IR 05000321/2018011
| ML18264A038 | |
| Person / Time | |
|---|---|
| Site: | Hatch |
| Issue date: | 09/21/2018 |
| From: | Shane Sandal Reactor Projects Region 2 Branch 6 |
| To: | Vehec T Southern Nuclear Operating Co |
| References | |
| IR 2018011 | |
| Download: ML18264A038 (12) | |
Text
September 21, 2018
SUBJECT:
EDWIN I. HATCH NUCLEAR PLANT - NUCLEAR REGULATORY COMMISSION TEAM INSPECTION REPORT 05000321/2018011
AND 05000366/2018011
Dear Mr. Vehec:
On August 23, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Edwin I. Hatch Nuclear Plant Units 1 and 2. The NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
The inspection examined activities conducted under your license as they relate to the implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders (EA-12-049 and EA-12-051) and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans, your compliance with the Commissions rules and regulations, and with the conditions of your operating license. Within these areas, the inspection involved examination of selected procedures and records, observation of activities, and interviews with station personnel.
The NRC inspectors did not identify any finding or violation of more than minor significance.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding. If you have any questions, please contact me at 404-997-4513.
Sincerely,
/RA/
Shane Sandal, Chief Reactor Projects Branch 6 Division of Reactor Projects
Docket Nos.: 50-321, 50-366 License Nos.: DPR-57 and NPF-5
Enclosure:
IR 05000321/2018011, 05000366/2018011
Inspection Report
Docket Numbers:
50-321, 50-366
License Numbers:
Report Numbers:
05000321/2018011 and 05000366/2018011
Enterprise Identifier: I-2018-011-0044
Licensee:
Southern Nuclear Operating Company, Inc.
Facility:
Edwin I. Hatch Nuclear Plant
Location:
Baxley, Georgia
Inspection Dates:
August 20 - 23, 2018
Inspectors:
R. Rodriguez, Senior Project Engineer (Team Leader)
S. Sanchez, Senior Reactor Inspector
J. Hickman, Resident Inspector
D. Mas-Penaranda, Project Engineer
Approved By:
S. Sandal, Chief
Reactor Projects Branch 6
Division of Reactor Projects
SUMMARY
The NRC continued monitoring licensees performance by conducting Temporary Instruction (TI) 2515/191, Implementation of Mitigation Strategies and Spent Fuel Pool (SFP)
Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans, inspection (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18191B074) at Edwin I. Hatch Nuclear Plant Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
Type Issue number Title Report Section Status TI TI 2515/191 Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans Other Activities Closed
TABLE OF CONTENTS
INSPECTION SCOPE
OTHER ACTIVITIES
- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL
INSPECTION RESULTS
..............................................................................................................
EXIT MEETINGS AND DEBRIEFS
............................................................................................ 6
DOCUMENTS REVIEWED
.......................................................................................................... 7
INSPECTION SCOPE
Inspections were conducted using the appropriate portions of Temporary Instruction (TI)
procedure 2515/191, Implementation of Mitigation Strategies and Spent Fuel Pool (SFP)
Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose
Assessment Plans, (ADAMS Accession No. ML18191B074). Documents reviewed by
inspectors are listed in the documents reviewed section of this report. The inspectors reviewed
selected procedures and records, observed activities, and interviewed personnel to assess
licensee performance and compliance with Commission rules and regulations, license
conditions, site procedures, and standards.
OTHER ACTIVITIES - TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL
TI 2515/191 - Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool
Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose
Assessment Plans
Inspectors verified plans for complying with NRC Orders EA-12-049, Order Modifying
Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis
External Events, (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML12056A045) and EA-12-051, Order Modifying Licenses with Regard to
Reliable Spent Fuel Pool Instrumentation, (ML12054A679) were in place and were being
implemented by the licensee. Additionally, the inspection verified implementation of staffing and
communications information provided in response to the March 12, 2012, request for
information letter (ML12053A340) and dose assessment information provided per COMSECY-
13-0010, Schedule and Plans for Tier 2 Order on Emergency Preparedness for Japan Lessons
Learned, dated March 27, 2013 (ML12339A262).
