{{#Wiki_filter:2012 POINT BEACH NUCLEAR PLANT INITAL LICENSE EXAMINATION MISCELLANEOUS CORRESPONDENCE

I UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 May 30,2012 Mr. Larry Meyer Site Vice President NextEra Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241

SUBJECT:

POINT BEACH NUCLEAR PLANT CONFIRMATION OF INITIAL LICENSE EXAMINATION

Dear Mr. Meyer:

In a telephone conversation on May 29,2012, between Mr. C. Zoia, Region III Examiner, and Mr. A. Zommers, Senior Training Instructor, arrangements were made for the administration of licensing examinations at the Point Beach Nuclear Plant during the weeks of December 3,2012, and December 10,2012. In addition, the U.S. Nuclear Regulatory Commission (NRC) will make an examination validation visit to your facility the week of November 5, 2012. As agreed during the telephone conversation, your staff will prepare the examinations based on the guidelines in Revision 9, Supplement 1, of NUREG-1 021, "Operator Licensing Examination Standards for Power Reactors." The NRC's regional office will discuss with your staff any changes that might be necessary before the examinations are administered. To meet the above schedule, it will be necessary for your staff to furnish the examination outlines by September 19, 2012. The written examinations, operating tests, and supporting reference materials identified in Attachment 3 to ES-201 will be due by October 19, 2012. Pursuant to Title 10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b }(3>>, an authorized representative of the facility licensee shall approve the outlines, examinations, and tests before they are submitted to the NRC for review and approval. All materials shall be complete and ready to use. We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Any delay in receiving the required examination and reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled. In order to conduct the requested written examinations and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the examination results are final.

L. Meyer -2 Appendix E of NUREG-1 021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered. To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator license applications (Office of Management and Budget (OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024), and waiver requests (if any) (OMB approval number 3150-0090) at least 30 days before the first examination date. If the applications are not received at least 30 days before the examination date, a postponement may be necessary. Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date. This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018. The public reporting burden for this collection is estimated to average 500 hours per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of these information collections, including suggestions for reducing the burden, to the Records and FOIAlPrivacy Services Branch (T -5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001. or by Internet electronic mail to INFOCOLLECTS@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018). Office of Management and Budget, Washington, DC 20503. The NRC may neither conduct nor sponsor, and a person is not required to respond to. a collection of information unless it displays a currently valid OMB control number. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html(the Public Electronic Reading Room). Thank you for your cooperation in this matter. Mr. A. Zommers has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. C. Zoia at 630-829-9863, or me at 630-829-9627. Sincerely, IRA! Tamara Bloomer, Acting Chief Operations Branch Division of Reactor Safety Docket Nos. 50-266 and 50-301 License Nos. DPR-24 and DPR-27 cc: Distribution via ListServ '

I L Meyer Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered. To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator license applications (Office of Management and Budget (OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024), and waiver requests (if any) (OMB approval number 3150-0090) at least 30 days before the first examination date. If the applications are not received at least 30 days before the examination date, a postponement may be necessary. Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date. This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018. The public reporting burden for this collection is estimated to average 500 hours per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of these information collections, including suggestions for reducing the burden, to the Records and FOIAlPrivacy Services Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail to INFOCOLLECTS@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503. The NRC may neither conduct nor sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html(the Public Electronic Reading Room). Thank you for your cooperation in this matter. Mr. A. Zommers has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. C. Zoia at 630-829-9863, or me at 630-829-9627. Sincerely, IRA! Tamara Bloomer, Acting Chief Operations Branch Division of Reactor Safety Docket Nos. 50-266 and 50-301 License Nos. DPR-24 and DPR-27 cc: Distribution via ListServ TM DISTRIBUTION See next page DOCUMENT NAME: LTR 053012 POINT BEACH CONFIRMATION OF INITIAL LICENSE EXAM.DOCX To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl liN". No co E RIII:DRS C. Zoia:cs T. Bloomer 05/30/12 05/30/12 OFFICIAL RECORD COPY

