ML103060112

From kanterella
Jump to navigation Jump to search
Submittal of Pre-op Test Instruction, 2-PTI-286-01, Rev 0, Permanent Hydrogen Mitigation System
ML103060112
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 10/28/2010
From: Bajestani M, Ballard R
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
2-PTI-268-01, Rev 0
Download: ML103060112 (125)


Text

Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 October 28, 2010 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391

Subject:

Watts Bar Nuclear Plant (WBN) Unit 2 - Submittal of Pre-op Test Instruction The following approved WBN Unit 2 Pre-op Test Instruction (PTI) is enclosed:

PTI NUMBER Rev.

TITLE 2-PTI-268-01 0

Permanent Hydrogen Mitigation System If you have any questions, please contact Pete Olson at (423) 365-3294.

Sincerely, Masoud ajstani Wafts Ba nit 2Vice President

U.S. Nuclear Regulatory Commission Page 2 October 28, 2010 cc (Enclosure):

U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381

WATTS BAR NUCLEAR PLANT UNIT 2 STARTUP TITLE: Permanent Hydrogen Mitigation System Instruction No: 2-PTI-268-01 Revision No: 0000 PREPARED BY:

REVIEWED BY:

Regina Ballard ICVR

,VAL(

PRINT "E/

SIGNATURE A. Blake Lowe 1A DATE

(

L-to DATE_

PRINT NAME/ SIGNATURE INSTRUCTION APPROVAL JTG MEETING

/0.0 JTG CHAIRMA APPROVED BY:

PREOPERATIONAL STARTUP MANAGEF DATE'V')

I \\i DATE I fa R

TEST RESULTS APPROVAL JTG MEETING NO:

JTG CHAIRMAN:

APPROVED BY:

DATE DATE PREOPERATIONAL STARTUP MANAGER SMP-8.0, R4, Administration of Preoperational Test Instructions, Appendix B

Revision Log Revision Affected or Change Effective Page Number Date Numbers Description of Revision/Change 0000 loliqhv ALL INITIAL ISSUE

Table of Contents

1.0 INTRODUCTION

4 1.1 Test Objectives.............................................................................................................

4 1.2 Scope................................................................

I........................................................

4

2.0 REFERENCES

5 2.1 Performance References.........................................................................................

5 2.2 Developmental References............................... !.......................................................

5 3.0 PRECAUTIONS AND LIMITATIONS.......................................................................

9 4.0 PREREQUISITE ACTIONS.....................................................................................

10 4.1 Preliminary Actions...............................................................................................

10 4.2 Special Tools, Measuring and Test Equipment (M&TE), Parts, and Supplies......................................................................................................................

13 4.3 Field Preparations..........................................................

14 4.4 Approvals and Notifications...................................................................................

15 5.0 ACCEPTANCE CRITERIA....................................................................................

16 6.0 PERFORMANCE...................................................................................................

19 6.1 PHMS Control and Alarm Function Tests...............................................................

19 6.2 Hydrogen Igniter Functional Tests - Train A...........................................................

63 6.3 Hydrogen Igniter Functional Tests - Train B...........................................................

91 7.0 POST PERFORMANCE ACTIVITIES..................................................................... 119 8.0 RECORDS................................................................................................................

119 Appendix A:

TEST PROCEDURES/INSTRUCTIONS REFERENCE REVIEW..................................................................................................

120 Appendix B:

TEMPORARY CONDITION LOG.............................................................

121 Table 1:

TEMPERATURE CONVERSION CHART................................................

122

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 4 of 123 Data Package: Page of Date

1.0 INTRODUCTION

1.1 Test Objectives The purpose of this test instruction is to verify that the Hydrogen Igniters will provide ignition sources of a specified minimum surface temperature without exceeding a designated maximum input power requirement by energizing each igniter circuit and verifying the voltage, current, and igniter surface temperature.

1.2 Scope A.

This test demonstrates the functionality of the Permanent Hydrogen Mitigation system by ensuring the igniters reach a minimum surface temperature of 1700OF and the power requirement for each Hydrogen Igniter circuit does not exceed 663 watts.

B.

The 68 igniters are equally divided into 2 redundant groups, each with independent and separate controls, power supplies and locations.

1.

38 Train A and Train B igniters located in the lower compartment of containment.

2.

30 Train A and Train B igniters located throughout the upper compartment of containment and the upper plenum of the ice condenser.

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 5 of 123 Data Package: Page

-of Date

2.0 REFERENCES

2.1 Performance References A.

SMP-9.0, Conduct of Test B.

SPP-10.11, Control of Ignition Sources (Hot Work) 2.2 Developmental References A.

Final Safety Analysis Report (FSAR)

1.

FSAR-Amendment 100

a.

FSAR Table 14.2-1, Sheet 40 of 89, Combustible Gas Control Systems Test Summary

b.

FSAR Chapter 6, Section 6.2.5A, Hydrogen Mitigation System B.

Drawings

1.

Flow Diagrams None

2.

Electrical Drawings

a.

45W2770-7, Rev 4, Wiring Diagrams 480V Cont & Aux Bldg Vent Bd 2A1-A Connection Diagrams, AD DRA 52348-031, Rev 0 DRA 52348-032, Rev 0

b.

45B2770-9E, Rev 5, Wiring Diagrams 480V C & A Bldg Vt Bd 2A1-A, Conn Diag - Compt 9E, AD DRA 53290-010, Rev 0

c.

45W2772-7, Rev 4, Wiring Diagrams 480V Cont & Aux Bldg Vent Bd 2B1-B Connection Diagrams, AD DRA 52348-033, Rev 0 DRA 52348-034, Rev 0

d.

45B2772-12C, Rev 4, Wiring Diagrams 480V C & A Bldg Vt Bd 2B1-B, Conn Diag.- Compt 12C, AD DRA 53290-037, Rev 0

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 6 of 123 Data Package: Page

-of Date 2.2 Developmental References (continued)

e.

45W2649-2, Rev 10, Wiring Diagrams Unit Control Board, Panel 2-M-10 Connection Diagrams, Sheet 2, AD

f.

2-45W2656-4, Rev 0, Wiring Diagrams Unit Control Board, Panel 2-M-21 Connection Diagrams, Sheet 4, CC DRA 52315-077, Rev 0

g.

2-45W756-2, Rev 0, Wiring Diagrams 480V Cont & Aux Bldg Vt Bd 2A1-A Single Line, Sheet 2, CC

h.

2-45W756-6, Rev 0, Wiring Diagrams 480V Cont & Aux Bldg Vt Bd 2B1-B Single Line, Sheet 2, CC

i.

2-45W760-268-1, Rev 0, Wiring Diagram Permanent Hydrogen Mitigation Sys Schematic Diagrams, CC DRA 52348-028, Rev 0 DRA 52348-029, Rev 0 DRA 52348-030, Rev 0 DRA 53290-050, Rev 0 DRA 53290-069, Rev 0

j.

2-45B655-5C, Rev 0, Main Control Room Annunciator Inputs Window Box, XA-55-5C, CC

k.

2-45B655-E5C, Rev 0, Electrical Annunciator Window Box XA-55-5C Engraving (Contract Number 75554B), CC

3.

Mechanical None

4.

Logic/Control None

5.

Other

a.

45W872-2, Rev 23, Conduit & Grounding Floor El. 716.0 Ceiling Plan, AD DRA 52348-002, Rev 0

b.

45W872-8, Rev 27, Conduit & Grounding El. 716.0 Details, Sheet 6, AD DRA 52348-003

Data Package: Page

-of Date 2.2 Developmental References (continued)

c.

45W872-9, Rev 33, Conduit & Grounding Floor El. 716.0 Details, Sheet 7, AD DRA 52348-004

d.

45W872-10, Rev 36, Conduit & Grounding Floor El. 716.0 Details, Sheet 8, AD DRA 52348-005

e.

45W872-11, Rev 28, Conduit & Grounding Floor El. 716.0 Details, Sheet 9, AD DRA 52348-006

f.

45W872-16, Rev 17, Conduit & Grounding Floor El. 716.0 Details, Sheet 14, AD DRA 52348-007

g.

45W872-18, Rev 25, Conduit & Grounding Floor El. 716.0 Details, Sheet 16, AD DRA 52348-008

h.

45W872-19, Rev 23, Conduit & Grounding Floor El. 716.0 Details, Sheet 17, AD DRA 52348-009

1.

45W874-2, Rev 22, Conduit & Grounding Floor El. 744.5 Ceiling Plan, AD DRA 52348-010

j.

45W874-9, Rev 9, Conduit & Grounding Floor El. 744.5 Details, Sheet 7, AD DRA 52348-011

k.

