Letter Sequence Request |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
Results
Other: CNL-14-201, Response to Questions Regarding the Unit 1/Unit 2 As-Constructed Fire Protection Report, CNL-15-174, Submittal of Updated Pages for Unit 1/Unit 2 As-Constructed Fire Protection Report & License Condition 2.C(9) Addition Request, CNL-15-214, Updated Pages for As-Constructed Fire Protection Report, ML113500239, ML12207A080, ML13051A045, ML13081A002, ML13081A003, ML14265A449, ML15175A508
|
MONTHYEARML1000800082010-01-11011 January 2010 Notice of Forthcoming Conference Call with Tennessee Valley Authority Sequoyah Nuclear Plant, Units 1 & 2; Watts Bar Unit 1 Project stage: Request ML1001914212010-01-11011 January 2010 Final Safety Analysis Report, Amendment 97 Project stage: Request ML1013701862010-05-14014 May 2010 OL - FW: Call Summary - TVA Clarification Call Project stage: Request ML1015401332010-06-10010 June 2010 Request for Additional Information Regarding Licensees Final Safety Analysis Report Amendment Related to Accident Dose Project stage: RAI ML1019402362010-06-18018 June 2010 Instrumentation and Controls Staff Information Requests Project stage: Request ML1018201562010-06-18018 June 2010 OL - Updated Open Items List Project stage: Request ML1015402502010-06-24024 June 2010 Request for Additional Information Regarding Licensees Final Safety Analysis Report Amendment Related to Nuclear Performance and Code Review, Plant Systems, and Testing (Tac Nos. ME2731 and ME3091) Project stage: RAI ML1016002782010-07-12012 July 2010 Request for Additional Information Regarding Licensees Final Safety Analysis Report Amendment Related to Accident Dose Project stage: RAI ML1019506102010-07-30030 July 2010 Request for Additional Information, Licensees Final Safety Analysis Report Amendment Related to Chapters 3.9.1, 3.9.2, and 3.9.3 Project stage: RAI ML1019404742010-07-30030 July 2010 Request for Additional Information, Licensees Final Safety Analysis Report Amendment Related to Chapter 10.4.7 Project stage: RAI ML1026305982010-09-28028 September 2010 Request for Additional Information, Regarding Final Safety Analysis Report Related to Sections 3.2 and 5.2 Project stage: RAI ML1029901502010-10-26026 October 2010 Cancelled - Notice of Meeting with (Tva), to Discuss Responses to the NRC Requests for Additional Information (Rals) for Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Project stage: RAI ML1035401772010-12-20020 December 2010 Notice of Meeting with Tennessee Valley Authority to Discuss Watts Bar Nuclear Plant, Unit 2, Final Safety Analysis Report Related to Section 7 Instrumentation and Control Project stage: Request ML1036101142010-12-21021 December 2010 Submittal of Pre-op Test Instruction Project stage: Request ML1101401972011-01-14014 January 2011 Notice of Meeting with Tennessee Valley Authority to Discuss Watts Bar Nuclear Plant, Unit 2, Final Safety Analysis Report Related to Section 7 Instrumentation and Control Project stage: Request ML1102801282011-02-0909 February 2011 Request for Additional Information, Regarding Final Safety Analysis Report Amendment Related to Section 9.5.1 Fire Protection System Project stage: RAI ML1106107452011-03-10010 March 2011 Request for Additional Information, Regarding Final Safety Analysis Report Related to Section 9.5.1 Fire Protection Report - Round 2 Project stage: RAI ML1107705372011-03-16016 March 2011 Instrumentation and Controls Staff Information Requests Project stage: Request ML1109104642011-04-13013 April 2011 Summary of Meeting with Tennessee Valley Authority to Discuss Watts Bar Nuclear Plant, Unit 2, Final Safety Analysis Report Related to Section 9.5.1 Fire Protection Project stage: Meeting ML1109607652011-04-25025 April 2011 Request for Additional Information Regarding Final Safety Analysis Report Related to Section 9.5.1 Fire Protection Round 3 Project stage: RAI ML11129A1582011-05-0606 May 2011 Request for Additional Information Regarding Fire Protection Report, Project stage: Request ML11165A1452011-05-18018 May 2011 OL - Commitments and Sser Open Items Project stage: Request ML1112404832011-05-23023 May 2011 Request for Additional Information Regarding Final Safety Analysis Report Related to Section 9.5.1 Fire Protection Round 4 Project stage: RAI ML1115201192011-05-26026 May 2011 Response to Request for Additional Information Regarding Fire Protection Report Project stage: Response to