1 NRR-PMDAPEm Resource From:

Feintuch, Karl Sent:

Monday, March 19, 2012 12:49 PM To:

Swenzinski, Laura Cc:

Robinson, Jay

Subject:

ME6818 RE: DAEC 60/90 day matrix - RAI processing identifier syntax Attachments:

image001.jpg My plans for the numbering system became moot when I learned of an existing RAI tracking process meant for use with all NFPA-805 applicants. Jay Robinson provided the syntax we will use. The text of the email message describing the syntax:

(Wed 3/14/2012 6:51 PM, to 'Cross, William'; 'Swenzinski, Laura'; Cc to Robinson, Jay; Fields, Leslie; Lain, Paul) follows. Jay has not further commented. In addition, you and Bill can build on or append your identifier(s) to the NRCs identifier so that RAI processing is optimized for all three sets of needs (NRC, DAEC, FPL fleet).

=== Text of Wed 3/14/2012 6:51 PM message follows=====

I learned more about the NRC process this afternoon.

A. The coordinating lead is Jay Robinson. The NRC process can operate independent of your efforts, with the connecting point being an identifier that can be imbedded in whatever you use to track RAIs that you manage for Duane Arnold or later plants.

The NRC identifier (possibly with slightly different acronyms) was used to convey the first set of 90 RAI items The syntax of the identifier is:

XXXX-nn Where The digits nn start at 01, 02,25, And XXXX is SSD = Safe Shutdown PRA = Probabilistic Risk Analysis FPE = Fire Protection Engineering PROG = Programmatic RADR = Radiological Release FM = Fire Modeling MON = Monitoring Program Jays software will map this identifier to the proper plant for NRC purposes; you can append what you need to XXXX-nn for FPL purposes.

B. Paul showed me the summary email that you sent to him.

Please expand the distribution to include Leslie and myself.

One Portal Status Summary message per day is a good frequency.

Can you generate summary emails telling us that the XXXX-nn information identified for specific items has entered the portal that day (not just a generic message)?

Karl Feintuch 301-415-3079

====== end Text==========

From: Swenzinski, Laura [1]

Sent: Monday, March 19, 2012 11:15 AM To: Feintuch, Karl

Subject:

FW: DAEC 60/90 day matrix Hi Karl, In an earlier email, you said you planned to issue this table as another email ML. Do you still plan to do that and if so, when do you expect to? Thank you, V/R

2 Laura From: Swenzinski, Laura Sent: Wednesday, March 07, 2012 10:33 AM To: 'Feintuch, Karl'; 'leslie.fields@nrc.gov' Cc: Rubano, Vinny

Subject:

DAEC 60/90 day matrix Karl and Leslie, Attached is a simple matrix showing each RAI question number with its due date - April 23 for 60 days and May 23 for 90 days. Please let me know if you have any questions.

Laura B. Swenzinski Sr. Licensing Engineer NextEra Energy Duane Arnold laura.swenzinski@nexteraenergy.com (319) 851-7724

Hearing Identifier:

NRR_PMDA Email Number:

302 Mail Envelope Properties (Karl.Feintuch@nrc.gov20120319124900)

Subject:

ME6818 RE: DAEC 60/90 day matrix - RAI processing identifier syntax Sent Date:

3/19/2012 12:49:01 PM Received Date:

3/19/2012 12:49:00 PM From:

Feintuch, Karl Created By:

Karl.Feintuch@nrc.gov Recipients:

"Robinson, Jay" <Jay.Robinson@nrc.gov>

Tracking Status: None "Swenzinski, Laura" <Laura.Swenzinski@fpl.com>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 2912 3/19/2012 12:49:00 PM image001.jpg 3564 Options Priority:

Standard Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date:

Recipients Received:

Page 1 of 1 3/19/2012 file://c:\\EMailCapture\\NRR_PMDA\\302\\attch1.jpg