MONTHYEARML16088A3252016-03-23023 March 2016 License Renewal Application Waterford Steam Electric Station, Unit 3 (Waterford 3) (Part 3 of 9) Project stage: Other ML16307A0062016-11-0707 November 2016 Requests for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application; Set 5 Project stage: RAI ML16307A0072016-11-0707 November 2016 Requests for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application Set 6 Project stage: RAI ML16315A2352016-11-10010 November 2016 Responses to Request for Additional Information Set 2 Regarding the License Renewal Application Project stage: Response to RAI ML16299A2822016-11-10010 November 2016 Scoping and Screening Methodology Audit Report Regarding Waterford Steam Electric Station, Unit 3 License Renewal Application Review Project stage: Other ML16320A0032016-11-15015 November 2016 Requests for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application Set 8 Project stage: RAI ML16320A0022016-11-15015 November 2016 Requests for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application - Set 7 Project stage: RAI ML16335A3742016-12-0202 December 2016 RAI Set 9 Letter Concurrence (11 30 2016) Project stage: RAI W3F1-2016-0075, Responses to Request for Additional Information Set 6 Regarding the License Renewal Application2016-12-0707 December 2016 Responses to Request for Additional Information Set 6 Regarding the License Renewal Application Project stage: Response to RAI ML16343A0722016-12-0808 December 2016 Requests for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application - Set 10 Project stage: RAI W3F1-2016-0070, Responses to Request for Additional Information Set 3 Regarding the License Renewal Application2016-12-12012 December 2016 Responses to Request for Additional Information Set 3 Regarding the License Renewal Application Project stage: Response to RAI ML16351A0452016-12-19019 December 2016 Requests for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application - Set 11 Project stage: RAI ML16341B0632016-12-21021 December 2016 November 30, 2016 Summary of Teleconference Held Between NRC and Entergy Operations, Inc. Concerning RAI Set 9 Pertaining to the Waterford Steam Electric Station, Unit 3, License Renewal Application Project stage: RAI ML16356A5822016-12-30030 December 2016 Summary of Teleconference with Entergy Operations, Inc. Concerning Requests for Additional Information Set 10 Pertaining to the Waterford Steam Electric Station Unit 3 License Renewal Application Project stage: RAI ML17018A3592017-01-26026 January 2017 Requests for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application Set 12 (CAC MF7492.) Project stage: RAI W3F1-2017-0004, Responses to Request for Additional Information from Sets 4, 5 and 6 Regarding the License Renewal Application2017-02-0606 February 2017 Responses to Request for Additional Information from Sets 4, 5 and 6 Regarding the License Renewal Application Project stage: Response to RAI ML17040A5382017-02-14014 February 2017 Requests for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application - Set 13 Project stage: RAI ML17272A3352017-03-0101 March 2017 Request for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application - Set 14 Project stage: RAI ML17072A0102017-03-14014 March 2017 Requests for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application Set - 15 Project stage: RAI ML17101A4432017-04-17017 April 2017 Requests for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application - Set 17 Project stage: RAI ML17054C5292017-05-0909 May 2017 Aging Management Programs Audit Report Regarding Waterford Steam Electric Station, Unit 3 License Renewal Application Review Project stage: Other ML17131A1942017-08-24024 August 2017 Status Update and Schedule Revision for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application Project stage: Approval W3F1-2017-0065, License Amendment Request for Use of RAPTOR-M3G Code for Neutron Fluence Calculations2017-11-28028 November 2017 License Amendment Request for Use of RAPTOR-M3G Code for Neutron Fluence Calculations Project stage: Request W3F1-2017-0083, License Renewal Application Supplement Clarification2017-12-0707 December 2017 License Renewal Application Supplement Clarification Project stage: Supplement ML17341A2412017-12-0707 December 2017 Entergy - 2017 Certification of Foreign