Letter to L. Meyer from T. Bloomer dated May 30,2012 SUB,JECT: POINT BEACH NUCLEAR PLANT CONFIRMATION OF INITIAL LICENSE EXAMINATION DISTRIBUTION: Shawn Williams RidsNrrDorlLpl3-1 Resource RidsNrrPMPointBeach RidsNrrDirslrib Resource Chuck Casto Cynthia Pederson Steven Orth Jared Heck Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak James McHale, NRR J. R. Kweiser, DRS

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 June 1,2011 Mr. Larry Meyer Site Vice President NextEra Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241

SUBJECT:

CONFIRMATION OF INITIAL OPERATOR LICENSE EXAMINATIONS: POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2

Dear Mr. Meyer:

We have received your letter dated July 20, 2010 (NRC 2010-0115). In that letter, you requested the initial operator licensing examinations scheduled for May of 2012 and May 2013 be cancelled. You also requested scheduling of initial operator licensing examinations for December 2012, November 2013, and for October 2014. In response, we have cancelled the May 2012 and May 2013 initial operator licensing examinations. We have also scheduled an initial operator licensing examination for the weeks of December 3 and 10, 2012, with an onsite validation date of November 12, 2012. We have scheduled an initial operator licensing examination for the weeks of November 18 and 25, 2013, with an onsite validation date of October 28, 2013. Additionally, we have scheduled an initial operator licensing examination for the weeks of November 3 and November 10, 2014, with an onsite validation date of the week of October 13, 2014. In the unlikely event that we are unable to support the examination during the scheduled weeks, we will inform you immediately upon discovery of such conditions and make arrangements to administer the examination at a mutually acceptable date. We understand that your staff will develop the examinations unless we determine it is necessary for the NRC to develop an examination in which case, we will notify you immediately upon discovery of that need. Because your letter indicated that there were more than nine applicants being considered for each of these examinations, the examinations were each scheduled for two weeks. Please inform us if the number of applicants decline below ten for any examination as this will impact the examination schedule. Also, please inform us at your earliest opportunity if you discover you need to change the scheduled dates for the examinations. A supplementary letter will be sent to the training department approximately 120 days prior to the examination informing the training manager of the chief examiner's name. The letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination date, and reconfirm the number of candidates you have in the training program.

L. Meyer -2 In accordance with 10 CFR 2.930 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publically Available Records System (PARS) component of !\\IRC's Agencywide Document Access and Management System (ADAMS), accessible from the NRC Web site at http://ww.nrc.gov/reading-rm/adams.html(the Public Electronic Reading Room). Sincerely, IRA by D. McNeil forI Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27 cc: Distribution via ListServ

L. Meyer -2 In accordance with 10 CFR 2.930 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room orfrom the Publically Available Records System (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS), accessible from the NRC Web site at http://ww.nrc.gov/reading-rm/adams.html{the Public Electronic Reading Room}. Sincerely, IRA by D. McNeil fori Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27 cc: Distribution via ListServ DISTRIBUTION: Daniel Merzke RidsNrrDorlLpl3-1 Resource RidsNrrPMPointBeach RidsNrrDirslrib Resource Steven West Steven Orth Jared Heck Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak Document Name: G:\\oRSIII\\DRS\\Work in Progress\\OL Exam Confirmation Lellers\\POI 060111 DRS OL Re Confirmation of Exam.docx o Publicly Available 0 Non-Publicly Available 0 Sensitive 0 Non-Sensitive of this document, Indicate in the box: 'C" Rill RKWalton:co HPeterson OM for OFFICIAL RECORD COpy 05/13/11 06/01/11

July 20,2010 NRC 20'10~O'11!5 RIG :;;>010"08 U.S. Nuclear Regulatory Commission ATIN: Document Control Desk Washington, DC 20555~0001 Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-266 and 50-301 Renewed License Nos. DPR-24 and DP~27 ResQonse to Regulatory Information SummarY 201 a-DB. "Preparation and Scheduling of Operator Licensing Examinations" On June 28,2010, the NRC issued Regulatory Issue Summary (RIS) 2010-08. RIG 2010-08 requests that each licensee provide an update of operator licensing examination information for calendar years 2011 through 2014. The enclosure to this letter provides the NextEra Energy Point Beach. llC, responr:;e for the Point Beach Nuclear Plant, Units 1and 2. During recent routine communications with representatives of the Region III Opera1or UGel1f)in~ Branch regarding examination scheduling, it was requested that NextEra formalize the proposecl changes. The changes are:

1. Release the May 2012 examination date Site Validation week of November 12, 2012 Examinations during the weeks of December 3 and 10, 2012
2. Release the May 2013 examination date Site Validation week of October 28, 2013 Examine the weeks of November 18 and 25, 2013 If there are questions associated with the content of the enclosures, please contaGt Mr. Douglas Lauterbur, Point Beach Nuclear Plant Training Manager, at 920/755~Tl91.

Very truly yours, NextEra Energy Point Beach, LlC ~~~~;~ Licensing Manager Enclosure cc: Administrator, Region III, USNRC Project Manager, Point Beach Nuclear Plant. USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC NextEra Energy Point Beach, llC. 6610 Nuclear Road, Two Rivers, WI 5424'1 -1'_

'-('Utb'~

JUL 2 1 2010

NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 1013112011 (10-2008) Esllmaled burden pBr res~onse to comply with this voluntary Information collecllon request: 1 hour. his Informallnn collection Is used to plan budgets OPERATOR LICENSING end resources for operator examinations. Send comments rer.-ardlnH burden estimate to the Records and FOtNPrlvacy Servlcos Branch -5 F 3), U.S. Nuclear Re?,ulatory Commission, WaShington, DC 20S55'{)OO, or bY, Internet EXAMINATION DATA a-mali 10 In ocottecls@nrc-g0v, and 10 the Desk Officer, Office of In ormation Bnd Regula!o~ Affairs, NE B-l0202, (3150-0131), Office of Managoment Bnd Budget, Wash nglon, DC 20503. If a moans used to Impose Rn Information CollBclion daBS nol display a currenlly valid OMB control number, the NRC may not conducl or s~onsor, and a person Is nol requlrad to raspond 10, the Information collcct on. FACILITY NRC REGION Point Beach Nuclear Plant Units 1 and 2 Dockets 50-266 and 50-301 III Renewed License Nos. DPR-24 and DPR-27 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2011 CY 2012 CY 2013 Cy 2014 ESTIMATED NUMBER OF LICENSEE-PREPARED 0 1 1 1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 1 0 0 0 EXAMINATIONS B. INITIAL OPERA TOR LICENSE EXAMINATIONS PROPOSED NUMBER CY 2011 CY 2012 CY2013 Cy 2014 NUMBER OF REACTOR 5 4 6 6 OPERATORS NUMBER OF SENIOR REACTOR 10 8 6 6 OPERATORS INSTANT NUMBER OF SENIOR REACTOR 0 0 0 0 OPERATORS-UPGRADE NUMBER OF SENIOR REACTOR 0 OPERATORS LIMITED 0 0 0 PROPOSED DATES PRIMARY DATE 04/25/2011 12/03/2012 11/18/2013 10/27/2014 ALTERNATE DATE 05/09/2011 01/07/2013 12/02/2013 11/10/2014

c. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 2011 Cy 2012 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED 12 0

O. 12 0 O. 0 NUMBER OF 0 CANDIDATES PRimED ON RECYCLED PAPER NRC FORM 536 (11)..2006)

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 February 19, 2010 Mr. Larry Meyer Site Vice-President NextEra Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241

SUBJECT:

CONFIRMATION OF INITIAL OPERATOR LICENSE EXAMINATIONS: POINT BEACH NUCLEAR PLANT

Dear Mr. Meyer:

