JACK A. BAILEY VICE PRESIDENT ENGINEERING Arizona Public Service Company PALO VERDE NUCLEAR GENERATING STATION P.O. BOX 52034
~
PHOENIX, ARIZONA85072-2034 102-03735-JAB/SAB July 17, 1996 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Station P1-37 Washington, DC 20555-0001
Dear Sirs:
Subject:
Palo Verde Nuclear Generating Station (PVNGS)
Units 1, 2, and 3 Docket Nos. STN 50-528/529/530 Degraded Voltage On July 11,
- 1996, Arizona Public Service Company (APS) met with Nuclear Regulatory Commission (NRC) management to provide an updated status of the double sequencing issue at the Palo Verde Nuclear Generating Station (PVNGS).
In that meeting APS committed to provide the information discussed in a followup letter.
The purpose of this letter is to document our commitment to submit the subject letter by August 2, 1996.
In addition, we propose to make a more detailed technical presentation to the NRC staff of degraded voltage issues, including double sequencing, compensatory
- actions, and planned corrective actions.
We will schedule this meeting through our Project Manager.
If you have any questions, please contact Scott A. Bauer, Section Leader, Nuclear Regulatory Affairs, at (602) 393-6492.
Sincerely, JAB/SAB/pv cc:
L. J. Callan K. E. Perkins K. E. Johnston J. W. Clifford I
9607250i64 960717 PDR ADQCKjj05000528 P