45W876-2, Rev 23, Conduit & Grounding El. 756.63 Ceiling Plan, AD DRA 52348-012 I.

45W876-4, Rev 18, Conduit & Grounding El. 756.63 Details, Sheet 2, AD DRA 52348-013

m. 45W876-7, Rev 19, Conduit & Grounding El. 756.63 Details, Sheet 5 DRA 52348-014
n.

45W876-8, Rev 13, Conduit & Grounding El. 756.63 Details, Sheet 6, AD DRA 52348-015

Data Package: Page of Date 2.2 Developmental References (continued)

o.

45W876-9, Rev 6, Conduit & Grounding El. 756.63 Details, AD DRA 52348-016

p.

45W876-10, Rev 7, Conduit & Grounding El. 756.63 Details, AD DRA 52348-017

q.

45W876-1 1, Rev 4, Conduit & Grounding El. 756.63 Details, AD DRA 52348-018

r.

45W876-12, Rev 7, Conduit & Grounding El. 756.63 Details, AD DRA 52348-019

s.

45W878-2, Rev 8, Conduit & Grounding Dome Plan, AD DRA 52348-020

6.

Vendor Drawings

a.

193-3442-4, Rev D, Igniter Assembly, Tayco Engineering Inc.,

Contract 829810

b.

F9275200001S, Rev 4, 3 Phase Line Regulator 3RTF-480/120-208-30, Power Conversion Products Inc, Contract 830802.

c.

7003-51051-53, Rev B, Electrical Schematic 120V Distribution Cabinet, Nutherm International Inc, Contract 830137.

C. Vendor Manuals

1.

WBN-VTM-N431-0090, Rev 5, Vendor Technical Manual for Nuthem International Power Distribution Panels, Contract Number 81-827910

2.

WBN-VTM-P319-0010, Rev 0, Vendor Technical Manual for Power Conversion Products, Inc. Three-Phase Regulating Transformers, Contract Number 82K05-00830802 D.

Documents

1.

2-TSD-268-01, Rev 0, Permanent Hydrogen Mitigation System Test Scoping Document

2.

WBN2-83-4001, Rev 0, System Description for Combustible Gas Control System

3.

L44850214800, Letter to NRC from TVA concerning surveillance requirements for demonstrating the functionality of hydrogen igniters

Data Package: Page

-of Date 3.0 PRECAUTIONS AND LIMITATIONS A.

Standard precautions shall be followed for working around energized electrical equipment in accordance with TVA Safety Manual Procedure 1021.

B.

Steps may be repeated if all components cannot be tested in a step. However, if the test has been exited, prerequisite steps must be re-verified and a Chronological Test Log (CTL) entry made.

C.

Component tags and labels may differ slightly (abbreviations, punctuation, letter case, etc.) from the description given in this test. If this situation occurs, it shall NOT be considered a test deficiency or procedure deviation. It shall be documented in the CTL and reconciled by way of a plant labeling request or drawing discrepancy or single-line date typo change in the procedure as appropriate.

D.

All wires removed/lifted from a terminal shall be identified and taped or covered with an insulator to prevent personnel or equipment hazard and possible spurious initiations. The wires should be grouped together and labeled with the work implementing document number that required them to be lifted if left unattended.

E.

All terminal points and connection are to be considered energized.

Instrumentation must be used to determine if the circuits are de-energized.

F.

All open problems are to be tracked by a corrective action document and entered on the appropriate system punchlist.

G.

Problems identified during the test shall be annotated on the Chronological Test Log (CTL) from SMP-9.0 including a description of the problem, the procedure step when/where the problem was identified, corrective action steps taken to resolve the problem, and the number of the corrective action document, if one was required.

H. Observe all Radiation Protection (RP) requirements when working in or near radiological areas.

I.

Figures 1 through 5 provide locations of the 68 hydrogen igniters in the containment. The figures may be marked up during test conduct, as required.

For example, as each igniter is located and the required temperature measurement is completed, place a check mark at the igniter location symbol.

J.

Ensure no adverse impact to the operation of Unit I structures, systems or components.

Data Package: Page

-of Date 4.0 PREREQUISITE ACTIONS NOTE Preliminary action steps may be performed in any order with Test Directors approval.

4.1 Preliminary Actions

[1]

VERIFY the test/performance copy of this Preoperational Test Instruction (PTI) is the current revision and as needed, each test person assisting in this test has the current revision.

[2]

OBTAIN copies of the applicable forms from the latest revision of SMP-9.0, AND ATTACH to this PTI for use during the performance of this PTI.

[3]

ENSURE changes to the references listed on 'Test Procedure and Instruction Reference Review", Appendix A, have been reviewed, and determined NOT to adversely affect the test performance.

[4]

VERIFY current revision and change paper for referenced drawings has been reviewed and determined NOT to adversely affect the test performance, AND ATTACH documentation of current drawing revision numbers and change paper that were reviewed to the data package.

[5]

EVALUATE Open items in Watts Bar Integrated Task Equipment List (WITEL), AND ENSURE that they will NOT adversely affect the test performance.

[6]

ENSURE required Component Testing has been completed prior to start of test.

[7]

ENSURE outstanding Design Change Notices (DCN's),

Engineering Document Construction Release (EDCR's) or Temporary Alterations (TA's) do NOT adversely impact testing.

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 11 of 123 Data Package: Page

-of Date 4.1 Preliminary Actions (continued)

[8]

ENSURE a review of outstanding Clearances has been coordinated with Operations for impact to the test performance, AND RECORD in Appendix B, Temporary Condition Log if required.

[9]

VERIFY Measuring and Test Equipment (M&TE) required for test performance has been (as required) filled, vented, place in service and recorded on Measuring and Test Equipment Log in SMP-9.0.

A.

Subsection 6.1 B.

Subsection 6.2 C.

Subsection 6.3

[10]

VERIFY Measuring and Test Equipment (M&TE) calibration due dates will support the completion of this test performance.

A.

Subsection 6.1 B.

Subsection 6.2 C.

Subsection 6.3

[11]

VERIFY the following system is operational and have been placed in service to the extent necessary to perform this test:

A.

System 214, 480V Control & Aux (C&A) Bldg Vent Boards 2-MCC-214-Al -A (Board 2A1 -A), 2-BKR-214-B/19E-B B.

System 214, 480V Control & Aux (C&A) Bldg Vent Boards 2-MCC-214-B1-B (Board 2B1-B), 2-BKR-214-Bi/12C-B

[12]

ENSURE components contained within the boundaries of this test are under the jurisdictional control of Preoperational Startup Engineering (PSE) or Plant Operations.

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 12 of 123 Data Package: Page

-of Date 4.1 Preliminary Actions (continued)

[13]

VERIFY System 55, Annunciator and Sequential Events Recording System, TBK switches and the Master switch associated with the following annunciator window inputs are in the ON position, AND VERIFY the annunciator window, 2-XA-55-5C/1 02-C, software inputs are ENABLED.

NOTE Inspect for combustibles within two feet of igniters during pretest walk down. Line of sight view of each igniter (profile or oblique) should be noted as required to facilitate thermography measurements as well as requirements for ladders and/or scaffolding.

[14]

PERFORM a pretest walkdown on equipment to be tested to ensure no conditions exist that will impact test performance.

A.

Subsection 6.1 B.

Subsection 6.2 C.

Subsection 6.3

[15]

ENSURE a Hot Work Permit which allows energization of the Hydrogen Igniters in the Containment has been obtained.

(See Control of Ignition Sources (Hot Work), SPP 10.11)

[16]

CONDUCT a pretest briefing with Test and Operations personnel in accordance with SMP-9.0.

[17]

ENSURE that communications are available for areas where testing is to be conducted.

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 13 of 123 Data Package: Page

-of Date 4.2 Special Tools, Measuring and Test Equipment (M&TE), Parts, and Supplies

[1]

ENSURE the following are available:

2 Jumpers

[2]

ENSURE following M&TE or equivalent is available and within their calibration due dates, AND RECORD the M&TE data on SMP-9.0, Measuring and Test Equipment (M&TE) Log.

Voltmeter, Minimum Range 0 to 150 Vac, Required Accuracy +/-0.5 Volts.

Optical/Infrared Pyrometer, Mikron Model - M90V or Equivalent, Minimum Range 15000 to 20000F, Required Accuracy +/-340F.

Optical/Infrared Pyrometer, Minimum Range 1420° to 25001F, Required Accuracy +/-340F.

Clamp-on Ammeter, Minimum Range 0 to 10 amperes, Required Accuracy +/-0.25 amperes.

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 14 of 123 Data Package: Page of Date 4.3 Field Preparations

[1]

ENSURE the following Handswitches at MCR Panel 2-M-10 are in the OFF position:

A.