RAI ML1114506732011-05-26026 May 2011 July 14, 2011 Notice of Forthcoming Meeting with Tennessee Valley Authority (TVA) to Discuss Bellefonte Nuclear Plant, Unit 1, Digital Instrumentation and Control and Human Factors Project stage: Request ML11161A1282011-06-0707 June 2011 Safety Evaluation Report Supplement 22 (Sser 22) - Second Response to NRC Required Action Items Project stage: Request ML1115109792011-06-0808 June 2011 Request for Additional Information Regarding Final Safety Analysis Report Related to Section 9.5.1 Fire Protection Round 5 Project stage: RAI ML11186A8642011-07-0101 July 2011 Submittal of Report in Accordance with 10 CFR 26.719(c)(1) for Drug and Alcohol Testing Errors Project stage: Request ML11200A1092011-07-14014 July 2011 Meeting Slides - TVA Phase 0 Meeting Bln/Nrc Bellefonte Digital I & C Upgrades Project stage: Request ML11200A1152011-07-14014 July 2011 Meeting Slides - TVA Phase 0 Meeting with NRC Bellefonte Units 1 & 2 Main Control Room Modernization Project stage: Request ML1118235802011-07-21021 July 2011 Request for Additional Information Regarding Final Safety Analysis Report Related to Section 9.5.1 Fire Protection Group 6 Project stage: RAI ML1120000992011-07-22022 July 2011 July 14, 2011 Summary of Pre-Application Meeting with Tennessee Valley Authority Regarding Digital Instrumentation and Control and Human Factors for the Potential, Proposed Updated Operating License Application at Bellefonte Nuclear Plant, Project stage: Meeting ML1120303872011-07-27027 July 2011 Request for Additional Information Regarding Incore Instrumentation System Project stage: RAI ML11215A1322011-07-29029 July 2011 Response to Request for Additional Information Regarding June 28, 2011 NRC Audit- Steam Line Break (Slb) and Other Miscellaneous RAIs Project stage: Response to RAI ML11227A2572011-08-0505 August 2011 Request for Additional Information (RAI) Group 6 Regarding Fire Protection Report Project stage: Request ML11230A3852011-08-15015 August 2011 Transmittal of Revised Unit 1 / Unit 2 As-Designed Fire Protection Report Project stage: Request ML1124904742011-09-14014 September 2011 Request for Additional Information Regarding Final Safety Analysis Report Related to Section 9.5.1 Fire Protection Group 7 Project stage: RAI ML11286A0352011-09-30030 September 2011 OL - Additional Draft RAI on Fire Protection - Group 8 Project stage: Request ML11286A0382011-09-30030 September 2011 OL - Draft RAIs on Fire Protection - Group 8 Project stage: Request ML13060A2252011-09-30030 September 2011 Response to Request for Additional Information Group 7 Regarding Fire Protection Report, (TAC No. ME3091) (Public Version) Project stage: Response to RAI ML11306A0902011-10-28028 October 2011 Response to Request for Additional Information Group 8 Regarding Fire Protection Report Project stage: Response to RAI ML11322A1032011-11-30030 November 2011 WCAP-17529-NP, Rev. 0, System Requirements Specification for the Common Q Post Accident Monitoring System Project stage: Request ML1135002392011-12-20020 December 2011 Audit Report of Fire Protection Relating to Final Safety Analysis Report Accident Analyses Project stage: Other ML12054A0622012-03-13013 March 2012 Summary of Public Meeting with Tennessee Valley Authority Regarding Watts Bar Nuclear Plant, Unit 2, Final Safety Analysis Report Related to Fire Protection Project stage: Request ML1207905812012-03-23023 March 2012 Request for Additional Information Regarding Final Safety Analysis Report Related to Section 9.5.1, Fire Protection Group 8 Project stage: RAI ML12142A0262012-05-17017 May 2012 OL - Request for Additional Information Regarding Fire Protection Review Group 10 Project stage: RAI ML12153A3742012-05-30030 May 2012 Watts, Unit 2, Response to Request for Additional Information Project stage: Response to RAI ML12181A5312012-06-27027 June 2012 Resolution of Concerns with Fire Protection Report (FPR) Operator Manual Action (OMA) 732 and Response to Requests for Additional Information Project stage: Response to RAI ML12207A0802012-07-19019 July 2012 Resolution of Concerns with Fire Protection Report Operator Manual Action 732 - Commitment Schedule Update Project stage: Other ML13051A0452013-02-14014 February 2013 Updated Response to NRC Bulletin 2011-01, Mitigation Strategies Project stage: Other 2011-05-23
[Table View] |
Text
Attachments 1 and 4 are to be withheld from public disclosure under 10 CFR 2.390.
