued procedures to safely operate the HCVS using normal power supplies, during an ELAP, and during a postulated severe accident scenario, and integrated the procedures into existing plant procedures and,
  • Trained their staff to assure personnel can proficiently operate the HCVS.

Based on samples selected for review, the inspectors verified the licensee satisfactorily implemented appropriate elements of the reliable wetwell venting strategy as described in the plant specific submittals and the associated safety evaluation and determined the licensee is in compliance with NRC Order EA-13-109 Phase 2, Reliable, Severe Accident Capable Drywell (or alternative strategy) Venting System. The inspectors verified the licensee satisfactorily developed a strategy making it unlikely that the licensee would need to vent from the containment drywell that included the following:

  • Implemented the severe accident water addition (SAWA) and severe accident water management (SAWM) systems as defined and fulfilled functional requirements for installed and portable equipment;
  • Installed and/or identified the previously-installed instrumentation necessary to implement SAWM;
  • Developed and implemented adequate maintenance and testing of SAWA/SAWM equipment to ensure availability and capability;
  • Developed and issued procedures to safely operate the SAWA/SAWM during an ELAP and during postulated severe accident scenario, and integrated their procedures into their existing plant procedures such that entry into and exiting from the procedures are clear when using existing plant procedures; and
  • Trained their staff to assure personnel can proficiently operate the HCVS during an ELAP and accident scenario.

The inspectors verified noncompliances with requirements, and standards identified during the inspection were entered into the licensee's corrective action program as appropriate.

The corrective action program documents generated as a result of the inspection are listed in the Documents Reviewed section of this inspection report.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2515/191