In a letter dated August 17, 2009, (NRC 2009-0083), your staff responded to the NRC's Regulatory Issue Summary (RIS) 2009-11) and requested we schedule initial operator license examinations in April 2011, May 2012, and in May 2013, at the Point Beach Nuclear Plant. We have scheduled the examination requested to be conducted in April 2011 to begin the week of April 26, 2011. For the examination requested in May 2012, we have re-scheduled the examination you previously requested for February 2012 to an examination beginning the week of May 7, 2012. For the examination requested in May 2013, we have schedule the examination to begin the week of May 13, 2013. On-site validation of each of these examinations will occur approximately three weeks before the start of the examination. In the unlikely event that we are unable to support the examination during the scheduled weeks, we will inform you immediately upon discovery of such conditions and make arrangements to administer the examination at a mutually acceptable date. We have discovered it will be necessary for the NRC examiners to develop the written and operating test to be administered during the April 2011 initial license examination. The NRC chief examiner assigned to that examination has already contacted your initial license operator training program supervisor and explained our need to develop the examination. We understand your staff will develop the examinations scheduled during 2012 and 2013. Each of the scheduled examinations was scheduled for two weeks because your letter indicated each examination has more than nine applicants taking the examinations. Please inform us if the number of applicants declines below ten as this will impact the examination schedule. Please inform us at your earliest opportunity if you discover you need to change the scheduled dates for the examinations. A supplementary letter will be sent to the Point Beach Nuclear Plant's Training Department approximately 120 days prior to the initial examination informing the training manager of the chief examiner's name. The letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination dates, and reconfirm the number of candidates you have in the training program. If you have any questions concerning this information, please contact Mr. Dell McNeil of my staff at 630-829-9737.

L. Meyer -2 In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html(the Public Electronic Reading Room). Sincerely, IRA! Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27 cc: Distribution via ListServ

L. Meyer -2 In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html(the Public Electronic Reading Room). Sincerely, IRA! Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27 cc: Distribution via ListServ DISTRIBUTION: Susan Bagley RidsNrrDorlLpl3-1 Resource RidsNrrPMPointBeach RidsNrrDirslrib Resource Cynthia Pederson Steven Orth Jared Heck Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak DOCUMENT NAME: G:\\DRS\\Work in Progress\\POI 021910 DRS OL.doc o Publicly Available 0 Non-Publicly Available 0 Sensitive 0 Non-Sensitive To receive a COPl of this document, indicate in the box "C" = COpy w/o attach/encl "E" = Copy with attach/end "N" = No copy OFFICE RIII:DRS I RIII:DRS I RIII:DRS I I NAME JKweiser:co DMcNeil HPeterson DATE 02/18/10 02/18110 02119/10 OFFICIAL RECORD COpy

.~ " ~ August17,2009 NRC 2009-0083 RIS 2009-11 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-266 and 50-301 Renewed License Nos. DPR-24 and DPR-27 Response to Regulatory Information Summary 2009-11.. "Preparation and Scheduling of Operator Licensing Examinations" On July 16, 2009, the NRC issued Regulatory Issue Summary (RIS) 2009-11. RIS 2009-11 requests that each licensee provide an update of operator licensing examination information for calendar years 2010 through 2013. The enclosure to this letter provides the NextEra Energy Point Beach. LLC, response for the Point Beach Nuclear Plant, Units 1and 2. There are no new regulatory commitments or revisions to existing commitments contained in the enclosure of this letter. If there are questions associated with the content of the enclosures. please contact Mr. Douglas Lautenbur, Point Beach Nuclear Plant Training Manager, at 920/755:"7791. Very truly yours, NextEra Energy Point Beach, LLC ~~~c~t;rr-James Costedio Licensing Manager Enclosure cc: Administrator, Region III, USNRC Project Manager, Point Beach Nuclear Plant, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC NextEra Energy Point Beach, LLC, 6610 Nuclear Road, Two Rivers, WI 54241 ) / ~-c (;'1 Z. dc t..,£ ~ AUG 1 8 2009

ENCLOSURE NEXTERA ENERGY POINT BEACH, LLC POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 RESPONSE TO REGULATORY INFORMATION