(1) Based on samples selected for review, the inspectors verified that the licensee
satisfactorily implemented appropriate elements of the Diverse and Flexible Coping
Strategies (FLEX) as described in the plant-specific submittals and the associated safety
evaluation (ML17179A286) and determined that the licensee is in compliance with NRC
Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation
Strategies for Beyond-Design-Basis External Events (ML12056A045). The inspectors
verified the licensee satisfactorily:
a) developed and issued FLEX Support Guidelines (FSGs) to implement the FLEX
strategies for postulated external events;
b) integrated their FSGs into their existing plant procedures such that entry into and
departure from the FSGs were clear when using existing plant procedures;
c) protected FLEX equipment from site-specific hazards;
d) developed and implemented adequate testing and maintenance of FLEX equipment
to ensure their availability and capability;
e) trained their staff to ensure personnel proficiency in the mitigation of
beyond-design basis events; and
f) developed the means to ensure the necessary off-site FLEX equipment would be
available from off-site locations.
(2) Based on samples selected for review, the inspectors verified that the licensee
satisfactorily implemented appropriate elements of the FLEX strategy as described in the
plant specific submittals and the associated safety evaluation (ML17179A286) and
determined that the licensee was in compliance with NRC Order NRC Order EA-12-
051, Order Modifying Licenses With Regard to Reliable Spent Fuel Pool
Instrumentation (ML12054A679). The inspectors verified that the licensee satisfactorily:
a) installed the spent fuel pool (SFP) instrumentation sensors, cabling and power
supplies to provide physical and electrical separation as described in the plant
specific submittals and safety evaluation;
b) installed the SFP instrumentation display in the location, environmental conditions
and accessibility as described in the plant-specific submittals;
c) trained their staff to ensure personnel proficiency with the maintenance, testing, and
use of the SFP instrumentation; and
d) developed and issued procedures for maintenance, testing and use of the reliable
SFP instrumentation.
(3) The inspectors reviewed information provided in the licensees dose submittal and in
response to the NRCs March 12, 2012, request for information letter (ML12053A340),
and verified that the licensee satisfactorily implemented enhancements pertaining to
Near-Term Task Force (NTTF) Recommendation 9.3 response to a large-scale natural
emergency event that results in an extended loss of all alternating current (ac) power
(ELAP) to all site units and impedes access to the site The inspectors verified the
following:
a) the licensee satisfactorily implemented required staffing changes to support a
ELAP scenario;
b) emergency preparedness (EP) communications equipment and facilities are
sufficient for dealing with a ELAP scenario; and
c) the licensee implemented dose assessment capabilities (including releases from
SFPs) using the licensees site-specific dose assessment software and approach.
The inspectors verified that noncompliances with requirements, and standards identified during
the inspection were entered into the licensee's corrective action program as appropriate.
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
No proprietary information was retained by the inspectors or documented in this report.
On August 23, 2018, the inspectors presented the inspection results to Mr.
- T. Vehec, Site Vice
President, and other members of the licensees staff.