When separated from these attachments, this letter is decontrolled.
Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 March 16, 2011 10 CFR 50.4 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391
Subject:
WATTS BAR NUCLEAR PLANT (WBN) UNIT 2 - INSTRUMENTATION AND CONTROLS STAFF INFORMATION REQUESTS
Reference:
- 1. Licensee Open Items to be Resolved for SER Approval List The purpose of this letter is to provide TVA's responses to NRC's information requests on the "Licensee Open Items to be Resolved for SER Approval List." Enclosure 1 to this letter provides TVA's responses to the information requested by NRC. contains the supporting documents for TVA's responses to NRC's requests/questions provided in Enclosure 1. Enclosure 3 provides the new regulatory commitment contained in this letter.
Attachments 1 and 4 contain information proprietary to Westinghouse Electric Corporation (WEC). TVA requests that the WEC proprietary information be withheld from public disclosure in accordance with 10 CFR § 2.390. Attachments 2 and 5 contain the corresponding non-proprietary versions of the documents. Attachments 3 and 6 contain the corresponding affidavits for withholding proprietary information from public disclosure.
U.S. Nuclear Regulatory Commission Page 2 March 16, 2010 I declare under penalty of perjury that the foregoing is true and correct. Executed on the 16th day of March, 2011.
If you have any questions, please contact William Crouch at (423) 365-2004.
Sincerely, David Stinson Watts Bar Unit 2 Vice President
Enclosures:
- 1. Responses to Licensee Open Items To Be Resolved For SER Approval
- 2.
List of Attachments
- 3. New Regulatory Commitment cc (Enclosures):
U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381
Enclosure I TVA Letter Dated March 16, 2011 Responses to Licensee Open Items to be Resolved for SER Approval For some NRC RAI requests, this letter provides TVA's initial response. For the other NRC RAI requests in this letter, a response has been provided in previous TVA letters to the NRC and the NRC has subsequently requested additional information. For these requests, the initial TVA response is not repeated below. The additional NRC information requests are identified in this letter as "Follow-up NRC Requests." TVA responses to these items are identified as "TVA Response to Follow-up NRC Request."
The following acronyms/abbreviations are used in this letter:
FAT Factory Acceptance Test FSAR Final Safety Analysis Report IV&V Independent Verification and Validation LTR Licensing Technical Report MTTR Mean Time To Repair NRC Nuclear Regulatory Commission PAMS Post Accident Monitoring System TVA Tennessee Valley Authority WBN2 Watts Bar Nuclear Unit 2 IEEE Institute of Electrical and Electronics Engineers Inc.
- 1.
NRC Request (Item Number 074)
By letter dated March 12, 2010 TVA stated that the target submittal date for the Post FAT IV&V Phase Summary Report was November 30, 2010.
TVA Response to NRC Request: contains WNA-VR-00283-WBT-P, "IV&V Summary Report for the Post Accident Monitoring System," Revision 4, dated March 2011 (proprietary). Attachment 2 contains WNA-VR-00283-WBT-NP, "IV&V Summary Report for the Post Accident Monitoring System," Revision 4, dated March 2011 (non-proprietary). Attachment 3 contains CWA-1 1-3121, Application for Withholding Proprietary Information from Public Disclosure, WNA-VR-00283-WBT-P, Revision 4 "Nuclear Automation IV&V Summary Report for the Post Accident Monitoring System" (Proprietary)," dated March 3, 2011.
- 2.
NRC Request (Item Number 212)
By letter dated June 18, 2010 (ML101940236) TVA stated (Enclosure 1, Attachment 3, Item No. 3) that the PAMS system design specification and software requirements specification contain information to address the "Design Report on Computer Integrity, Test and Calibration..." The staff has reviewed these documents, and it is not clear how this is the case.
