Nuclear Decommissioning Citizens Advisory Panel (NDCAP)
May 25, 2017
Introductions
1 Joseph R. Lynch Sr. Manager, Government Affairs Decommissioning - EWC
Decommissioning Project Status 2
1 VY Decommissioning Update
- Dry Fuel Storage Project
- ISFSI Pad Construction
- Construction restarted on March 13th, 2017
- Rebar placement for the second ISFSI pad is complete
- Concrete placement is the next project milestone
- Dry Fuel Loading
- 2017: Approximately 20 Dry Casks
- 2018: Target loading remainder with 45 total loaded
- All fuel transferred to the ISFSI: Target 3Q/4Q 2018, pending NRC approvals 3
1 VY Decommissioning Update (Contd) 4 Pouring of Leveling Slab for ISFSI Pad 2 Current ISFSI Pad Configuration
1 VY Decommissioning Update (Contd) 5 Rebar Placement for 2nd ISFSI Pad
1 VY Water Management Update
- Water Management Update
- Intrusion Water Disposition Plan
- Intrusion water retention, shipment and removal plan continues to be implemented.
- In-leakage prevention projects seeking to further reduce the intrusion of groundwater continue.
- EnergySolutions is providing shipment and disposal services
- Groundwater is being shipped to EnergySolutions licensed disposal site in Tennessee.
- Shipping approximately three shipments per month at the present intrusion rate to minimize on-site storage.
- A total of 517,000 gallons have been shipped to date.
6
Proposed VY Sale and Accelerated Decommissioning 7
1 Public Service Board Proceeding Update
- First Round of Discovery Requests on Petitioners - March 17th
- Responses to First Round of Discovery Requests - April 26th
- DPS filed motion for protective order for confidential documents - May 2nd
- NorthStar filed Motion for Special Protocol for Access to Highly Confidential Documents - May 5th
- Second Round of Discovery Requests on Petitioners -
May 10th*
- NEC filed a Motion for Partial Summary Judgment - May 5th
- Petitioner response to NEC Motion due June 5th
- DPS filed Motion for Extension of Discovery Request Deadline 8
Nuclear Decommissioning Trust Update 9
1 Nuclear Decommissioning Trust Update
$568.9 Million on March 31, 2017
- The NDT balance was $570 Million on April 30, 2017 The increase was due to positive market performance, partially offset by reimbursements from the NDT. Fund expenses occur periodically throughout the year.
Summary of NDT Performance in 2017:
$11.9M in Qualified Withdrawals
$21.7M in Market Gains
$1.4M in Fund Expenses
- The Site Restoration Trust balance was $23.6 Million on April 30, 2017.
Entergy has funded $20M to date; $3.6M fund growth.
Final $5M annual contribution to the Site Restoration Trust scheduled for December 2017.
10
1 Open Communication and Transparency
- Nuclear Decommissioning Citizens Advisory Panel (NDCAP)
- Stakeholder Outreach
- Speaking Engagements
- Media Interviews
- Local Advertising
- Continued Community Involvement
- Tours for Key Stakeholders
- Updated ENVY Decommissioning Website, www.vydecommissioning.com 11
1 Open Communication and Transparency 12