Handswitch 2-HS-268-73, H2 IGNITERS GROUP A.

B.

Handswitch 2-HS-268-74, H2 IGNITERS GROUP B.

[2]

VERIFY that required ladders and/or scaffolding are installed (if required) to facilitate thermography measurements.

A.

Subsection 6.2 B.

Subsection 6.3

[3]

VERIFY that each Hydrogen Igniters has been energized continuously for a period of at least 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> and allowed to cool to ambient temperature following installation to ensure that any protective factory coating has been burned off the igniters, AND RECORD method of this verification in the Chronological Test Log. (Subsections 6.2 & 6.3)

Data Package: Page of Date 4.4 Approvals and Notifications

[1]

OBTAIN permission of the Preoperational Startup Manager to start the test.

Preoperational Startup Manager Signature

[2]

OBTAIN Shift Manager's (SM) authorization.

Date SM Signature Date

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 16 of 123 Data Package: Page

-of Date 5.0 ACCEPTANCE CRITERIA NOTE Acceptance criteria values of 1325 Watts and 1700OF as listed in the Permanent Hydrogen Mitigation System Test Scoping Document, 2-TSD-268-01, are adjusted to account for M&TE tolerances.

[1]

Each igniter maintains a minimum surface temperature of 1734°F while not exceeding 1275 Watts, the maximum power requirement for two igniters.

A.

Train A Igniters:

Steps 6.2[64] and 6.2[65]

B.

Train B Igniters:

Steps 6.3[64] and 6.3[65]

[2]

Record the voltage and current for each circuit at the Distribution Panels:

A.

Train A Distribution Panel, 2-DPL-268-1 -A:

Step 6.2[29]

B.

Train B Distribution Panel, 2-DPL-268-2-B:

Step 6.3[29]

[3]

Each train can be energized from the Main Control Room.

A.

Train A Igniters 6.1[165.2]

B.

Train B Igniters 6.1(169.2]

[4]

Indicating lights indicate the correct status of each igniter train in the Main Control Room.

A.

Train A Igniters Steps 6.1[164] and 6.1[165.1]

B.

Train B Igniters Steps 6.1[168] and 6.1[169.1]

[5]

Annunciator "PHMS PWR DIST. PNL. A/B UV/BKR TRIP" alarms on:

[5.1]

Handswitch in "ON" and undervoltage.

A.

Train A:

Steps 6.1[46.1] and 6.1[46.2]

B.

Train B:

Steps 6.1[48.1] and 6.1[48.2]

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 17 of 123 Data Package: Page

-of Date 5.0 ACCEPTANCE CRITERIA (continued)

[5.2]

Distribution Panel supply circuit breaker open.

A.

Train A - Distribution panel, 2-DPL-268-1-A, supply breaker, 2-BRK-268-1/M 1-A:

Step 6.1[122]

B.

Train B - Distribution panel 2-DPL-268-2-B, supply breaker, 2-BKR-268-2/Ml-B:

Step 6.1[124]

[5.3]

Distribution Panel output circuit breaker 1 through 18 trip.

[5.3.1]

Train A - Distribution panel, 2-DPL-268-1-A, output breakers:

A.

B.

C.

D.

E.

F.

G.

H.

I.

J.

K.

L.

M.

N.

0.

P.

2-BKR-268-1/1-A:

2-BKR-268-1/2-A:

2-BKR-268-1/3-A:

2-BKR-268-1/4-A:

2-BKR-268-1/5-A:

2-BKR-268-1/6-A:

2-BKR-268-1/7-A:

2-BKR-268-1/8-A:

2-BKR-268-1/9-A:

2-BKR-268-1 /10-A:

2-BKR-268-1/11-A:

2-BKR-268-1/12-A:

2-BKR-268-1/13-A:

2-BKR-268-1/14-A:

2-BKR-268-1/15-A:

2-BKR-268-1/16-A:

Step 6.1[50]

Step 6.1[52]

Step 6.1[54]

Step 6.1[56]

Step 6.1[58]

Step 6.1[60]

Step 6.1[62]

Step 6.1[64]

Step 6.1[66]

Step 6.1[68]

Step 6.1[70]

Step 6.1[72]

Step 6.1[74]

Step 6.1[76]

Step 6.1[78]

Step 6.1[80]

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 18 of 123 Data Package: Page

-of Date 5.0 ACCEPTANCE CRITERIA (continued)

Q.

2-BKR-268-1/17-A:

Step 6.1[82]

R.

2-BKR-268-1/18-A:

Step 6.1184]

[5.3.2]

Train B - Distribution panel, 2-DPL-268-2-B, output breakers:

A.

2-BKR-268-2/1-B:

Step 6.1[86]

B.

2-BKR-268-2/2-B:

6.1[88]

C.

2-BKR-268-2/3-B:

6.1[90]

D.

2-BKR-268-2/4-B:

6.1[92]

E.

2-BKR-268-2/5-B:

6.1[94]

F.

2-BKR-268-2/6-B:

6.1[96]

G.

2-BKR-268-2/7-B:

6.1[98]

H. 2-BKR-268-2/8-B:

6.1[100]

I.

2-BKR-268-2/9-B:

6.1[102]

J.

2-BKR-268-2/10-B:

6.1[104]

K. 2-BKR-268-2/11-B:

6.1[106]

L.

2-BKR-268-2112-B:

6.1[108]

M. 2-BKR-268-2/13-B:

6.1[110]

N. 2-BKR-268-2/14-B:

6.1[112]

0. 2-BKR-268-2/15-B:

6.1[114]

P.

2-BKR-268-2/16-B:

6.1[116]

Q.

2-BKR-268-2/17-B:

6.1[118]

R.

2-BKR-268-2/18-B:

6.1[120]

Data Package: Page of Date 6.0 PERFORMANCE 6.1 PHMS Control and Alarm Function Tests

[1]

ENSURE precautions and limitations in Section 3.0 have been reviewed.

[2]

VERIFY prerequisites listed in Section 4.0 for Subsection 6.1 have been completed.

[3]

ENSURE the following PHMS Supply Breaker, Breaker 2-BKR-268-1-A, PERMANENT HYDROGEN MITIGATION SYSTEMS 2-DXF-268-1 -A, at Compt 9E of Board 2A1 -A, is in the OFF position.

CV

[4]

ENSURE the following PHMS Supply Breaker, Breaker 2-BKR-268-2-B, PERMANENT HYDROGEN MITIGATION SYSTEM 2-DXF-268-2-B, at Compt 12C of Board 2B-B, is in the OFF position.

CV NOTE Hydrogen Mitigation Distribution Panel 2-DPL-268-1-A is located at COL A12V, EL 782'.

[5]

ENSURE Breaker 2-BKR-268-1/1 -A, Breaker I at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, is in the ON position.

CV

Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[6]

ENSURE Breaker 2-BKR-268-1/2-A, Breaker 2 at Hydrogen Mitigation Distribution Panel 2-DPL-268-1-A, is in the ON position.

Cv

[7]

ENSURE Breaker 2-BKR-268-1/3-A, Breaker 3 at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, is in the ON position.

Cv

[8]

ENSURE Breaker 2-BKR-268-1/4-A, Breaker 4 at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, is in the ON position.

Cv

[9]

ENSURE Breaker 2-BKR-268-1/5-A, Breaker 5 at Hydrogen Mitigation Distribution Panel 2-DPL-268-1-A, is in the ON position.

Cv

[10]

ENSURE Breaker 2-BKR-268-1/6-A, Breaker 6 at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, is in the ON position.

Cv

[11]

ENSURE Breaker 2-BKR-268-1/7-A, Breaker 7 at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, is in the ON position.

Cv

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 21 of 123 Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[12]

ENSURE Breaker 2-BKR-268-1/8-A, Breaker 8 at Hydrogen Mitigation Distribution Panel 2-DPL-268-1-A, is in the ON position.

Cv

[13]

ENSURE Breaker 2-BKR-268-1/9-A, Breaker 9 at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, is in the ON position.

Cv

[14]

ENSURE Breaker 2-BKR-268-1/10-A, Breaker 10 at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, is in the ON position.

Cv

[15]

ENSURE Breaker 2-BKR-268-1/1 1-A, Breaker 11 at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, is in the ON position.

Cv

[16]

ENSURE Breaker 2-BKR-268-1/12-A, Breaker 12 at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, is in the ON position.

Cv

[17]

ENSURE Breaker 2-BKR-268-1/13-A, Breaker 13 at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, is in the ON position.

Cv

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 22 of 123 Data Package: Page

-of Date.

6.1 PHMS Control and Alarm Function Tests (continued)

[18]

ENSURE Breaker 2-BKR-268-1/14-A, Breaker 14 at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, is in the ON position.