Corrective Action

Documents

2474611-02

QDC-0000-5-2153 Impact on Robust FLEX Bldg Roll-Up Door

2/31/2015

04098335

Workorder to Set SAWA Flow Meter Parameter

01/29/2018

04137905

PM's for FLEX/SAWA Installed Valves

05/15/2018

224363

Local Intense Precipitation Response Procedure Clarification

2/28/2018

240219

EOID: SAWA Flow Meter Needs Troubleshooting/Calibration

04/16/2019

240525

FLEX SAWA Flow Meter Pushbutton Broken

04/16/2019

Corrective Action

Documents

Resulting from

Inspection

202046

Recommend Installing Jack Stands on Flex Diesel Generators

2/11/2018

242835

NRC Identified Potential Base Metal Corrosion on Deep Well

Pump Casing

4/23/2019

242950

Flex Inspection - LIP Procedure Change Documentation

04/24/2019

243132

FLEX Inspection - FLEX Equipment Refueling Methods

04/24/2019

243508

FLEX - Evaluate Enhancement Alternatives to Yanmar

Placement

04/28/2019

Drawings

4E-1791

Unit 1 External Wiring Diagram, Spent Fuel Pool Level

Instrumentation

A

4E-2661A

Local Intense Precipitation Response Procedure Clarification

F

4E-2791

Unit 2 External Wiring Diagram, Spent Fuel Pool Level

Instrumentation

A

Engineering

Changes

EC 0000399944

FLEX Diesel Fuel Oil Plan Fukushima

2/24/2015

EC 395862

Fuel Oil Storage Tanks FLEX Vent Installation

EC 398181

EOC - FLEX Robust Storage Building

Miscellaneous

Lesson N-QC-EP-

FLEX-REC4

GAP Training for Flex Core Cooling

LN-1602

Containment Auxiliaries Training

LN-1900

Operator Initial/ Continuing Training-Fuel Pool Cooling

LN-Flex 1

Diverse and Flexible Coping Strategies

LN-Flex 2

Flex Equipment

RS-13-035

Overall Integrated Plan in Response to Commission Order

Modifying Licenses with Regard to Requirements for Reliable

Spent Fuel Pool Instrumentation

2/28/2013

RS-18-087

Final Integrated Plan Document Mitigating Strategies NRC

08/14/2018

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Order EA-12-049

Procedures

189937-01

PMID Preventive Maintenance Monthly Check for FLEX and

B.5.b. Pumps, Equipment and Trailers

CC-AA-118

Diverse and Flexible Coping Strategies (FLEX), Spent Fuel

Pool Instrumentation (SFPI), and Hardened Containment Vent

System (HCVS) Program Document

CC-QC-118

Site Implementation of Diverse and Flexible Coping Strategies

CC-QC-118

FLEX Periodic Activities

EP-AA-100-200

Dose Assessment

EP-AA-110-200-

F-39

URI Detailed Assessment - Summing Dose Assessments

A

EP-AA-110-201

On Shift Dose Assessment

OU-AA-103

Shutdown Safety Management Program

OU-AA-103

Shutdown Safety Management Program

QCAP 1500-07

Administrative Tracking Requirements For Unavailable FLEX,

HCVS, And SAWA

QCIPM 1900-01

Spent Fuel Pool Indication System Calibration

QCOA 0010-22

Local Intense Precipitation Response Procedure

QCOA 6100-02

Loss of Offsite Power

QCOA 6100-04

Station Blackout

QCOP 0050-01

Unit 1 FLEX DC Load Shed

QCOP 0050-02

Unit 2 FLEX DC Load Shed

QCOP 0050-04

FLEX Refuel Floor Action

QCOP 0050-05

FLEX/SAWA Fire Hose Deployment

QCOP 0050-06

FLEX RPV, Suppression Pool, and Spent Fuel Pool Level

Control

QCOP 0050-07

FLEX Generator and Pump Power Cable Deployment

QCOP 0050-08

FLEX Electrical Restoration

QCOP 0050-09

FLEX Response Instrumentation and Communication

Equipment

QCOP 0050-10

FLEX Battery Room Ventilation

QCOP 0050-11

FLEX Control Room Ventilation

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

QCOP 0050-12

FLEX RCIC System Operation

2

QCOP 0050-13

FLEX Generator/Pump Refueling

QCOP 0050-16

FLEX National SAFER Response Center Interface

QCOP 0050-17

FLEX RCIC Room Cooler Lineup

QCOP 1300-10

Bypassing RCIC Isolations: Low RPV Pressure or High Area

Temperature

QCOS 0050-01

Flex Generator Test

QCOS 0050-01-

Flex Well Pump Test

QCOS 0050-06

HCVS Rupture Disc Integrity Test

QGA 100

RPV Control

QGA 200

Primary Containment Control

QGA 500-4

RPV Flooding

QGA 6900-07

Loss of AC Power to the 125 VDC Battery Chargers

Self-Assessments

Quad Cities Nuclear Power Station

NEI 12-01 Phase 2 Staffing Assessment Report

11/03/2014

Work Orders

04678198

480 VAC Annual Inspection and Load Test (DG-1)

03/17/2019

04760168 01

Pre-Outage - SFP Level Probe Camera Inspect and Calibration

Check

2/18/2018

047771006

Emergency Portable Pump A Surveillance

09/03/2018

04796512

FLEX Deep Well Flow Rate Test

2/06/2018

04825926

Security Event Support Equipment Surveillance

11/25/2018

04828799

Emergency Portable Pump C Surveillance

03/12/2019

04896251 01

PMID Preventive Maintenance Monthly Check for FLEX and

B.5.b. Pumps, Equipment and Trailers Completed 4/10/2019

4/10/2019

1740593

FLEX Robust Storage Building Construction EC 398181

05/04/2016

2515/193

Corrective Action

Documents

2473798

Potential Hardened Vent Tower Fabrication Issues

10/07/2016

04024472

HCVS AOV Assembly Bettis Actuator Part 21 Applicability

05/18/2017

04035644

NOS ID: HCVS EC DCS Not Updated to Reflect Calc Revision

07/24/2017

04036129

NOS ID: HCVS Nitrogen Pipe Model Omitted Elements

03/27/2017

04072155

HCVS Battery Charger Not Functioning

11/07/2017

Engineering

Changes

24618

HCVS Phase 2 Validation Evaluation

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Miscellaneous

Initial and Requal

Training N-AN-

EP-SAM

Severe Accident Guidelines Management

Procedures

QCOP 1600-13

Venting of Containment

QCOP 6900-56

Hardened Containment Vent 125 VDC Battery System

QCOS 1600-59

Hardened Containment Vent System Test

QCOS 1600-60

Hardened Containment Vent System (HCVS) Operating Cycle

Walkdown

SAMG-1

RPV and Primary Containment Injection

SAMG-2

RPV, Containment, and Radioactivity Release Control

Work Orders

04627858

EC 618667 U1 Hardened Containment Vent System (HCVS)

Phase 2

03/06/2019

04802810

Hardened Containment Vent System Test (IST)

03/18/2019