DOCUMENTS REVIEWED
Condition Reports Initiated as a Result of the Inspection
10527657, FLEX bolt thread PMs
10527679, HNP NRC FLEX Audit Dome Material Conditions
10527695, NRC walkdown material condition West Cable way
10527914, HNP NRC FLEX Audit load shed walkdown comment
10528292, FLEX audit observed inconsistencies in circle slash methods for past PM work orders
10527700, Revise NMP-OS-019-059 to include location of tooling for emergency opening Dome
doors
10528430 FLEX Staffing Study did not document resources to obtain CST Level
10527184 NMP-OS-019-293 Procedure Enhancement
10527703 NRC Resident Walkdown material condition - FLEX Walkdown
10528253 HNP NRC FLEX Inspection walkdown comments - RB Roof Conditions
10528469 HNP Maintaining a Priority on FLEX
Procedures
31EO-FSG-003-2, FSG - ELAP (Extended Loss of AC Power), Ver. 3.1
NMP-EP-147, Offsite Dose Assessment, Ver. 2.1
NMP-OS-019-003, Security Support for Beyond Design Basis Events, Ver. 1.1
NMP-OS-019-013, Beyond Design Basis Equipment Unavailability Tracking, Ver. 3.0
NMP-OS-019-253, Hatch Unit C SIG-12, Mode 5 RPV Inventory Control, Ver. 2.2
NMP-OS-019-254, Hatch Unit C SIG-11, Critical Instrumentation, Ver. 3.0
NMP-OS-019-256, Hatch Unit C Initial Site Damage Assessment, Ver. 4.0
NMP-OS-019-257, Hatch Unit C Diesel Fuel Oil Transfer, Ver. 1.1
NMP-OS-019-258, Miscellaneous FLEX Equipment, Ver. 1
NMP-OS-019-259, Hatch Unit C SIG-9, Communications, Ver. 1.2
NMP-OS-019-261, Hatch Unit 1 SIG-1, 4160V Alternate Power, Ver. 2
NMP-OS-019-262, Hatch Unit C SIG -2, 600V Alternate Power Division 1, Ver. 6.2
NMP-OS-019-264, Hatch Unit 1 SIG-4, Reactor Pressure Vessel Makeup, Ver. 2.0
NMP-OS-019-266, Hatch Unit 1 SIG-6, Containment Integrity, Ver. 2.1
NMP-OS-019-268, Hatch Unit 1 SIG-8, Spent Fuel Makeup, Ver. 3.1
NMP-OS-019-270, Hatch Unit 1 SIG-10, Ventilation, Ver. 1.1
NMP-OS-019-281, Hatch Unit 2 SIG-1, 4160V Alternate Power, Ver. 2
NMP-OS-019-282, Hatch Unit C SIG -2, 600V Alternate Power Division 2, Ver. 6.2
NMP-OS-019-293, FLEX 600V Diesel Generator Operating Instruction, Ver. 1
NMP-OS-019-296, FLEX RapidCom Generator Operating Instructions, Ver. 1
NMP-OS-019-299, FLEX Light Tower Operating Instruction, ver. 1
NMP-ES-005, Scoping and Importance Determination for Equipment Reliability, Ver. 17.0
NMP-GM-038, Diverse and Flexible Coping Strategies (FLEX) Program, Ver. 2.0
NMP-GM-038-002, Hatch Nuclear Plant Diverse and Flexible Coping Strategies
(FLEX) Program Document, Ver. 3.0
NMP-MA-050, Work Package Preparation, Ver. 6.1
NMP-OM-002, Shutdown Risk Management, Ver. 5.0
31EO-FSG-003-1, FSG - ELAP (Extended Loss of AC Power, Ver. 2.0
34AB-G41-001-1, Loss of Fuel Pool Cooling, Ver. 6.6
34GO-OPS-007-0, Shutdown/Refueling Mode Preparation for Flex, Ver. 1.2
34GO-OPS-030-1, Daily Inside Rounds, Ver.33.1
57IT-G41-001-0, Flex Pool Level Sensors, Ver. 3.0
RapidRack 1X86E018 Functional Test and PM, Ver. 3.0
34IT-FLE-002-0, FLEX Storage Building Equipment Checks, Ver. 2
31EO-FSG-003-1, FSG - ELAP (Extended Loss of AC Power), Ver. 2.1
31EO-FSG-003-2, FSG - ELAP (Extended Loss of AC Power), Ver. 3.1
Drawings
D-11004, Edwin
Ver. 43
H-21039, Edwin
Design Changes
DCP SNC467474, Unit 2 FLEX Alternate Power
DCP SNC467488, Unit 2 Flex Core Cooling
DCP SNC467489, Unit 2 FLEX Condensate Storage Tank
Condition Reports
10313397
10317995
10336555
10345427