Cv

[19]

ENSURE Breaker 2-BKR-268-1/15-A, Breaker 15 at Hydrogen Mitigation Distribution Panel 2-DPL-268-1-A, is in the ON position.

Cv

[20]

ENSURE Breaker 2-BKR-268-1/16-A, Breaker 16 at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, is in the ON position.

Cv

[21]

ENSURE Breaker 2-BKR-268-1/17-A, Breaker 17 at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, is in the ON position.

Cv

[22]

ENSURE Breaker 2-BKR-268-1/18-A, Breaker 18 at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, is in the ON position.

Cv

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 23 of 123 Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

NOTE Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B is located at COL A12V, EL 782'.

[23]

ENSURE Breaker 2-BKR-268-2/1-B, Breaker I at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, is in the ON position.

CV

[24]

ENSURE Breaker 2-BKR-268-2/2-B, Breaker 2 at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, is in the ON position.

CV

[25]

ENSURE Breaker 2-BKR-268-2/3-B, Breaker 3 at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, is in the ON position.

CV.

[26]

ENSURE Breaker 2-BKR-268-2/4-B, Breaker 4 at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, is in the ON position.

CV

[27]

ENSURE Breaker 2-BKR-268-2/5-B, Breaker 5 at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, is in the ON position.

CV

Data Package: Page_

of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[28]

ENSURE Breaker 2-BKR-268-2/6-B, Breaker 6 at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, is in the ON position.

Cv

[29]

ENSURE Breaker 2-BKR-268-2/7-B, Breaker 7 at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, is in the ON position.

Cv

[30]

ENSURE Breaker 2-BKR-268-2/8-B, Breaker 8 at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, is in the ON position.

Cv

[31]

ENSURE Breaker 2-BKR-268-2/9-B, Breaker 9 at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, is in the ON position.

Cv

[32]

ENSURE Breaker 2-BKR-268-2/10-B, Breaker 10 at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, is in the ON position.

Cv

[33]

ENSURE Breaker 2-BKR-268-2/11 -B, Breaker 11 at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, is in the ON position.

Cv

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 25 of 123 Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[34]

ENSURE Breaker 2-BKR-268-2/12-B, Breaker 12 at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, is in the ON position.

Cv

[35]

ENSURE Breaker 2-BKR-268-2/13-B, Breaker 13 at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, is in the ON position.

Cv

[36]

ENSURE Breaker 2-BKR-268-2/14-B, Breaker 14 at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, is in the ON position.

Cv

[37]

ENSURE Breaker 2-BKR-268-2/15-B, Breaker 15 at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, is in the ON position.

Cv

[38]

ENSURE Breaker 2-BKR-268-2/16-B, Breaker 16 at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, is in the ON position.

Cv

[39]

ENSURE Breaker 2-BKR-268-2/17-B, Breaker 17 at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, is in the ON position.

Cv

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 26 of 123 Data Package: Page of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[40]

ENSURE Breaker 2-BKR-268-2/18-B, Breaker 18 at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, is in the ON position.

CV

[41]

ENSURE AC POWER Breaker CB1, 2-BKR-268-1A-A, AC CIRCUIT BREAKER PHMS GROUP A, at Panel 2-DXF-268-1-A, is in the ON position.

CV

[42]

ENSURE AC POWER Breaker CB1, 2-BKR-268-2A-B, AC CIRCUIT BREAKER PHMS GROUP B, at Panel 2-DXF-268-2-B, is in the ON position.

CV

[43]

ENSURE Hydrogen Mitigation Distribution Panel MAIN Breaker, 2-BKR-268-1/M1-A, GROUP A PHMS ISOL BKR, at Panel 2-DPL-268-1-A, is in the ON position.

CV

[44]

ENSURE Hydrogen Mitigation Distribution Panel MAIN Breaker, 2-BKR-268-2/M1-B, GROUP B PHMS ISOL BKR, at Panel 2-DPL-268-2-B, is in the ON position.

CV NOTE Annunciator Window, 2-XA-55-5C/102-C, PHMS PNL A/B UV/BKR TRIP is located in the Main Control Room on panel 2-M-5.

[45]

VERIFY 2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, is CLEAR.

Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[46]

PLACE and HOLD handheld jumper across points 6 and 7 of the auxiliary contact at 480V C&A Bldg Vent Bd 2A1-A, Compt 9E.

CV

[46.1]

VERIFY 2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS. (Acc Crit)

[46.2]

VERIFY Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in ALARM (Red). (Acc Crit)

[47]

REMOVE handheld jumper across points 6 and 7 of the auxiliary contact at 480V C&A Bldg Vent Bd 2A1-A, Compt 9E.

CV

[47.1]

VERIFY 2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

[47.2]

VERIFY Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is NORMAL (Blue).

[48]

PLACE and HOLD handheld jumper across points 6 and 7 of the auxiliary contact at 480V C&A Bldg Vent Bd 2B1-B, Compt 12C.

CV

[48.1]

VERIFY 2-XA-55-5C1102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS. (Acc Crit)

[48.2]

VERIFY Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is in ALARM (Red). (Acc Crit)

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 28 of 123 Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[49]

REMOVE handheld jumper across points 6 and 7 of the auxiliary contact at 480V C&A Bldg Vent Bd 2B1-B, Compt 12C, Breaker 2-BKR-268-2-B.

CV

[49.1]

VERIFY 2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B W/BKR TRIP, CLEARS.

[49.2]

VERIFY Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is NORMAL (Blue).

NOTES

1)

Section 6.1[50] to 6.1[85] verifies the breakers at Panel 2-DPL-268-1-A TRIP and RESET.

2)

Each of the following breakers is equipped with a Red TRIP Button which trips the breaker when turned clockwise.

[50]

TRIP Breaker 2-BKR-268-1/1-A, (Breaker 1), at Panel 2-DPL-268-1 -A, by way of Red TRIP Button. (Acc Crit)

CV

[50.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in ALARM (Red).

[51]

RESET Breaker 2-BKR-268-1/1-A, (Breaker 1), at Panel 2-DPL-268-1-A.

CV

Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[51.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in NORMAL (Blue).

[52]

TRIP Breaker 2-BKR-268-1/2-A, (Breaker 2), at Panel 2-DPL-268-1-A, by way of Red TRIP Button. (Acc Crit)

CV

[52.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in ALARM (Red).

[53]

RESET Breaker 2-BKR-268-1/2-A, (Breaker 2), at Panel 2-DPL-268-1 -A.

CV

[53.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in NORMAL (Blue).

[54]

TRIP Breaker 2-BKR-268-1/3-A, (Breaker 3), at Panel 2-DPL-268-1-A, by way of Red TRIP Button. (Acc Crit)

CV

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 30 of 123 Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[54.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in ALARM (Red).

[55]

RESET Breaker 2-BKR-268-1/3-A, (Breaker 3), at Panel 2-DPL-268-1 -A.

CV

[55.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in NORMAL (Blue).

[56]

TRIP Breaker 2-BKR-268-1/4-A, (Breaker 4), at Panel 2-DPL-268-1-A, by way of Red TRIP Button. (Acc Crit)

CV

[56.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in ALARM (Red).

Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[57]

RESET Breaker 2-BKR-268-1/4-A, (Breaker 4), at Panel 2-DPL-268-1-A.

Cv

[57.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL ANB UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in NORMAL (Blue).

[58]

TRIP Breaker 2-BKR-268-1/5-A, (Breaker 5), at Panel 2-DPL-268-1-A, by way of Red TRIP Button. (Acc Crit)

CV

[58.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL NB UV/BKR TRIP, ALARMS.-

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in ALARM (Red).

[59]

RESET Breaker 2-BKR-268-1/5-A, (Breaker 5), at Panel 2-DPL-268-1-A.

CV

[59.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL NB UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in NORMAL (Blue).

Data Package: Page of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[60]

TRIP Breaker 2-BKR-268-1/6-A, (Breaker 6), at Panel 2-DPL-268-1-A, by way of Red TRIP Button. (Acc Crit)

Cv

[60.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in ALARM (Red).

[61]

RESET Breaker 2-BKR-268-1/6-A, (Breaker 6), at Panel 2-DPL-268-1-A.

CV

[61.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL ANB UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in NORMAL (Blue).

[62]

TRIP Breaker 2-BKR-268-1/7-A, (Breaker 7), at Panel 2-DPL-268-1-A, by way of Red TRIP Button. (Acc Crit)

Cv

[62.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in ALARM (Red).

Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[63]

RESET Breaker 2-BKR-268-1/7-A, (Breaker 7), at Panel 2-DPL-268-1-A.

Cv

[63.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in NORMAL (Blue).

[64]

TRIP Breaker 2-BKR-268-1/8-A, (Breaker 8), at Panel 2-DPL-268-1-A, by way of Red TRIP Button. (Acc Crit)

CV

[64.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in ALARM (Red).

