ML16342C730

From kanterella
Jump to navigation Jump to search
Insp Rept 50-323/94-28 on 941019-28.Violations Noted.Major Areas Inspected:Dg Surveillance Testing,Tailboard & Supervision Involvement & Sys Engineer Involvement W/Surveillance Testing
ML16342C730
Person / Time
Site: Diablo Canyon Pacific Gas & Electric icon.png
Issue date: 11/07/1994
From: Kirsch D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML16342C729 List:
References
50-323-94-28, NUDOCS 9411170047
Download: ML16342C730 (16)


See also: IR 05000323/1994028

Text

APPENDIX B

U.S.

NUCLEAR REGULATORY COMMISSION

REGION IV

Inspection Report:

50-323/94-28

License:

DPR-82

Licensee:

Pacific

Gas

and Electric Company

77 Beale Street,

Room 1451.

P.O.

Box 770000

San Francisco,

California

Facility Name:

Diablo Canyon Nuclear

Power Plant, Unit

2

Inspection At:

Diablo Canyon Site,

San Luis Obispo County, California

Inspection

Conducted:

October

19-28,

1994

Inspector:

H. Tschiltz, Resident

Inspector

Approved:

.

K rsc

,

C i

, Reactor

Prospects

rane

t

Ins ection

Summar

D te

Areas

Ins ected

Unit 2

A special

inspection of the circumstances

associated

with the loss of residual

heat

removal

(RHR) cooling during diesel

generator

(DG) testing

on October

18,

1994.

During the inspection,

Inspection

Procedures

92901

and

92703 were used.

Areas

Ins ected

Unit

1

No inspection of Unit

1 was performed.

Results

Unit 2

On October

18,

1994, during

DG surveillance testing,

the failure of licensee

personnel

to follow the procedural

requirements

resulted

'in the inadvertent

shutdown of the

RHR pump providing cooling to the core.

After a period of

approximately

6 minutes the control operator

noted that the'running

RHR pump

had

been de-energized

during the testing

and restarted

the

RHR pump.

Prior to

de-energizing

Bus H, there were two separate

steps

in the procedure

which, if

performed properly,

would have identified that

RHR Pump 2-2 should not be in

operation during the testing which de-energized

4 kv Bus H.

Additionally,

a

note in the procedure

should

have alerted operators

to the fact that

RHR

Pump 2-2 should not

be in service to support

any critical plant operations

during the testing.

9411170047

941109

PDR

ADOCK 05000323

9

PDR

0

Plant

0 erations

Weaknesses:

The inspection identified two instances

of operator failure to follow

surveillance

procedure

requirements

which resulted

in the loss of RHR

cooling flow through the core.

A detailed tailboard

was not conducted prior to performing the

surveillance.

Neither the shift foreman nor shift supervisor

were

involved with the discussion

of DG testing.

The tailboard conducted

by

the operator

and

system engineer did not meet

management

expectations

for integrated

plant testing.

~

The shift foreman did not provide adequate

oversight of testing which

had the 'potential to impact core cooling.

The level of involvement

by

the shift foreman did not meet

management

expectations

for integrated

plant testing.

~

The control operator failed to adequately

consider the effect of the

surveillance test

on core cooling.

A visual examination of the control

boards to identify components

that would be de-energized

during the

surveillance test failed to identify that

RHR Pump 2-2 was in operation.

t

~R1 i:

N

pl i

b1

Summar

of Ins ection Findin s:

~

Violation 323/94-28-01

was identified (Section 2).

Attachment:

~

Attachment

I - Persons

Contacted

and Exit Heeting

~

Attachment

2

Acronyms.

0

'

DETAILS

1

BACKGROUND

At the time of the Diablo Canyon Unit 2 loss of RHR cooling,

on October

18,

1994,

the unit was in Mode

5 with a reactor coolant

system temperature

of

96'F.

The unit was in the 25th day of 'Refueling Outage

2R6.

Core reload

was

complete

and both trains of RHR were available.

RHR Pump 2-2 was running

and

powered

from 4 kv Bus

H.

DG surveillance testing

was being performed that

required vital

4 kv Bus

H to be de-energized.

RHR

Pump 2-2 was improperly

left in service during this testing.

When power to 4 kv Bus

H was secured,

per the surveillance,

DG 2-2 autostarted

and aligned to re-energize

4 kv

Bus

H; however,

as expected for the autoload feature

under test,

the

RHR pump

did not autoload

back onto the

4 kv bus

~

The de-energization

of RHR

Pump 2-2

resulted

in the loss of core cooling.

The loss of RHR flow was noted

by the

control operator

approximately

6 minutes after the

pump was de-en'ergized,

at

which point

RHR

Pump 2-2 was restarted.

During the interruption of core

cooling core temperature

increased

approximately 6'F from 96 to 102'F.

" The

licensee

made

a 4-hour nonemergency

report regarding this event to the

NRC in

accordance

with 10 CFR 50.72(b)(2)(iii)(B).

