ML18095A159
| ML18095A159 | |
| Person / Time | |
|---|---|
| Site: | Vallecitos Nuclear Center, 07000754, 07001113, 07200001, Vallecitos |
| Issue date: | 03/30/2018 |
| From: | Rachel Johnson Fuel Manufacturing Branch |
| To: | Anthony Bowers, Chris Mckenney, Richard Turtil Office of Nuclear Material Safety and Safeguards, NRC/NMSS/DREFS/FAB, NRC/NSIR/DPCP/RSB |
| Naquin T | |
| References | |
| Download: ML18095A159 (1) | |
Text
From:
Johnson, Robert To:
Bowers, Anthony; McKenney, Christepher; Turtil, Richard Cc:
Naquin, Tyrone; Brockington, Tamyra; Augustus, Reginald; Harwell, Shawn
Subject:
FW: Work Request - GNF/GEH Date:
Friday, March 30, 2018 12:20:57 PM Importance:
High Chris and Rich,
Please find the work request below for the review of GEs Decommissioning Funding financial assurance documents. Ty has already done some of the leg work and reached out to Reggie and Shawn and will be forwarding an EPID, as soon as it is available.
Please review the request and the proposed dates and let us know if you all can support the review and the requested dates.
- Thanks,
Robert K. Johnson Fuel Manufacturing Branch Chief NRC / NMSS / FCSE / FMB Office / MS : TWFN04-B06 / TWFN04-A60 PHONE / FAX: 301.415.7314 / 301.415.0020
From: Naquin, Tyrone Sent: Friday, March 30, 2018 9:15 AM To: Johnson, Robert <Robert.Johnson@nrc.gov>
Cc: Brockington, Tamyra <Tamyra.Brockington@nrc.gov>
Subject:
Work Request - GNF/GEH
- Robert,
Please forward this work request to Chris McKenney and Tony Bowers to engage Reggie Augustus and Shawn Harwell to complete the reviews for the Financial Assurance Documents submitted on Tuesday. Tony is on leave right not and Rich Turtil is acting for him, so please forward to him. I have confirmed with both Reggie and Shawn that the dates in the work request are acceptable. I have been awaiting an EPID but that has not arrived yet so I want to go ahead with issuing the work request this week and I will follow up with Reggie and Shawn to send the EPID. Thanks
The Fuel Manufacturing Branch of the Division of Fuel Cycle Safety, Safeguards and Environmental Review requests technical assistance for the following project:
PROJECT: Global Nuclear Fuels - Americas (GNF-A), GE Hitachi (GE-H) Nuclear Energy
DOCKET NO: 70-1113,70-754, 72-01, 50-18, 50-70, 50-73, 50-183
LICENSE NO: SNM-1097, SNM-960, SNM-2500, DPR-1, TR-1, R-33, DR-10
EPID NO: Notification of EPID to be forwarded to reviewers upon receipt.
ADAMS NO: ML18087A172 (Package)
REQUESTED ACTION: Review the Financial Assurance Submittal (Surety Bonds) received from GNF-A/GEH for the material licensees identified on the docketed correspondence. The purpose of the review of the licensees financial assurance mechanism is to ensure that sufficient funds will be available to carry out all required decommissioning activities prior to license termination and, if the license is being terminated under restricted conditions, to enable an independent third party to assume and carry out responsibilities for any necessary control and maintenance of the site.
Determine if there are major deficiencies that make the submittal unacceptable for detailed review and prepare a recommendation to accept or deny (if required). Prepare requests for additional information, if needed. Evaluate any additional information submitted. Participate in meetings, conference calls, and site visits, if necessary. Provide input for a Final Report. The review should be consistent with the guidance of NUREG-1757, Volume 3, Revision 1, Financial Assurance, Recordkeeping, and Timeliness.
The above task is estimated to require approximately 40 staff hours.
Acceptance review requested by: April 30, 2018
RAI requested by: June 14, 2018
SER input requested by: September 6, 2018
The Final Report on this review must be issued by September 25, 2018.
NRR/DLP/PFPB/ NMSS/DFCSE/DUWP Branch Chief please and fill in the following:
Technical Reviewer: __NRR/DLP/PFPB: Harwell NMSS/DUWP/PAB: Augustus
Acceptance review target date: _________________________
RAI input target date: _________________________
SER input target date: ____________________________
Contacts: PM: Ty Naquin (301) 415-7352 LA: Tamyra Brockington (301) 415-8714
T. D. Naquin, CHP NMSS/DFCSE/FMB
(301) 415-7352