[65]

RESET Breaker 2-BKR-268-1/8-A, (Breaker 8), at Panel 2-DPL-268-1-A.

CV

[65.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in NORMAL (Blue).

Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[66]

TRIP Breaker 2-BKR-268-1/9-A, (Breaker 9), at Panel 2-DPL-268-1-A, by way of Red TRIP Button. (Acc Crit)

Cv

[66.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS..

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in ALARM (Red).

[67]

RESET Breaker 2-BKR-268-1/9-A, (Breaker 9), at Panel 2-DPL-268-1 -A.

Cv

[67.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in NORMAL (Blue).

[68]

TRIP Breaker 2-BKR-268-1/10-A, (Breaker 10), at Panel 2-DPL-268-1 -A, by way of Red TRIP Button. (Acc Crit)

CV

[68.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL NB UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in ALARM (Red).

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 35 of 123 Data Package: Page of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[69]

RESET Breaker 2-BKR-268-1/10-A, (Breaker 10), at Panel 2-DPL-268-1-A.

Cv

[69.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in NORMAL (Blue).

[70]

TRIP Breaker 2-BKR-268-1/11-A, (Breaker 11), at Panel 2-DPL-268-1 -A, by way of Red TRIP Button. (Acc Crit)

Cv

[70.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL NB UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in ALARM (Red).

[71]

RESET Breaker 2-BKR-268-1/11-A, (Breaker 11), at Panel 2-DPL-268-1 -A.

Cv

[71.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL NB UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in NORMAL (Blue).

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 36 of 123 Data Package: Page of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[72]

TRIP Breaker 2-BKR-268-1/12-A, (Breaker 12), at Panel 2-DPL-268-1-A, by way of Red TRIP Button. (Acc Crit)

Cv

[72.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL ANB UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in ALARM (Red).

[73]

RESET Breaker 2-BKR-268-1/12-A, (Breaker 12), at Panel 2-DPL-268-1 -A.

CV

[73.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in NORMAL (Blue).

[74]

TRIP Breaker 2-BKR-268-1/13-A, (Breaker 13), at Panel 2-DPL-268-1-A, by way of Red TRIP Button. (Acc Crit)

CV

[74.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in ALARM (Red).

Data Package: Page of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[75]

RESET Breaker 2-BKR-268-1/13-A, (Breaker 13), at Panel 2-DPL-268-1-A.

Cv

[75.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL ANB UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in NORMAL (Blue).

[76]

TRIP Breaker 2-BKR-268-1/14-A, (Breaker 14), at Panel 2-DPL-268-1-A, by way of Red TRIP Button. (Acc Crit)

CV

[76.11 VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL NB UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in ALARM (Red).

[77]

RESET Breaker 2-BKR-268-1/14-A, (Breaker 14), at Panel 2-DPL-268-1 -A.

CV

[77.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL NB UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in NORMAL (Blue).

Data Package: Page of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[78]

TRIP Breaker 2-BKR-268-1/15-A, (Breaker 15), at Panel 2-DPL-268-1-A, by way of Red TRIP Button. (Acc Crit)

Cv

[78.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in ALARM (Red).

[79]

RESET Breaker 2-BKR-268-1/15-A, (Breaker 15), at Panel 2-DPL-268-1-A.

CV

[79.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL'A UV/BKR TRIPPED is in NORMAL (Blue).

[80]

TRIP Breaker 2-BKR-268-1116-A, (Breaker 16), at Panel 2-DPL-268-1-A, by way of Red TRIP Button. (Acc Crit)

CV

[80.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in ALARM (Red).

Data Package: Page of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[81]

RESET Breaker 2-BKR-268-1/16-A, (Breaker 16), at Panel 2-DPL-268-1 -A.

Cv

[81.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL NB UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in NORMAL (Blue).

[82]

TRIP Breaker 2-BKR-268-1/17-A, (Breaker 17), at Panel 2-DPL-268-1 -A, by way of Red TRIP Button. (Acc Crit)

Cv

[82.1]

VERIFY the following:

A.

2-XA-55-5C/1 02-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in ALARM (Red).

[83]

RESET Breaker 2-BKR-268-1/17-A, (Breaker 17), at Panel 2-DPL-268-1-A.

Cv

[83.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL NB UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in NORMAL (Blue).

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 40 of 123 Data Package: Page of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[84]

TRIP Breaker 2-BKR-268-1/18-A, (Breaker 18), at Panel 2-DPL-268-1-A, by way of Red TRIP Button. (Acc Crit)

Cv

[84.11 VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is in ALARM (Red).

[85]

RESET 2-BKR-268-1/18-A, (Breaker 18), at Panel 2-DPL-268-1 -A.

Cv

[85.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL NB UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL A UV/BKR TRIPPED is NORMAL (Blue).

NOTES

1)

Section 6.1[86] to 6.1[121J verifies the breakers at Panel 2-DPL-268-2-B TRIP and RESET.

2)

Each of the following breakers is equipped with a Red TRIP Button which trips the breaker when turned clockwise.

[86]

TRIP Breaker 2-BKR-268-2/1-B, (Breaker 1), at Panel 2-DPL-268-2-B, by way of Red TRIP Button. (Acc Crit)

Cv

Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[86.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is in ALARM (Red).

[87]

RESET 2-BKR-268-2/1-B, (Breaker 1), at Panel 2-DPL-268-2-B.

CV

[87.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL NB UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UVIBKR TRIPPED is NORMAL (Blue).

[88]

TRIP Breaker 2-BKR-268-2/2-B, (Breaker 2), at Panel 2-DPL-268-2-B, by way of Red TRIP Button. (Acc Crit)

CV

[88.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL NB UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is in ALARM (Red).

[89]

RESET 2-BKR-268-2/2-B, (Breaker 2), at Panel 2-DPL-268-2-B.

CV

Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[89.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is NORMAL (Blue).

[90]

TRIP Breaker at 2-BKR-268-2/3-B, (Breaker 3), at Panel 2-DPL-268-2-B, by way of Red TRIP Button. (Acc Crit)

CV

[90.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is in ALARM (Red).

[91]

RESET 2-BKR-268-2/3-B, (Breaker 3), at Panel 2-DPL-268-2-B.

CV

[91.1]

VERIFY the following:

A.

2-XA-55-5C/1 02-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is NORMAL (Blue).

[92]

TRIP Breaker 2-BKR-268-2/4-B, (Breaker 4), at Panel 2-DPL-268-2-B, by way of Red TRIP Button. (Acc Crit)

CV

Data Package: Page of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[92.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL ANB UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is in ALARM (Red).

[93]

RESET 2-BKR-268-2/4-B, (Breaker 4), at Panel 2-DPL-268-2-B.

Cv

[93.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is NORMAL (Blue).

[94]

TRIP Breaker 2-BKR-268-2/5-B, (Breaker 5), at Panel 2-DPL-268-2-B, by way of Red TRIP Button. (Acc Crit)

CV

[94.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is in ALARM (Red).

[95]

RESET 2-BKR-268-2/5-B, (Breaker 5), at Panel 2-DPL-268-2-B.

CV

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 44 of 123 Data Package: Page of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[95.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER D1ST PNL B UV/BKR TRIPPED is NORMAL (Blue).

[96]

TRIP Breaker at 2-BKR-268-2/6-B, (Breaker 6), at Panel 2-DPL-268-2-B, by way of Red TRIP Button. (Acc Crit)

CV

[96.1]

VERIFY the following:

A.

2-XA-55-5C/1 02-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is in ALARM (Red).

[97]

RESET 2-BKR-268-2/6-B, (Breaker 6), at Panel 2-DPL-268-2-B.

CV

[97.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL NB UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is NORMAL (Blue).

[98]

TRIP Breaker 2-BKR-268-2/7-B, (Breaker 7), at Panel 2-DPL-268-2-B, by way of Red TRIP Button. (Acc Crit)

CV

Data Package: Page of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[98.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is in ALARM (Red).

[99]

RESET 2-BKR-268-2/7-B, (Breaker 7), at Panel 2-DPL-268-2-B.

Cv

[99.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is NORMAL (Blue).

[100] TRIP Breaker 2-BKR-268-2/8-B, (Breaker 8), at Panel 2-DPL-268-2-B, by way of Red TRIP Button. (Acc Crit)

CV

[100.1]

VERIFY the following:

A.

2-XA-55-5C/1 02-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is in ALARM (Red).

[101] RESET 2-BKR-268-2/8-B, (Breaker 8), at Panel 2-DPL-268-2-B.

CV

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 46 of 123 Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[101.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL ANB UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is NORMAL (Blue).

[102] TRIP Breaker 2-BKR-268-2/9-B, (Breaker 9), at Panel 2-DPL-268-2-B, by way of Red TRIP Button. (Acc Crit)

CV

[102.1]

VERIFY the following:

A.

2-XA-55-5C/1 02-C, PHMS PWR DIST PNL NB UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is in ALARM (Red).

[103] RESET 2-BKR-268-2/9-B, (Breaker 9), at Panel 2-DPL-268-2-B.

CV

[103.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL NB UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is NORMAL (Blue).

[104] TRIP Breaker 2-BKR-268-2/10-B, (Breaker 10), at Panel 2-DPL-268-2-B, by way of Red TRIP Button. (Acc Crit)

CV

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 47 of 123 Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[104.1]

VERIFY the following:

A.

2-XA-55-5C/1 02-C, PHMS PWR DIST PNL NB UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is in ALARM (Red).

[105] RESET 2-BKR-268-2/10-B, (Breaker 10), at Panel 2-DPL-268-2-B.

Cv

[105.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

I B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B.UV/BKR TRIPPED is NORMAL (Blue).

[106] TRIP Breaker 2-BKR-268-2/1 1-B, (Breaker 11), at Panel 2-DPL-268-2-B, by way of Red TRIP Button. (Acc Crit)

Cv

[106.1]

VERIFY the following:

A.

2-XA-55-5C/1 02-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is in ALARM (Red).

[107] RESET 2-BKR-268-2/1 1-B, (Breaker 11), at Panel 2-DPL-268-2-B.

. Cv

Data Package: Page of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[107.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is NORMAL (Blue).

[108] TRIP Breaker 2-BKR-268-2/12-B, (Breaker 12), at Panel 2-DPL-268-2-B, by way of Red TRIP Button. (Acc Crit)

CV

[108.1]

VERIFY the following:

A.

2-XA-55-5C/1 02-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is in ALARM (Red).

[109] RESET 2-BKR-268-2/12-B, (Breaker 12), at Panel 2-DPL-268-2-B.

CV

[109.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL NB UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is NORMAL (Blue).

[110] TRIP Breaker 2-BKR-268-2/13-B, (Breaker 13), at Panel 2-DPL-268-2-B, by way of Red TRIP Button. (Acc Crit)

CV

Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[110.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is in ALARM (Red).

[111] RESET 2-BKR-268-2/13-B, (Breaker 13), at Panel 2-DPL-268-2-B.

CV

[111.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is NORMAL (Blue).

[112] TRIP Breaker 2-BKR-268-2/14-B, (Breaker 14), at Panel 2-DPL-268-2-B, by way of Red TRIP Button. (Acc Crit)

CV

[112.1]

VERIFY the following:

A.

2-XA-55-5C/1 02-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is in ALARM (Red).

[113] RESET 2-BKR-268-2/14-B, (Breaker 14), at Panel 2-DPL-268-2-B.

CV

Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[113.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is NORMAL (Blue).

[114] TRIP Breaker 2-BKR-268-2/15-B, (Breaker 15), at Panel 2-DPL-268-2-B, by way of Red TRIP Button. (Acc Crit)

Cv

[114.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is in ALARM (Red).

[115] RESET 2-BKR-268-2/15-B, (Breaker 15), at Panel 2-DPL-268-2-B.

CV

[115.1]

VERIFY the following:

A.

2-XA-55-5C/1 02-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is NORMAL (Blue).

[116] TRIP Breaker 2-BKR-268-2/16-B, (Breaker 16), at Panel 2-DPL-268-2-B, by way of Red TRIP Button. (Acc Crit)

CV

Data Package: Page of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[116.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is in ALARM (Red).

[117] RESET 2-BKR-268-2/16-B, (Breaker 16), at Panel 2-DPL-268-2-B.

CV

[117.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL ANB UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is NORMAL (Blue).

[118] TRIP Breaker 2-BKR-268-2/17-B, (Breaker 17), at Panel 2-DPL-268-2-B, by way of Red TRIP Button. (Acc Crit)

Cv

[118.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is in ALARM (Red).

[119] RESET 2-BKR-268-2/17-B, (Breaker 17), at Panel 2-DPL-268-2-B.

Cv

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 52 of 123 Data Package: Page of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[119.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is NORMAL (Blue).

[120] TRIP Breaker 2-BKR-268-2/18-B, (Breaker 18), at Panel 2-DPL-268-2-B; by way of Red TRIP Button. (Acc Crit)

Cv

[120.1]

VERIFY the following:

A.

2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is in ALARM (Red).

[121] RESET 2-BKR-268-2/18-B, (Breaker 18), at Panel 2-DPL-268-2-B.

Cv

[121.1]

VERIFY the following:

A.

2-XA-55-5C/1 02-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

B.

Unit 2 Event Display Monitor indicates 102-C PHMS POWER DIST PNL B UV/BKR TRIPPED is NORMAL (Blue).

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 53 of 123 Data Package: Page_

of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[122] PLACE MAIN Breaker 2-BKR-268-1/M1-A at Panel 2-DPL-268-1 -A in the OFF position. (Acc Crit)

Cv

[122.1]

VERIFY 2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

[123] PLACE MAIN Breaker 2-BKR-268-1/M1-A at Panel 2-DPL-268-1-A in the ON position.

Cv

[123.1]

VERIFY 2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, is CLEAR.

[124] PLACE MAIN Breaker 2-BKR-268-2/M1-B at Panel 2-DPL-268-2-B in the OFF position. (Acc Crit)

Cv

[124.1]

VERIFY 2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

[125] PLACE MAIN Breaker 2-BKR-268-2/M1-B at Panel 2-DPL-268-2-B in the ON position.

Cv

[125.1]

VERIFY 2-XA-55-5C/102-C, PHMS PWR DIST PNL NB UV/BKR TRIP, is CLEAR.

[126] PLACE Breaker 2-BKR-268-1/1-A, Breaker 1, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the OFF position.

Cv

Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[127] PLACE Breaker 2-BKR-268-1/2-A, Breaker 2, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the OFF position.

Cv

[128] PLACE Breaker 2-BKR-268-1/3-A, Breaker 3, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the OFF position.

Cv

[129] PLACE Breaker 2-BKR-268-1/4-A, Breaker 4, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1-A, in the OFF position.

Cv

[130] PLACE Breaker 2-BKR-268-1/5-A, Breaker 5, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the OFF position.

Cv

[131] PLACE Breaker 2-BKR-268-1/6-A, Breaker 6, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the OFF position.

Cv

[132] PLACE Breaker 2-BKR-268-1/7-A, Breaker 7, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1-A, in the OFF position.

Cv

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 55 of 123 Data Package: Page of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[133] PLACE Breaker 2-BKR-268-1/8-A, Breaker 8, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1-A, in the OFF position.

Cv

[134] PLACE Breaker 2-BKR-268-1/9-A, Breaker 9, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1-A, in the OFF position.

Cv

[135] PLACE Breaker 2-BKR-268-1/10-A, Breaker 10, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1-A, in the OFF position.

Cv

[136] PLACE Breaker 2-BKR-268-1/1 1-A, Breaker 11, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1-A, in the OFF position.

Cv

[137] PLACE Breaker 2-BKR-268-1/12-A, Breaker 12, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1-A, in the OFF position.

Cv

[138] PLACE Breaker 2-BKR-268-1/13-A, Breaker 13, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the OFF position.

Cv

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 56 of 123 Data Package: Page

.of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[139] PLACE Breaker 2-BKR-268-1/14-A, Breaker 14, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1-A, in the OFF position.

Cv

[140] PLACE Breaker 2-BKR-268-1/15-A, Breaker 15, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the OFF position.

Cv

[141] PLACE Breaker 2-BKR-268-1/116-A, Breaker 16, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the OFF position.

Cv

[142] PLACE Breaker 2-BKR-268-1/17-A, Breaker 17, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the OFF position.

Cv,

[143] PLACE Breaker 2-BKR-268-1/18-A, Breaker 18, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the OFF position.

Cv

[144] PLACE Breaker 2-BKR-268-2/1-B, Breaker 1, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the OFF position.

Cv

Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[145] PLACE Breaker 2-BKR-268-2/2-B, Breaker 2, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the OFF position.

Cv

[146] PLACE Breaker 2-BKR-268-2/3-B, Breaker 3, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the OFF position.

Cv

[147] PLACE Breaker 2-BKR-268-2/4-B, Breaker 4, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the OFF position.

Cv

[148] PLACE Breaker 2-BKR-268-2/5-B, Breaker 5, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the OFF position.

Cv

[149] PLACE Breaker 2-BKR-268-2/6-B, Breaker 6, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the OFF position.

Cv

[150] PLACE Breaker 2-BKR-268-2/7-B, Breaker 7, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the OFF position.

Cv

Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[151] PLACE Breaker 2-BKR-268-2/8-B, Breaker 8, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the OFF position.

Cv

[152] PLACE Breaker 2-BKR-268-2/9-B, Breaker 9, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the OFF position.

Cv

[153] PLACE Breaker 2-BKR-268-2/1 0-B, Breaker 10, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the OFF position.

Cv

[154] PLACE Breaker 2-BKR-268-2/1 1-B, Breaker 11, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the OFF position.

Cv

[155] PLACE Breaker 2-BKR-268-2/12-B, Breaker 12, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the OFF position.

Cv

[156] PLACE Breaker 2-BKR-268-2/13-B, Breaker 13, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the OFF position.

Cv

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 59 of 123 Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[157] PLACE Breaker 2-BKR-268-2/14-B, Breaker 14, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the OFF position.

Cv

[158] PLACE Breaker 2-BKR-268-2/15-B, Breaker 15, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the OFF position.

CV

[159] PLACE Breaker 2-BKR-268-2/16-B, Breaker 16, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the OFF position.

CV

[160] PLACE Breaker 2-BKR-268-2/17-B, Breaker 17, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the OFF position.

Cv

[161] PLACE Breaker 2-BKR-268-2/18-B, Breaker 18, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the OFF position.

Cv

[162] PLACE the 480V C&A Bldg Vent Board 2A1-A, Compt 9E Breaker 2-BKR-268-1 -A, in the ON position.

Cv

[163] VERIFY Red, POWER ON, Light on Hydrogen Mitigation Transformer Panel, 2-DXF-268-1 -A, is OFF.

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 60 of 123 Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[164] VERIFY the following light indications at Panel 2-M-1 0, Handswitch 2-HS-268-73, H2 IGNITERS GROUP A:

(Acc Crit)

A.

Green Light ON.

B.

Red Light OFF.

[1651 PLACE Handswitch 2-HS-268-73, H2 IGNITERS GROUP A, in the ON position.

[165.11 VERIFY the following light indications at Panel 2-M-10, Handswitch 2-HS-268-73, H2 IGNITER GROUP A.

(Acc Crit)

A.

Green Light OFF.

B.

Red Light ON.

[165.2]

VERIFY Red, POWER ON, Light is ON at 480V C&A Bldg Vent Board 2A1 -A, Compt 9E, Breaker 2-BKR-268-1-A. (Acc Crit)

[166] PLACE 480V C&A Bldg Vent Board 2B1-B, Compt 12C, Breaker 2-BKR-268-2-B in the ON position.

CV

[167] - VERIFY Red, POWER ON, Light on Hydrogen Mitigation Transformer Panel, 2-DXF-268-2-B, is OFF.

[168] VERIFY the following light indications at Panel 2-M-10, Handswitch 2-HS-268-74, H2 IGNITERS GROUP B:

(Acc Crit)

A.

Green Light ON.

B.

Red Light OFF.

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 61 of 123 Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[169] PLACE Handswitch 2-HS-268-74, H2 IGNITERS GROUP B, in the ON position.

[169.1]

VERIFY the following light indications at Panel 2-M-10, Handswitch 2-HS-268-74, H2 IGNITERS GROUP B.

(Acc Crit)

B. Green Light OFF.

C.

Red Light ON.

[169.2]

VERIFY Red, POWER ON, Light is ON at 480V C&A Bldg Vent Board 2B1-B, Compt 12C, Breaker 2-BKR-268-2-B. (Acc Crit)

[170] VERIFY 2-XA-55-5C/102-C, PHMS PWR DIST PNL NB UV/BKR TRIP, in MCR is CLEAR.

[171] PLACE AC POWER Breaker CB1, 2-BKR-268-1A-A, at Hydrogen Mitigation Transformer Panel, 2-DXF-268-1 -A, in the OFF position.

CV

[172] VERIFY 2-XA-55-5C/1 02-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

[173] PLACE AC POWER Breaker CB1, 2-BKR-268-IA-A, at Hydrogen Mitigation Transformer Panel, 2-DXF-268-1-A, in the ON position.

CV

[174] VERIFY 2-XA-55-5C/102-C, PHMS PWR DIST PNL NB UV/BKR TRIP, CLEARS.

Data Package: Page

-of Date 6.1 PHMS Control and Alarm Function Tests (continued)

[175] PLACE AC POWER Breaker CB1, 2-BKR-268-2A-B, at Hydrogen Mitigation Transformer Panel, 2-DXF-268-2-B, in the OFF position.

Cv

[176] VERIFY Window 102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, ALARMS.

[177] PLACE AC POWER Breaker CB1, 2-BKR-268-2A-B, at Hydrogen Mitigation Transformer Panel, 2-DXF-268-2-B, in the ON position.

CV

[178] VERIFY 2-XA-55-5C/102-C, PHMS PWR DIST PNL A/B UV/BKR TRIP, CLEARS.

[179] PLACE the following Handswitches at MCR Panel 2-M-1 0 in the OFF position:

A.

Handswitch 2-HS-268-73, H2 IGNITERS GROUP A.

B.

Handswitch 2-HS-268-74, H2 IGNITERS GROUP B.

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 63 of 123 Data Package: Page

-of Date 6.2 Hydrogen Igniter Functional Tests - Train A NOTE Subsections 6.2 and 6.3 may be performed concurrently.

[1]

VERIFY prerequisites listed in Section 4.0 for Subsection 6.2 have been completed.

[2]

ENSURE the following PHMS Supply Breaker, Breaker 2-BKR-268-1-A, PERMANENT HYDROGEN MITIGATION SYSTEM 2-DXF-268-1 -A, at Compt 9E of Board 2A1-A, is in the ON position.

CV NOTE Hydrogen Mitigation Distribution Panel 2-DPL-268-1-A is located at COL Al2V EL782.

[3]

PLACE Breaker 2-BKR-268-1/1 -A, Breaker 1, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the ON position.

CV

[4]

PLACE Breaker 2-BKR-268-1/2-A, Breaker 2, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the ON position.

CV

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 64 of 123 Data Package: Page of Date 6.2 Hydrogen Igniter Functional Tests - Train A (continued)

[5]

PLACE Breaker 2-BKR-268-1/3-A, Breaker 3, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the ON position.

Cv

[6]

PLACE Breaker 2-BKR-268-1/4-A, Breaker 4, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the ON position.

Cv

[7]

PLACE Breaker 2-BKR-268-1/5-A, Breaker 5, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the ON position Cv

[8]

PLACE Breaker 2-BKR-268-1/6-A, Breaker 6, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the ON position.

Cv

[9]

PLACE Breaker 2-BKR-268-1/7-A, Breaker 7, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the ON position.

Cv

[10]

PLACE Breaker 2-BKR-268-1/8-A, Breaker 8, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the ON position.

Cv

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 65 of 123 Data Package: Page

-of Date 6.2 Hydrogen Igniter Functional Tests - Train A (continued)

[11]

PLACE Breaker 2-BKR-268-1/9-A, Breaker 9, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the ON position.

CV

[12]

PLACE Breaker 2-BKR-268-1/10-A, Breaker 10, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the ON position.

CV

[13]

PLACE Breaker 2-BKR-268-1/11-A, Breaker 11, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1-A, in the ON position.

CV

[14]

PLACE Breaker 2-BKR-268-1/12-A, Breaker 12, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the ON position.

CV

[15]

PLACE Breaker 2-BKR-268-1/13-A, Breaker 13, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the ON position.

CV

[16]

PLACE Breaker 2-BKR-268-1/14-A, Breaker 14, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the ON position.

CV

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 66 of 123 Data Package: Page of Date 6.2 Hydrogen Igniter Functional Tests - Train A (continued)

[17]

PLACE Breaker 2-BKR-268-1/15-A, Breaker 15, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1-A, in the*ON position.

Cv

[18]

PLACE Breaker 2-BKR-268-1/16-A, Breaker 16, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the ON position.

Cv

[19]

PLACE Breaker 2-BKR-268-1/17-A, Breaker 17, at Hydrogen Mitigation Distribution Panel 2-DPL-268-1 -A, in the ON position.

Cv NOTE Breaker 18, 2-BKR-268-1/1 8-A, is'a spare breaker.

CAUTION The following steps energize the hydrogen igniters creating fire and safety hazard.

a Before the following steps, inspect each igniter to ensure no flammable material is within 2 feet of the igniters.

0 All entrances to the Unit 2 reactor building must be posted with personnel to brief those entering the building after operations announce that the igniters will be energized.

[20]

NOTIFY operations to announce that Hydrogen Igniter Heaters will be energized in the Containment, AND RECEIVE concurrence to proceed.