Ownership Control or Influence (FOCI) Project stage: Request ML17347A1272017-12-20020 December 2017 Status Update and Schedule Revision for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application Project stage: Approval ML18085A6942018-03-26026 March 2018 NRR E-mail Capture - Ref: Waterford Steam Electric Station, Unit 3, License Renewal Application - RAI Set 18 Project stage: RAI ML18165A1392018-08-16016 August 2018, 20 August 2018 Notice of Availability of the Draft Plant-Specific Supplement 59 to the Generic Environmental Imapct Statement for License Renewal of Nuclear Plants Regarding Waterford 3 Project stage: Request ML18221A2442018-08-17017 August 2018 Safety Evaluation Report (Cover Letter) Related to the License Renewal of Waterford Steam Electric Station, Unit 3 Project stage: Approval ML18221A1162018-08-17017 August 2018 Status Update and Schedule Revision for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application Project stage: Approval ML18228A6682018-08-17017 August 2018 Safety Evaluation Report Related to the License Renewal of Waterford Steam Electric Station, Unit 3 Project stage: Approval ML18275A2152018-12-27027 December 2018 Issuance of Renewed Facility Operating License No. NPF-38 for Waterford Steam Electric Station, Unit 3 CAC Nos. MF7492 and MF7493) Project stage: Approval 2017-11-28
[Table View] |
Text
CNRO-2017-0024 December 7, 2017 ATTN: Document Control Desk Director, Division of Security Operations Office of Nuclear Security and Incident Response U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
SUBJECT:
Entergy - 2017 Certification of Foreign Ownership Control or Influence (FOCI)
Arkansas Nuclear One, Units 1 and 2; Grand Gulf Nuclear Station; Indian Point Energy Center, Units 1, 2 and 3; Palisades Nuclear Plant; Pilgrim Nuclear Power Station; River Bend Station; Vermont Yankee Nuclear Power Station; and Waterford 3 Steam Electric Station
REFERENCES:
- 1.
Letter from D. Parsons to M. Halter, dated November 28, 2017, Entergy Redetermination of Foreign Ownership, Control, or Influence (CNRI-2017-0004)
- 2.
Letter from F.G. Burford to USNRC, dated August 23, 2004, Entergy Corporation - Response to Foreign Ownership Control or Interest (FOCI) Request for Additional Information (CNRO-2004-00056)
- 3.
Letter to M.R. Kansler from A. Lynn Silvious, dated July 11, 2007, Request for Annual Recertification (CNRI-2007-00016)
Dear Sir or Madam:
This letter is the Entergy Operations, Inc., (EOI) and Entergy Nuclear Operations, Inc. (ENOI)
(herein after collectively referred to as Entergy) 2017 response to the Reference 1 requirement for Entergy, as a holder of an NRC-issued facility clearance that has executed a Board resolution to mitigate Foreign Ownership, Control, or Influence (FOCI) concerns, to provide an annual certification that the resolution continues to be in effect.
Entergy hereby certifies that the Board resolutions adopted in 2004 (Reference 2) by EOI, ENOI, and Entergy Corporation (EC) remain in effect serving as insulation tools to ensure that EOI and ENOI have been delegated full authority to act independently of the aforementioned parent organization (EC) in matters which relate to the responsibility of safeguarding classified information to which EOI and ENOI has access. The resolutions also ensure that EC will not have access to classified information being used or handled by EOl and ENOI.
Entergy had previously been providing an annual FOCI certification pursuant to the requirement set forth in Reference 3. Entergy understands that this requirement has been superseded by the Reference 1 annual certification requirement. Therefore, Entergy no longer Entergy Operations, Inc.
Entergy Nuclear Operations, Inc.
1340 Echelon Parkway Jackson, MS 39213 Tel : 601-368-5000 Mandy Halter Director, Nuclear Licensing
CNRO-2017-0024 / Page 2 of 2 intends to provide an annual certification based on the Reference 3 requirements, but will instead provide an annual certification based on Reference 1 or as requested by the NRC.
There are no new regulatory commitments in this letter. If you have any questions, please contact Mr. Philip Couture, Manager, Fleet Licensing Programs, at (601) 368-5102.
Sincerely, MH / plc cc:
NRC Regional Administrators (Regions I, III and IV)
NRC Project Managers (Entergy, ANO, GGNS, IPEC, PAL, PNPS, RBS, WF3, VY)