SUMMARY

2009-11, "PREPARATION AND SCHEDULING OF OPERATOR LICENSING EXAMINATIONS" 1 page follows

NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION (10-2008) OPERATOR LICENSING EXAMINATION DATA APPROVED BY OMB: NO. 3150*0131 EXPIRES: 10131/2011 Estimated burden per res~onse to comply with this voluntary Information collection request: 1 hour. his Information coUeollon Is used 10 plan budgets end resources for operator examlnallons. Send comments rSfi'dlng buraen estimate to the Records and FOIAlPrlvaoy Services Brenoh oS F 3). U.S. Nuclear Re2ulatory CommiSSion. Washlnglon. DC 2066S..(JOO

  • or ~ Internet a*mall to In ocollects@nrc-gQV, and to the Dask Officer, Olllce of In ormaDon and Regulato~ Affairs, NE B*10202, (3150..(J131), Olllee of Mana~ement end Budget. Wash oglon DC 20503.

If a means used 10 Impose an nformatlon collection does not displaY a currenUy valid OMB control number, the NRC mey not conduct or seonsor, and a person Is nol required to respond to, the InformeUon collect on. FACIUTY Point Beach Nuclear Plant Units 1 and 2 6610 Nuclear Road Two Rivers, WI 54241 NRC REGION m A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY 2010 CY 2011 CY 201.2 CY 2013 ESTIMATED NUMBER OF LICENSEE-PREPARED EXAMINATIONS 0 1 1 1 ESTIMATED NUMBER OF NRC-PREPARED EXAMINATIONS 0 0 0 0 B. INITIAL OPERA TOR LICENSE EXAMINATIONS PROPOSED NUMBER CY 2010 Cy2011 CY2012 Cy2013-NUMBER OF REACTOR OPERATORS 0 5 4 6 NUMBER OF SENIOR REACTOR OPERATORS - INSTANT 0 13 (; (; NUMBER OF SENIOR REACTOR OPERATORS-UPGRADE 0 0 0 0 NUMBER OF SENIOR REACTOR OPERATORS - LIMITED 0 0 0 0 PROPOSED DATES PRIMARY DATE 04/25/2011 05/0712012 05/06/2013 ALTERNATE DATE 05/09/2011 0511412012 05/13/2013 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE PROPOSED NUMBER CY 2010 CY 2011 MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF CANDIDATES 0 0 0 10 0 0 0 12 NRC FORM 636 (10-2008) PRINTED ON RECYCLED PAPER

October 20,2008 Mr. Larry Meyer Site Vice President FPL Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241

SUBJECT:

CONFIRMATION OF INITIALlREQUALIFICATION OPERATOR LICENSE EXAMINATIONS: POINT BEACH NUCLEAR PLANT

Dear Mr. Meyer:

In a letter dated July 28,2008 (NRC 2008-0055), your staff requested we schedule initial operator license examinations in May 2009 and in February 2012 at the Point Beach Nuclear Plant. We have scheduled the examination requested to be conducted in May 2009 to begin the week of May 4,2009. We have scheduled the examination requested for February 2012 to begin the week of February 13, 2012. Your staff also requested an examination be scheduled during February 2011. This request is actually a change request to move a previously scheduled examination from May 2011 to February 2011. Unfortunately, we are unable to accommodate the examination requested in February 2011 due to a heavy examination load. After discussing available examination weeks, Mr. M. Durbin of your staff notified Mr. D. McNeil, NRC Senior Operations Engineer, that the proposed examination start week of March 21, 2011, would be acceptable examination start week. Therefore, an examination has been scheduled for the Point Beach Nuclear Plant beginning the week of March 21, 2011. On-site validation of each of these examinations will occur approximately three weeks before the start of the examination. In the unlikely event that we are unable to support the examination during the scheduled weeks, we will inform you immediately upon discovery of such conditions and make arrangements to administer the examination at a mutually acceptable date. We understand that your staff will develop the examination unless we determine it is necessary for the NRC to write the examination. Each of the scheduled examinations was scheduled for two weeks because your letter indicated each examination has more than nine applicants taking the examinations. Please inform us if the number of candidates for an examination declines below ten as this will impact the examination schedule. Please inform us at your earliest opportunity if you discover you need to change the scheduled dates for the examinations. A supplementary letter will be sent to the Point Beach Nuclear Plant's Training Department approximately 120 days prior to the initial examination informing the training manager of the chief examiner's name. The letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination dates, and reconfirm the number of candidates you have in the training program.