10345429
10376424
10388441
10388459
10396083
10399336
10436501
10437237
10503233
10505569
10505570
10513860
274476
294000
10364690
10442844
10477543
10482391
10503233
10514374
10505569
10505570
10513860
256152
279510
10350442
10367864
10437236
10303704
10481351
10311058
10379670
10472446
10514717
10314760
10436989
10323081
10329317
Work Orders
SNC808521, 57IT-G41-001-0 Flex Pool Level Sensors, dated 12/2/16
SNC829784, 57IT-G41-001-0 Flex Pool Level Sensors, dated 1/23/18
SNC829789, 57IT-G41-001-0 Flex Pool Level Sensors, dated 12/7/17
SNC847511, FLEX Booster Pump Operational Inspection, dated 12/5/17
SNC889967, Flex Diesel Powered Lights, dated 6/11/18
SNC911773, Flex Booster Pump Inoperable, dated 1/5/18
SNC756506, FLEX PM : 600V FLEX Generator Operational Inspection, dated 12/6/2016
SNC846059, FLEX Support PM: 600V FLEX D/G Cable Trailer Functional Test & Inspection,
dated 12/4/2017
SNC846063, FLEX PM: 600V FLEX Diesel Generator Functional Test & Inspection, dated
2/8/2017
SNC847524, FLEX PM: 600V FLEX Generator Operational Inspection, dated 12/6/2017
SNC889973, FLEX Support PM: 600V FLEX D/G Cable Trailer Functional Test & Inspection,
dated 6/19/2018
SNC889977, FLEX PM: 600V FLEX Diesel Generator Functional Test & Inspection, dated
6/26/2018
SNC915082, 1 Year PM FLEX Mode 5 Core Cooling Pump Operational Inspection,
dated June 13, 2018
SNC821126, FLEX Support PM: RapidCase Communications Functional Test & Inspection,
dated 8/17/7
SNC822483, FLEX Support PM: RapidCom Communications Functional Test & Inspection,
dated 10/26/17
SNC84287, FLEX Support PM: RapidCase Communications Functional Test & Inspection,
dated 1/25/18
SNC857772, FLEX Support PM: RapidCom Communications Functional Test & Inspection,
dated 4/3/18
SNC887274, FLEX Support PM: RapidCase Communications Functional Test & Inspection,
dated 8/8/18
Other
NMP-GM-038-002, Hatch Nuclear Plant Diverse and Flexible Coping Strategies (FLEX)
Program Document, Ver. 3
NMP-GM-038, Diverse and Flexible Coping Strategies (FLEX) Program, Ver. 2
HNP-FLEX-2016-19, Hatch Nuclear Plant FLEX Verification and Validation Report, dated
2/27/2016
S76305, Report of Liquefaction Potential Assessment FLEX Dome Storage Building and Travel
Paths Hatch Nuclear Plant (HNP), date 10/3/2014
FHC-S-13-001/X1AR50, Procurement Specification for FLEX equipment Storage Building,
Ver. 1
SNC600781, Hatch FLEX dome infrastructure, Ver. 2
August 2018 NRC TI-191 Inspection Plant Hatch FLEX Overview Slides
DOEJ-HRSNC600781-C001, Evaluation of Tie-Downs for Equipment in the FLEX Storage
Building, Ver. 1.0
Diesel Fuel Supply Assurance Letter from Diversified Energy Supply, dated June 27, 2018
Edwin
- I. Hatch Nuclear Plant, Units 1 and 2-Safety Evaluation Regarding Implementation of
Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders
EA-12-049 and EA-12-051, dated 8/4/17
Edwin
- I. Hatch Nuclear Plant, Units 1 and 2-Notification of Full Compliance of Required Action
for NRC Order EA-12-051 Reliable Spent Fuel Pool Instrumentation, dated 2/13/17
Hatch Nuclear Plant FLEX Verification & Validation Report, dated 2/28/16
Safer Response Plan for Edwin
- I. Hatch Nuclear Plant, dated 8/11/15
S-76305, Report of Liquefaction Potential Assessment for Flex Dome Storage Building and
Travel Paths Hatch Nuclear Plant, dated 10/3/14
SNC600781-05, Hatch Dome Infrastructure, dated 3/2/16