2

DG SURVEILLANCE TESTING

2. 1

DG 2-2 Autostart

and

Load Transfer Testin

On the evening of October

18,

1994,

DG 2-2 testing

per Surveillance

Test

Procedure

STP M-9G, Revision

18,

"Diesel Generator

24-Hour Load Test,"

was

performed which involved the

demonstration

of autostart

and load transfer

functions.

The autostart

portion of the test involved running

DG 2-2 at full

load for

1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> or until operating

temperature

stabilized,

unloading

and

securing

the

DG, opening the auxiliary power feeder breaker

supplying the

4 kv

bus associated

with the

DG being tested,

and verifying that the

DG autostarted

and loaded onto the

bus within 10 seconds.

The load transfer portion of the

test verified that breakers for 4 kv auto-connected

loads closed

onto the

bus

after the

DG breaker closed.

A licensed operator

was assigned

to operate

and align equipment

per

STP M-9G,

as required,

during the test.

A system engineer

was assigned

to the testing

team to provide technical

guidance if required during testing.

Control

room

equipment alignments,

required during the performance

of STP M-9G, were

accomplished

by the licensed operator with the surveillance

procedure

in hand.

Changes

in equipment

lineups

were communicated

to the control operator.

In preparation for the autostart

auto load test portion of STP M-9G, the

procedure

specified

alignment of Vital Bus

H equipment.

Systems

and

components

affected

by the loss of 4 kv Bus* H power were required to be

realigned, prior to de-energizing

the bus,

to ensure

the test did not

adversely

impact plant operation.

Step

12.3. I.e.4, stated,

in part, that

"The

following equipment will not autostart

in this test

and must

be shut

down:

a)

0

0

'

RHR

Pump

No.

2

b) Containment

Spray

Pump

No.

2 c) SIS

Pump

No. 2."

This step

was initialed by the operator

as complete

in error,

since the

RHR pump was not

secured.

Immediately following Step

12.3. l.e-.4, the procedure

contained

a

note which explains that these

4 kv bus

H loads

are secured

because

the load

shed signal,

which is generated

during the test, will trip the breakers

supplying

power to the

pumps if they are in service.

The note additionally

cauti'oned that "if the autotransfer

signal

cannot

be reset

these

pumps

can not

be manually restarted"

and concludes with the statement

that "these

pumps

should not be in service to support

any critical plant operations."

At a subsequent

point in the procedure,

prior to securing

the power to

4 kv

Bus

H, Step 12.3.2.g.

1 required that

a review be performed to verify that the

equipment lost. due to the transfer will not place the plant in a Technical

Specification

(TS) action statement.

The step

was initialed as being

completed

by the operator;

however,

the operator did not identify that the

operating

RHR pump

was

powered

from 4 kv Bus

H and that securing

power to

4 kv

Bus

H would result in the entry into TS 3.4. 1.4. 1 action statement.

TS 3.4.1.4.

1 requires that

one

RKR train be operable

and in operation

when in

Mode

5 with the reactor coolant loops filled.

Prior to securing

the auxiliary power feed to the bus,

the control operator

discussed

the

sequence

of events

from de-energizing

the

bus to the

autostarting of the loads with the operator.

The shift foreman

was informed

.

when the portion of the test which de-energized

the bus

commenced.

The

control operator

scanned

the control

board to determine

which loads would be

lost during the transfer.

During the scan,

the control operator did not

identify that the running

RHR pump would be stripped

from the

bus during

testing.

Caution tags were'hanging

on the control

board which obscured

the

control operator's

view of color coded labeling indicating equipment

power

sources;

however,

the tags did not obscure

RHR

Pump 2-2 running light

indication.

The control operator did not recognize that the running

RHR pump

would be affected

by the surveillance.

Conclusion

The two instances

where the operator failed to follow the instruction of the

surveillance test procedure,

STP M-9G, are

examples of failure to follow

procedural

requirements

and are

a violation of TS 6.8. 1.

TS 6.8. 1 requires

that written procedures

shall

be established,

implemented,

and maintained

covering the applicable

procedures

recommended

in Appendix

A of Regulatory

Guide 1.33,

Revision 2, including procedures

covering the performance of

surveillance tests

on emergency

power systems

{Violation 323/9428-01).

2.2

Tailboard

and

Su ervision

Involvement

During the previous

performance

of STP

M-9G for DG 2-2 on October

17,

1994,

DG 2-2 failed to meet the acceptance

criteria for time to hot restart

and load

onto the bus.

The actual

time for this portion of the testing

was greater

than

10 seconds,

which is the maximum allowable per the surveillance

procedure.

The licensee's

preliminary review of the conditions in effect

!

during the test indicated that the failure to meet the test criteria was

related to the slow rate of voltage decrease

following the opening of the

auxiliary feeder breaker.

NRC review of the initial failure of DG 2-2 to meet

the acceptance

criteria will be documented

in NRC Inspection

Report 50-

323/94-27.

On October

18,

1994,

the shift foreman

made the decision to not conduct

a

tailboard for the

STP M-9G testing

scheduled for the evening of October

18,

1994.