L. Meyer -2 We have scheduled a Licensed Operator Requalification Training Program Inspection (IP 71111.11) for the week of August 31,2009. Please inform us at your earliest opportunity if you discover this week is outside of your normally scheduled requalification training program's annual examinations. If you have any questions concerning this information, please contact Mr. Dell McNeil of my staff at 630-829-9737. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the Electronic Reading Room page of the NRC's public Web site at http://www.nrc.gov/reading-rm/adams.html. Sincerely, IRA! Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27 cc: M. Nazar, Senior Vice President and Nuclear Chief Operating Officer J. Stall, Executive Vice President, Nuclear and Chief Nuclear Officer A. Khanpour, Vice President, Engineering Support Licensing Manager, Point Beach Nuclear Plant M. Ross, Managing Attorney A. Fernandez, Senior Attorney M. Warner, Vice President, Nuclear Plant Support M. Gettler, Vice President, New Nuclear Projects W. Maher, Licensing Director, New Nuclear Projects T. O. Jones, Vice President, Nuclear Operations, Mid-West Region P. Wells, (Acting) Vice President, Nuclear Training and Performance Improvement J. McCarthy, Vice President, Point Beach Recovery J. Bjorseth, Plant General Manager K. Duveneck, Town Chairman Town of Two Creeks Chairperson Public Service Commission of Wisconsin J. Kitsembel, Electric Division Public Service Commission of Wisconsin P. Schmidt, State Liaison Officer

L. Meyer -2 We have scheduled a Licensed Operator Requalification Training Program Inspection (IP 71111.11) for the week of August 31, 2009. Please inform us at your earliest opportunity if you discover this week is outside of your normally scheduled requalification training program's annual examinations. If you have any questions concerning this information, please contact Mr. Dell McNeil of my staff at 630-829-9737. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the Electronic Reading Room page of the NRC's public Web site at http://www.nrc.gov/reading-rm/adams.html. Sincerely, IRA! Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27 cc: M. Nazar, Senior Vice President and Nuclear Chief Operating Officer J. Stall, Executive Vice President, Nuclear and Chief Nuclear Officer A. Khanpour, Vice President, Engineering Support Licensing Manager, Point Beach Nuclear Plant M. Ross, Managing Attorney A. Fernandez, Senior Attorney M. Warner, Vice President, Nuclear Plant Support M. Gettler, Vice President, New Nuclear Projects W. Maher, Licensing Director, New Nuclear Projects T. O. Jones, Vice President, Nuclear Operations, Mid-West Region P. Wells, (Acting) Vice President, Nuclear Training and Performance Improvement J. McCarthy, Vice President, Point Beach Recovery J. Bjorseth, Plant General Manager K. Duveneck, Town Chairman Town of Two Creeks Chairperson Public Service Commission of Wisconsin J. Kitsembel, Electric Division Public Service Commission of Wisconsin P. Schmidt, State Liaison Officer DISTRIBUTION See next page SEE PREVIOUS CONCURRENCES DOCUMENT NAME: G:\\DRS\\Work in Progress\\POl102008 DRS OL.doc o Publicly Available 0 Non-Publicly Available 0 Sensitive 0 Non-Sensitive or this documen RIII:DRS indicate in the box "e" = Co JKweiser:cco 10102/08 OFFICIAL RECORD COpy

Letter to Larry Meyer from Hironori Peterson, dated October 20, 2008

SUBJECT:

CONFIRMATION OF INITIAUREQUALIFICATION OPERATOR LICENSE EXAMINATIONS: POINT BEACH NUCLEAR PLANT DISTRIBUTION: Tamara Bloomer RidsNrrDorlLpl3-1 RidsNrrPMPointBeach RidsNrrDirslrib Resource Mark Satorius Kenneth Obrien Jared Heck Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak

Janet Kweiser From: Carmen Olteanu Sent: Wednesday, October 22, 2008 2:25 PM To: Tamara Bloomer; RidsNrrDorlLpl3-1 Resource; RidsNrrPMPointBeach Resource; RidsNrrDirslrib Resource; Mark Satorius; Kenneth OBrien; Jared Heck; Carole Ariano; Linda Unn; DRPIII; DRSIII; Patricia Buckley; Tammy Tomczak

