March 4, 2013

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR THREE MILE ISLAND NUCLEAR STATION, UNIT 1 (REPORT 05000289/2012001)

Dear Mr. Pacilio:

On February 13, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance review of Three Mile Island Nuclear Station, Unit 1. The NRC reviewed the most recent quarterly performance indicators in addition to inspection results and enforcement actions from January 1, 2012 through December 31, 2012. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined that overall, Three Mile Island Unit 1 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the perfor-mance at Three Mile Island Unit 1 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all performance indicators demonstrated that your performance was within the nominal, expected range (i.e, green).

Therefore, the NRC plans to conduct Reactor Oversight Process baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through June 30, 2014. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. In addition to baseline inspections, the NRC will perform Inspection Procedure (IP) 71003, Post-Approval Site Inspection for License Renewal, and Temporary Instruction (TI) 182, Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence. In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (610)337-5046 with any questions you have regarding this letter.

Sincerely,

/RA/

Gordon K. Hunegs, Chief Projects Branch 6 Division of Reactor Projects

Docket Nos.: 50-289 License Nos.: DPR-50

Enclosure: Three Mile Island Inspection/Activity Plan

cc w/encl: Distribution via ListServ

ML13057A300 SUNSI Review

Non-Sensitive Sensitive

Publicly Available

Non-Publicly Available OFFICE RI/DRP RI/DRP

NAME mmt SBarber/GSB GHunegs/GKH

DATE 02/ 21 /13 02/ 26 /13

Page 1 of 2 01/30/2013 08:40:03 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Three Mile Island Inspection / Activity Plan 01/01/2013 - 06/30/2014 7111111B

- TMI REQUAL INSPECTION WITH P/F RESULTS

1 IP Licensed Operator Requalification Program 7111111B 03/11/2013 03/15/2013 HP

- EXPOSURE CONTROLS AND ALARA INSPECTION

1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 01/14/2013 01/18/2013

IP Occupational ALARA Planning and Controls 71124.02 01/14/2013 01/18/2013 EP EX

- EP EXERCISE EVALUATION

1 IP Exercise Evaluation - Hostile Action (HA) Event 7111407 04/15/2013 04/19/2013 HP

- RADIOACTIVITY & OC DOSE ASSESSMENT

1 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 04/15/2013 04/19/2013

IP Occupational Dose Assessment 71124.04 04/15/2013 04/19/2013 71124.08

- RADWASTE

1 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 06/03/2013 06/07/2013 HP

- RAD. ENV MONITORING PROGRAM

1 IP Radiological Environmental Monitoring Program 71124.07 06/10/2013 06/14/2013 7111117

- PERMANENT PLANT MODIFICATIONS

1 IP Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 7111117T 06/24/2013 06/28/2013

IP Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 7111117T 07/08/2013 07/12/2013 7111107T

- TRIENNIAL HEAT SINK

1 IP Heat Sink Performance 7111107T 08/12/2013 08/16/2013 71124

- RAD SAFETY INSPECTIONS

1 IP Radiation Monitoring Instrumentation 71124.05 09/09/2013 09/13/2013

IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 09/09/2013 09/13/2013 TI-182

- DEGRAD UNDERGROUND PIPING - PHASE 2

1 IP Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping 2515/182 10/07/2013 10/11/2013 HP

- HP OUTAGE INSP

1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 11/04/2013 11/08/2013

IP Occupational ALARA Planning and Controls 71124.02 11/04/2013 11/08/2013

IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 11/04/2013 11/08/2013

IP Occupational Dose Assessment 71124.04 11/04/2013 11/08/2013

IP Occupational Exposure Control Effectiveness 71151-OR01 11/04/2013 11/08/2013 71003

- LR COMMITMENTS PHASE 1-OUTAGE INSP

1 IP Post-Approval Site Inspection for License Renewal 71003 11/04/2013 11/08/2013 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 2 01/30/2013 08:40:03 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Three Mile Island Inspection / Activity Plan 01/01/2013 - 06/30/2014 7111108P

- INSERVICE INSPECTION

1 IP Inservice Inspection Activities - PWR 7111108P 11/04/2013 11/15/2013 HP

- EXPOSURE CONTROLS AND ALARA INSPECTION

1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 01/06/2014 01/10/2014

IP Occupational ALARA Planning and Controls 71124.02 01/06/2014 01/10/2014 TRI FI

- TRIENNIAL FIRE PROTECTION

1 IP Fire Protection [Triennial]

7111105T 01/27/2014 01/31/2014

IP Fire Protection [Triennial]

7111105T 02/10/2014 02/14/2014 EP PROG

- EP PROGRAM INSPECTION

1 IP Alert and Notification System Testing 7111402 02/03/2014 02/07/2014

IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 02/03/2014 02/07/2014

IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 02/03/2014 02/07/2014 71003

- LR COMMITMENT INSP PHASE 2

1 IP Post-Approval Site Inspection for License Renewal 71003 02/17/2014 02/21/2014

IP Post-Approval Site Inspection for License Renewal 71003 03/03/2014 03/07/2014 HP

- RADIOACTIVITY & OC DOSE ASSESSMENT

1 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 03/24/2014 03/28/2014

IP Occupational Dose Assessment 71124.04 03/24/2014 03/28/2014 71152B

- PI&R BIENNIAL

1 IP Problem Identification and Resolution 71152B 05/05/2014 05/10/2014

IP Problem Identification and Resolution 71152B 05/19/2014 05/24/2014 71124

- RAD SAFETY INSPECTIONS

1 IP Radiation Monitoring Instrumentation 71124.05 06/23/2014 06/27/2014 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.