This decision

was

based

on the shift foreman's

assessment

that the

involved system engineer

and operator familiarity with STP

M-9G was

acceptable,

in part,

because

portions of STP

M-9G had

been

performed

by the

operators

and the

system engineer

the previous day.

Neither the shift foreman

or the senior control operator

were directly involved with supervision

or

oversight of the

STP

M-9G testing prior to commencing

the testing which

resulted

in de-energizing

the running

RHR pump.

The shift foreman relied upon

the system engineer to conduct the test with the operator.

The system

engineer

and the operator did review portions of the test procedure

together

prior to performing the test.

The review included

a basic overview of the

sequence

of the test

and

DG limitations.

The control operator participated

in

a portion of the test review for the discussion of the electrical

loads which

would be de-energized

during the test

and the loads which would autoload

onto

4 kv Bus

H.

During this review the system engineer

explained that all

Bus

H

loads

would initially be de-energized

during the test.

The operator's

primary

concern

was the

480 volt loads which were to be de-energized

and the loads

which were to autoload

onto the

bus during the test.

Conclusion

The decision of the shift foreman to not

be involved with critical portions of

the testing involving de-energizing

Bus

H was not in accordance

with

management

expectations

for integrated plant testing.

Additionally, the

decision that

a formal tailboard for the

DG testing

was not required

was not

in accordance

with management

expectations

for the conduct of tailboards.

As

a result of these

problems,

licensee

management

has initiated actions to

reinforce expectations

for the conduct

and content of tailboards.

'.3

S stem

En ineer Involvement with Surveillance Testin

The authority and responsibilities of the system engineer during the

surveillance test were not clearly understood.

Perso'nnel

involved with the

test

had differing views of the system engineer's

role during the test.

The

system engineer role in the performance of testing is defined in licensee

administrative

Procedure

AD13. ID1, Revision

1A, "Conduct of Plant

Equipment

Tests,"

paragraph

5.4.3,

which states, "if technical

guidance of testing

activities is needed,

the person

in charge of the test

should contact the

appropriate

System

Engineer

or the procedure's

sponsor."

0

'

Conclusion

There is not

a clear definition or understanding

of system engineer

responsibilities

during system testing.

The involvement of system engineers

with surveillance testing

has

increased

with the shortened

outage periods.

The

NRC views the increased

involvement of the system engineer

as

a strength

of the outage testing

program;

however,

increased

system engineer

involvement

without clear definition of system'engineer

responsibilities

during the

conduct of testing creates

an increased

potential for errors in

communications.

The licensee

is reviewing the-need for more clearly

establishing

the role of the system engineer during the conduct of testing.

0

'

1

PERSONS

CONTACTED

ATTACKHENT 1

1. 1

Licensee

Personnel

G.

H. Rueger,

Senior Vice President

and General

Manager,

Nuclear

Power

Generation

Business

Unit

J.

D. Townsend,

Vice President,

Nuclear Technical

Services

  • W. K. Fujimoto, Vice President

and Plant Manager,

Diablo Canyon Operations

R.

P.

Powers,

Manager,

Nuclear guality Services

  • H. J.

Angus,

Manager,

Nuclear Technical

Services

D.

B. Barkley, Shift Foreman,

Operations

S.

Bednarz,

System Engineer,

Systems

Engineering

  • C.

C

Belmont, Auditor, equality Assurance

  • B. J.

Berndt,

Engineer,

Regulatory

Compliance

  • T. L. Grebel,

Superv,isor,

Regulatory

Compliance

  • W. G. Crockett,

Manager,

Technical

and Support, Services

  • S.

R. Fridley, Director, Operations

C.

H. Harvey, Control Operator,

Operations

  • J.

R. Kinds, Director, Nuclear Safety Engineering

  • K. A. Hubbard,

Engineer,

Regulatory

Compliance

H,

S.

Lemke, Shift Supervisor,

Operations

  • D. B. Hiklush, Manager,

Operations

Services

  • D. K. Oatley, Director, Materials Services
  • R. Ortega,

System Engineer,

Systems

Engineering

  • J. L. Portney,

System Engineer,

Systems

Engineering

J.

B. Whetsler,

Nuclear Operator,

Operations

1. 2

NRC Personnel

  • H. Tschiltz, Resident

Inspector

  • Denotes those attending

the exit meeting

November

2,

1994.

In addition to the personnel

listed above,

the inspectors

contacted

other

personnel

during this inspection period.

I

2

EXIT MEETING

An exit meeting

was conducted

on November

2,

1994.

During this meeting,

the

inspectors

reviewed the scope

and findings of the report.

The licensee

'acknowledged

the inspection findings documented

in this report.

The licensee

did not identify as proprietary

any information provided to, or reviewed by,

the inspectors.

'

DG

KV

RHR

TS

STP

ATTACHNENT 2

ACRONYHS

Diesel

Generator

Ki 1 o-volt

residual

heat

removal

Technical Specification

surveillance test procedure

I