Subject:

Point Beach Letter Re Confirmation of Initial Exam Attachments: POI 102008 DRS OLdoc The subject document has been completed and has been submitted to DPe to be declared in ADAMS. A Word copy of the document has been attached and the document has been assigned Accession

  1. ML082960707.

1

{"' t! "" I' ) I'.A:.~" j6'!":A'-{ fj FPL Energy Point Beach. LLC, 6610 Nuclear"Road. Two Rivers, WI 54241 I=PLEnergy Point Beach Nuclear Plant July 28, 2008 NRC 2008~0055 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-266 and 50-301 Renewed License Nos. DPR-24 and DPR-27 Response to Regulatorv Information Summary 2008-16, "Preparation and Scheduling of Operator Licensing Examinations" On June 27.2008, the NRC issued Regulatory Issue Summary (RIS) 2008-16. RIS 2008-16 requests that each licensee provide an update of operator licensing examination information for calendar years 2009 through 2012. The enclosure to this letter provides the FPL Energy Point Beach. LLC, response for the Point Beach Nuclear Plant. There are no new regulatory commitments or revisions to existing commitments contained in the enclosure of this letter. If there are questions associated with the content of the enclosures, please contact Mr. Charles Sizemore. Point Beach Nuclear Plant Training Manager, at 920/755-7791. Very truly yours. FPL Energy Point Beach, LLC Larry Meyer Site Vice President Enclosure An FPl Group company JUL 292008

ENCLOSURE FPL ENERGY POINT BEACH, LLC POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 RESPONSE TO REGULATORY INFORMATION

SUMMARY

2008-16, "PREPARATION AND SCHEDULING OF OPERATOR LICENSING EXAMINATIONS" 1 page follows

NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION (8*2005) OPERATOR LICENSING EXAMINATION DATA APPROVED BY OMB: NO. 3150*0131 EXPIRES: 0813112006 Estimated burden per response to comply with Ihis lIoluntary informalion collection request; 1 hour. This inlonnatlon collection Is used to plan budgets al1d resourcss for operator examinations. Send comments re~ardin~ burden estimate to Iha Records and FOIAIPriliacy Services Branch ( *5 F.3), U.S. Nuclear R~ulalory Commission. Washington, DC 20555-0001, or brc internet a-mail to in ocollects@nrc80v, and to tha Desk Officer, Office 01 In ormation and Regulatory Affairs, NE B*10202. (3150-0131). Off:ce of Management and Budget, Washington, DC 20503, If a means used 10 impose an Information collection does not display II curronUy valid OMS control number, toe NRC may not conduct or sponsor, and a person Is no! required 10 respond to, the information conectlon, FAClltlY Point Beach Nuclear Plant, Units 1 and 2 6610 Nuclear Road Two Rivers, WI 54241 NRC REGION III A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2009 CY2010 CY2011 Cy2012 eSTIMATED NUMBER OF LICENSEE-PREPARED EXAMINATIONS 1 0 1 1 ESTIMATED NUMBER OF NRC*PREPAREO EXAMINATIONS 0 0 0 0 B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY2009 CY2010-CY2011 CY2012 NUMBER OF REACTOR OPERATORS 2 0 5 4 NUMBER OF SENIOR REACTOR OPERATORS -INSTANT 7 0 12 6 NUMBER OF SENIOR REACTOR OPERATORS-UPGRADE 1 0 0 a NUMBER OF SENIOR REACTOR OPERATORS - LIMITED 0 0 0 a PROPOSED DATES PRIMARY DATE 05/04/2009 02/14/2011 02/1312012 ALTERNATE DATE 0511812009 02121/2011 02J20/2012 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE PROPOSED NUMBER CY 2009 CY 2010 MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF CANDIDATES 0 0 17 0 0 0 10 0 NRC FORM 536 (8-2005) PRINTED ON RECYClED PAPER}}