Independent Spent Fuel Storage Installation, Supplement 1 to Amendment Applications 264 and 249 Section 161A Preemption Authority
ML15092A132
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 03/31/2015
From: Thomas J. Palmisano
Southern California Edison Co
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
EA-13-092
Download: ML15092A132 (4)


Text

\\\\ISOUTHERN CALIFORNIA

~j EDISON An EDISON INTERNATIONAL& Company Thomas 1. Palmisano Vice President & Chief Nuclear Officer 10 CFR 50.90 42 USC 2201a March 31, 2015 ATTN: Document Control Desk U. S. Nuclear Regulatory Commission Washington D.C. 20555-0001

Subject:

Docket Nos. 50-361, 50-362 and 72-41 Supplement I to Amendment Applications 264 and 249 Section 161A Preemption Authority San Onofre Nuclear Generating Station Units 2 and 3 and Independent Spent Fuel Storage Installation

References:

1) Nuclear Regulatory Commission (NRC) Order EA-13-092 dated June 5, 2013, subject "Issuance of Order Designating an Interim Class of NRC-Licensed Facilities that Are Eligible to Apply to the Commission for Authorization to Use the Authority Granted Under the Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended and Associated Federal Register Notice" (ADAMS Accession No. ML13038A114)
2) Letter from D. R. Bauder (SCE) to Document Control Desk (NRC) dated August 28, 2013;

Subject:

Docket Nos. 50-361, 50-362 and 72-41, Amendment Applications 264 and 249, Section 161A Preemption Authority, San Onofre Nuclear Generating Station Units 2 and 3 and Independent Spent Fuel Storage Installation (ADAMS Accession No. ML13242A277)

3) Letter from T. J. Palmisano (SCE) to Document Control Desk (NRC), dated May 15, 2014;

Subject:

Docket Nos. 50-361 and 50-362, Responses to Requests for Additional Information on Federal Preemption, San Onofre Nuclear Generating Station, Units 2 and 3 (ADAMS Accession No. ML14139A424)

4) Letter from T. J. Palmisano (SCE) to Document Control Desk (NRC) dated February 10, 2015;

Subject:

Docket Nos. 50-361, 50-362 and 72-41, Supplement 1 to Amendment Applications 264 and 249, Section 161A Preemption Authority San Onofre Nuclear Generating Station Units 2 and 3 and Independent Spent Fuel Storage Installation (ADAMS Accession No. ML15044A0477)

Dear Sir or Madam:

Order EA-1 3-092 (Reference 1) defined the interim class of NRC-licensed facilities that are eligible to apply to the Commission for authorization to use preemption authority under Section 161A of the Atomic Energy Act of 1954, as amended (42 USC 2201 a), and the process to be used for such application.

P.O. Box 128 San Clemente, CA 92672 (949) 368-6575 PAX 86575 Fax: (949) 368-6183 Torn.Palniisano@sce.com ocj I~A

In accordance with Reference 1, Southern California Edison (SCE) applied pursuant to 10 CFR 50.90 by letter dated August 28, 2013 (Reference 2) for Commission authorization to use Section 161 preemption authority under 42 USC 2201a. By letter dated May 15, 2014 (Reference 3) SCE responded to questions from the NRC related to Reference 2. By letter dated February 10, 2015, SCE provided Supplement 1 to Reference 2.

In order to support NRC review of SCE's request, Enclosure 1 of this letter provides a consent and waiver form stating that SCE will consent to the terms and conditions of any Confirmatory Orders arising from the Reference 2 submittal and waive the right to request a hearing on all or any part of such a Confirmatory Order.

This letter does not contain any commitments.

If you have any questions or require additional information, please contact Ms. Andrea Sterdis at (949) 368-9985.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on:

3Z 3 ZZ-Z),)-

Sincerely, :

Consent and Waiver Form cc: M. L. Dapas, Regional Administrator, NRC Region IV T. J. Wengert, NRC Project Manager, SONGS Units 2 and 3 W. C. Allen, NRC Project Manager, SONGS ISFSI S. Hsu, California Department of Public Health, Radiologic Health Branch Consent and Waiver Form

CONSENT AND HEARING WAIVER FORM Southern California Edison Company hereby agrees to comply with the terms and conditions of the Confirmatory Orders arising out of the San Onofre Nuclear Generating Station submittal dated August 28, 2013, as supplemented by letters dated December 31, 2013, May 15, 2014, and February 10, 2015. By signing below, Southern California Edison Company consents to the issuance of the referenced Confirmatory Order, and by doing so, agrees to waive the right to request a hearing on all or any part of the Confirmatory Order.

Thomas J. Pa!s'sano Vice President and Chief Nuclear Officer Southern California Edison Company Date