(1) Please describe how the information provided demonstrates compliance with IEEE 603-1991 Clauses 5.5, 5.7, 5.10, & 6.5.
(2) Please describe how the information provided demonstrates conformance with IEEE 7-4.3.2-2003 Clauses 5.5 & 57.
1
Enclosure I TVA Letter Dated March 16, 2011 Responses to Licensee Open Items to be Resolved for SER Approval NRC Follow up Request:
(a) IEEE 603 Clause 5.5 basically states that conditions identified in IEEE 603 Clauses 4.7 & 4.8 must be addressed in the design. Energy supply conditions have not been identified, or explicitly addressed.
(b) WNA-AR-00189-WBT Rev. 0 Table 5-2 shows a MTTR of 7.2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. It is not clear how this satisfies the contractual item No. 179.
TVA Response to Follow-up NRC Request:
(a) Energy Supply conditions are specified in WNA-DS-01617-WBT-P, System Requirements Specification Rev. 4, Requirement 4.1-1 which requires 120Vac +/-10%
and 60+/-3Hz. Power to the Common Q PAMS is provided from the 120Vac vital power system. Per WBN Unit 2 FSAR section 8.3.1.1 the vital 120 volt ac system specifications are 120Vac +/-2% and 60+/-0.5Hz. Based on this, the power provided meets the system requirements.
Electromagnetic compatibility, seismic and environmental qualification of the equipment to meet the design basis requirements is documented in EQ-QR-68-WBT-P, Revision 0 "Qualification Summary Report for Post-Accident Monitoring System (PAMS)" (Proprietary) (Attachment 4). Attachment 5 contains EQ-QR-68-WBT-NP, Revision 0 "Qualification Summary Report for Post-Accident Monitoring System (PAMS)" (non-proprietary). Attachment 6 contains CWA-1 1-3118, Application for Withholding Proprietary Information from Public Disclosure, EQ-QR-68-WBT-P, Revision 0 "Qualification Summary Report for Post-Accident Monitoring System (PAMS)," (Proprietary), dated February 28, 2011.
(b) The Contract Compliance Matrix Item 179 in Revision 3 of the Licensing Technical Report will be revised to show this item as a deviation and to reflect TVA's acceptance of the 7.2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> MTTR value. WNA-LI-00058-WBT-P, "Post-Accident Monitoring System (PAMS) Licensing Technical Report," Revision 3, (proprietary) dated March 2011, will be submitted no later than March 29, 2011.
2 TVA Letter Dated March 16, 2011 Responses to Licensee Open Items to be Resolved for SER Approval List of Attachments
- 1.
Westinghouse Electric Company WNA-VR-00283-WBT-P, Revision 4 "Nuclear Automation IV & V Summary Report for the Post Accident Monitoring System" (Proprietary), dated March 2011
- 2.
Westinghouse Electric Company WNA-VR-00283-WBT-NP, Revision 4 "Nuclear Automation IV&V Summary Report for the Post Accident Monitoring System," dated March 2011 (non-proprietary)
- 3.
Westinghouse Electric Company CWA-1 1-3121, Application for Withholding Proprietary Information from Public Disclosure, WNA-VR-00283-WBT-P, Revision 4 "Nuclear Automation IV&V Summary Report for the Post Accident Monitoring System" (Proprietary)," dated March 3, 2011
- 4.
Westinghouse Electric Company EQ-QR-68-WBT-P, Revision 0 "Qualification Summary Report for Post-Accident Monitoring System (PAMS)" (Proprietary), dated February 2011
- 5.
Westinghouse Electric Company EQ-QR-68-WBT-NP, Revision 0 "Qualification Summary Report for Post-Accident Monitoring System (PAMS)" (non-proprietary), dated February 2011
- 6.
Westinghouse Electric Company CWA-1 1-3118, Application for Withholding Proprietary Information from Public Disclosure, EQ-QR-68-WBT-P, Revision 0 "Qualification Summary Report for Post-Accident Monitoring System (PAMS)," (Proprietary), dated February 28, 2011 1
TVA Letter Dated March 16, 2011 Responses to Licensee Open Items to be Resolved for SER Approval New Regulatory Commitment WNA-LI-00058-WBT-P, "Post-Accident Monitoring System (PAMS) Licensing Technical Report,"
Revision 3, (proprietary) dated March 2011, will be submitted no later than March 29, 2011.