Letter Sequence Other |
|---|
|
|
MONTHYEARML18016A0562018-01-10010 January 2018 International - HI-STAR 80 Schedule for Response to 2nd Round of RAIs Project stage: Other ML18072A1702018-02-28028 February 2018 HI-2146261, Rev. 2.C, Safety Analysis Report on the HI-STAR 80 Package Project stage: Other ML18072A1582018-03-0101 March 2018 Submittal of RAI Responses for Holtecs Application for the Design Certification of the HI-STAR 80 Transportation Package Project stage: Request ML18072A1662018-03-0101 March 2018 Response to NRCs 2nd Request for Additional Information HI-STAR 80 Transportation Package Project stage: Request ML18072A1682018-03-0101 March 2018 Summary of Proposed Changes HI-STAR 80 2nd Round RAI Submittal Project stage: Request ML18256A1552018-09-0404 September 2018 HI-2146261, Revision 3, Safety Analysis Report on the HI-STAR 80 Package Project stage: Other ML18256A1722018-09-0404 September 2018 Submittal of Final SAR for Holtecs Application for the Design Certification of the HI-STAR 80 Transportation Package Project stage: Request ML18262A1012018-09-18018 September 2018 Enclosure 2: Safety Evaluation Report (Letter to L. Hinojosa Certificate of Compliance No. 9374, Revision No. 0, for the Model No. HI-STAR 80 Package) Project stage: Approval ML18262A1032018-09-18018 September 2018 Package: Letter to L. Hinojosa Certificate of Compliance No. 9374, Revision No. 0, for the Model No. HI-STAR 80 Package Project stage: Request ML18262A1002018-09-18018 September 2018 Letter to L. Hinojosa Certificate of Compliance No. 9374, Revision No. 0, for the Model No. HI-STAR 80 Package Project stage: Other ML18262A0992018-09-18018 September 2018 Enclosure 1: Certificate of Compliance No. 9374, Rev. No. 0 (Letter to L. Hinojosa Certificate of Compliance No. 9374, Revision No. 0, for the Model No. HI-STAR 80 Package) Project stage: Other 2018-03-01
[Table View] |
Text
HOLTEC Holtec Technology Campus, 1 Holtec Blvd, Camden, NJ 08104 INTERNATIONAL January I 0, 2018 Pierre Saverot, Project Manager Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Docket No.: 71-9374 (HI-STAR 80 Model)
CAC No.: L25141 Telephone (856) 797-0900 Fax (856) 797-0909
References:
[I] USN RC Letter, Pierre Saverot to Luis Hinojosa, dated September 25, 2017
Subject:
HI-STAR 80 Schedule for Response to 2 11 ct Round of RA ls
Dear Mr. Saverot:
In order to address the performance of cask materials under fire accident conditions as requested in
[I], a minor change to the shielding design of the cask was required. The corresponding revised safety evaluations are now being finalized, and we expect to submit the documents to NRC for their final review by the middle to end of February 2018.
If you have any questions, then please contact me at 856-797-0900, ext. 3659.
Sincerely, Stefan Anton, Dr. -Ing Vice President of Engineering Holtec International cc: