ML16189A068
| ML16189A068 | |
| Person / Time | |
|---|---|
| Site: | Browns Ferry |
| Issue date: | 07/07/2016 |
| From: | Bono S Tennessee Valley Authority |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| NUREG 1843, Supplement 1 | |
| Download: ML16189A068 (1) | |
Text
Tennessee Valley Authority, Post Office Box 2000, Decatur, Alabama 35609-2000 July 7, 2016 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001
Subject:
Reference:
Browns Ferry Nuclear Plant, Unit 3 Renewed Facility Operating License No. DPR-68 NRC Docket No. 50-296 Completion of Activities to Support Entry Into the Period of Extended Operation NUREG 1843 Supplement 1, "Safety Evaluation Report Related to the 10 CFR 54 License Renewal of Browns Ferry Nuclear Plant Units 1, 2, and 3," dated April 2006 The referenced Safety Evaluation identified the commitments to the Nuclear Regulatory Commission (NRC) that are required to be completed prior to Browns Ferry Nuclear Plant, (BFN) Unit 3, entering the period of extended operation (POE) on July 2, 2016. BFN, Unit 3, License Condition 2.E states, in part, that certain future activities to be completed prior to the POE shall be completed no later than July 2, 2016, and that the Tennessee Valley Authority (TVA) shall notify the NRC in writing when implementation of these activities is complete and can be verified by NRC inspection.
Accordingly, TVA has completed the activities associated with commitments specified in the referenced safety evaluation required for entry into POE.
There are no new regulatory commitments contained in this letter. Should you have any questions concerning this submittal, please contact J. L. Paul, Browns Ferry Site Licensing Manager, at (256) 729-2636.
cc:
NRC Regional Administrator - Region II NRC Senior Resident Inspector - Browns Ferry Nuclear Plant