Mitman, Jeffrey I
Mitman, Jeffrey
/
From:
Sent:
To:
Cc:
Subject:
Attachments:
Importance:
Mitman, Jeffrey \\ J Thursday, January 07, 2010 6:05 PM Galloway, Melanie James, Lois FW: Oconee Ext Flood Order Plan word (3).doc Oconee Ext Flood Order Plan word (3).doc High Melanie, if you've not yet seen this, you should definitely review it. It is my understanding (which is incomplete) that the "order team" will have two tasks. First, to put together a letter requesting more information. Second, write an order.
Jeff From: Khanna, Meena Sent: Thursday, January 07, 2010 5:37 PM To: James, Lois; Mitman, Jeffrey Cc: Wilson, George
Subject:
Oconee Ext Flood Order Plan word (3).doc Lois and Jeff, as promised, here is the document that lays out the "Order Team" and milestones... pIs note that the dates for the completion of the milestones are no longer valid since we are first planning to issue a letter.
I'll send out a scheduler for the meeting next week.
- Thanks, Meena 1
Oconee External Flooding Issue - NRR Plans for Issuance of Order Contacts for Issuance of Order:
DE: George Wilson and Meena Khanna DORL: John Stang and Gloria Kulesa DRA: Jeff Mitman Region 2: Jonathan Bartley OGC: Kimberly Sexton and Marcia Simon OE: Gerald Gulla and Nick Hilton Proposed Schedule for Issuance of Order:
Date Milestone/Task Week of January 4 Briefing of ET to get approval of path forward with Duke (letter or order)
Week of January 11 Meetings with all of the contacts identified above to discuss the Oconee external flooding issue, write letter or discuss basis for issuance of Order, issues to be addressed in the order, and language of the order.
Week of January 11 DE and DRA modify language of the adequate protection/backfit discussion.
January 13 DORL to provide DE with template with boilerplate language of the Order or letter.
January 15 DE, with support from DRA, as necessary, to provide technical input to DORL in support of the Order or letter.
Week of January 18 DRA and DE to meet to finalize adequate protection/backfit discussion.
Week of January 18 Briefing of EDO's office (Mallett and Borchardt) regarding NRR's plans to issue letter or Order to Duke.
January 22 DORL to consolidate input and develop draft Order or letter.
Week of January 25 Brief Commissioners and Commission TAs via walk-arounds (Dave Skeen)
February 3 Meeting with all contacts identified above to discuss draft letter or Order and make modifications as necessary.
February 5 DORL to issue draft letter or Order with mods to all contacts for final review.
February 9 DORL to incorporate comments from DE, DRA, OGC and OE.
February 11 DORL to issue draft letter or Order to SES management for review.
February 16 DORL to incorporate comments from SES management.
February 17 Meeting with all parties involved to discuss final revisions to draft letter or Order.
February 18 Provide draft letter or Order to Grobe, Boger, and Leeds for review.
February 22-25 Obtain concurrences from all offices, as 1
i appropriate February 26 Issue letter or Order Note: DORL to issue memo from Giitter to Leeds that reaffirms that JCO is okay based on the new information that we have today.
AOF/KICIALASE 0I/SECURITY-R LTED INF RMAT Proposed Issues to be Addressed in Order:
- 1. Duke is to provide the staff with its final Case of parameters and sensitivity analysis for its inundation analysis with the amount of flooding that will result from its analysis, which takes into consideration the Jocassee earthworks project, based on reasonable assurance.
- 2.
Duke is to continue to address this issue deterministically.
- 3.
Duke to address the justification for continued operation, including plans for interim repairs or mitigative actions, operating procedures, etc., and a schedule for the interim repairs to protect the site until final repairs are made to the site.
- 4.
Duke to follow 10 CFR 50.71(e) with regards to updating its UFSAR and revising its licensing basis to include the results of its analysis and any repairs made to its site in the future.
- 5.
Management meeting to be scheduled for end of January with Duke to discuss all issues, including tornado, HELB, NFPA-805, and the external flooding issue, and how they all fit together, impacts, and path forward in resolving the issues. (not sure if we need to include this) 2