Data Package: Page

-of Date 6.2 Hydrogen Igniter Functional Tests - Train A (continued)

.[21]

PLACE Handswitch 2-HS-268-73, H2 IGNITERS GROUP A, in the ON position at MCR Panel 2-M-10, AND RECORD time.

Time

[22]

RECORD Phase-to-Phase bus voltage measurements at Panel 2-DPL-268-1-A, AND VERIFY voltage is between 230.36 VAC and 233.82 VAC.

A.

M&TE Cal Due Date VAC A-B (230.36-233.82 VAC)

B.

M&TE B-C Cal Due Date VAC (230.36-233.82 VAC)

Cal Due Date C.

M&TE C-A VAC (230.36-233.82 VAc)

Data Package: Page

-of Date 6.2 Hydrogen Igniter Functional Tests - Train A (continued)

[23]

IF any voltage measurement in 6.2[22] is NOT 230.26 to 233.82 VAC, THEN ADJUST potentiometer R13 in 2-DXF-268-268-1-A on control board AlA for Phase A, Al B for Phase B, and Al C for Phase C so that each phase is 230.26 to 233.82 VAC, AND RECORD as-left voltages for each phase below:

A.

Phase A to Phase B:

VAc B.

Phase B to Phase C:

VAC C.

Phase C to Phase A:

VAc

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 69 of 123 Data Package: Page

-of Date 6.2 Hydrogen Igniter Functional Tests - Train A (continued)

NOTE Voltage measurements in the following steps are to be taken to circuit neutral and not to common ground.

[24]

RECORD Phase-to-Neutral bus voltage measurements at Panel 2-DPL-268-1 -A, AND VERIFY voltage is between 132 and 135 VAc.

A.

M&TE A-NEUTRAL Cal Due Date VAc (132 - 135 VAC)

B.

M&TE B-NEUTRAL Cal Due Date VAC (13 2 - 135 VAC)

C.

M&TE C-NEUTRAL Cal Due Date VAC (132 - 135 VAc)

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 70 of 123 Data Package: Page

-of Date 6.2 Hydrogen Igniter Functional Tests - Train A (continued)

NOTES

1)

Breaker #18 is a spare breaker.

2)

The following step verifies both igniters are energized by measuring a current greater than 7.4 amperes at the breaker.

3)

If the current reading is between 3.7 and 4.4 amperes one igniter is considered to be operable.

4)

Current readings between 4.4 and 7.4 indicate a fault of an indeterminable nature and will require further troubleshooting to resolve.

[25]

VERIFY 7.4 amperes or greater measured at each breaker (#1 through #17 in any order) at Panel 2-DPL-268-1-A after a minimum of 5 minutes from time recorded in Step 6.2[21].

M&TE Cal Due Date BREAKER NUMBER AMPERES BREAKER NUMBER AMPERES 1

10 2

11 3

12 4-13 5

14 6

15 7

16 8

17 9

[26]

PLACE Handswitch 2-HS-268-73, H2 IGNITERS GROUP A, in the OFF position, AND RECORD time:

Time

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 71 of 123 Data Package: Page

-of Date 6.2 Hydrogen Igniter Functional Tests - Train A (continued)

[27]

WHEN the hydrogen igniters have been allowed to cool for at least 30 minutes, THEN PLACE Handswitch 2-HS-268-73, H2 IGNITERS GROUP A, in the ON position, AND RECORD time.

Time

Data Package: Page

-of Date 6.2 Hydrogen Igniter Functional Tests - Train A (continued)

NOTES

1) Measurements of igniter temperatures are by line-of-sight view (profile or oblique) using optical thermography and should indicate a stabilized temperature. Directly head-on (end) views of the hydrogen igniter may measure lower than actual temperature and should be avoided. See Appendix C, Temperature Conversion Chart, for conversion from °C to OF, if required.
2)

Steps 6.2[28] and 6.2[291 are performed concurrently by breaker number.

3)

Igniter Component ID numbers are typical of the following example: (#1 is 2-HTR-268-0001 and #66 is 2-HTR-268-0066).

[28]

WHEN the hydrogen igniters have warmed up 5 minutes to allow the current to the igniters to stabilize, THEN MEASURE and RECORD each of the following hydrogen igniter heater temperatures (in any order by breaker number) using an optical infrared thermometer or a contact thermometer: (See Figures 1 thru 5 for igniter locations)

HYDROGEN TEMPERATURE HYDROGEN TEMPERATURE BREAKER IGNITER IGNITER NUMBER HEATER HEATER

  1. 1 oF
    1. 32 OF BKR #1
  1. 2 OF
  1. 23 OF BKR #2
  1. 5 OF
  1. 6 OF BKR#3
  1. 7 OF
  1. 8 OF BKR #4
  1. 13 oF
  1. 14 OF BKR #5
  1. 15 oF
  1. 16 OF BKR #6
  1. 21 OF
  1. 22 OF BKR #7
  1. 25 OF
  1. 53 OF BKR #8
  1. 24 OF
  1. 29 OF BKR #9
  1. 30 OF
  1. 31 OF BKR#10
  1. 35 oF
  1. 36 OF BKR #11
  1. 26 oF
  1. 33 oF BKR#12
  1. 34 OF
  1. 42 OF BKR#13
  1. 49 OF
  1. 50 OF BKR #14
  1. 54 OF
  1. 55 OF BKR#15
  1. 27 OF
  1. 28 OF BKR#16
  1. 65 OF
  1. 66 OF BKR #17 M&TE Cal Due Date

Data Package: Page

-of Date 6.2 Hydrogen Igniter Functional Tests - Train A (continued)

NOTES

1) The following step is performed concurrently with Step 6.2[28] in a manner to obtain measurements as close as possible to the time when igniter temperatures are measured by indicated breaker number.
2)

Power Factor of 1.0 is assumed for calculation.

[29]

CALCULATE total load wattage for each Panel 2-DPL-268-1 -A Breaker as follows: (Acc Crit)

VOLTMETER M&TE AMMETER M&TE Cal Due Date Cal Due Date

[29.1]

RECORD Volts and Amps measurements for 2-BKR-268-1/1 -A, (Breaker 1).

VOLTS AMPS

[29.2]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-1/1 -A, (Breaker 1).

Watts Calculations Performed by:

Calculations Verified by:

[29.3]

RECORD Volts and Amps measurements for 2-BKR-268-1/2-A, (Breaker 2).

VOLTS AMPS

6.2 Data Package: Page of Hydrogen Igniter Functional Tests - Train A (continued)

[29.4]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-1/2-A, (Breaker 2).

Watts Date Calculations Performed by:

Calculations Verified by:

[29.5]

RECORD Volts and Amps measurements for 2-BKR-268-1/3-A, (Breaker 3).

VOLTS AMPS

[29.6]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-1/3-A, (Breaker 3).

Watts Calculations Performed by:

Calculations Verified by:

[29.7]

RECORD Volts and Amps measurements for 2-BKR-268-1/4-A, (Breaker 4).

VOLTS AMPS

Data Package: Page

-of Date 6.2 Hydrogen Igniter Functional Tests - Train A (continued)

[29.8]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-1/4-A, (Breaker 4).

Watts Calculations Performed by:

Calculations Verified by:

[29.9]

RECORD Volts and Amps measurements for 2-BKR-268-1/5-A, (Breaker 5).

VOLTS AMPS

[29.10]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-1/5-A, (Breaker 5).

Watts Calculations Performed by:

Calculations Verified by:

[29.11]

RECORD Volts and Amps measurements for 2-BKR-268-1/6-A, (Breaker 6).

VOLTS AMPS

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 76 of 123 Data Package: Page of Dat 6.2 Hydrogen Igniter Functional Tests - Train A (continued)

[29.12]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-1/6-A, (Breaker 6).

Watts Calculations Performed by:

Calculations Verified by:

[29.13]

RECORD Volts and Amps measurements for 2-BKR-268-1/7-A, (Breaker 7).

VOLTS AMPS

[29.14]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-1/7-A, (Breaker 7).

Watts Calculations Performed by:

Calculations Verified by:

[29.15]

RECORD Volts and Amps measurements for 2-BKR-268-1/8-A, (Breaker 8).

VOLTS AMPS e

6.2 WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM*

Rev. 0000 Page 77 of 123 Data Package: Page

-of Dal Hydrogen Igniter Functional Tests - Train A (continued)

[29.16]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-1/8-A, (Breaker 8).

Watts Calculations Performed by:

Calculations Verified by:

[29.17]

RECORD Volts and Amps measurements for 2-BKR-268-1/9-A, (Breaker 9).

VOLTS AMPS

[29.18]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-1/9-A, (Breaker 9).

Watts e

Calculations Performed by:

Calculations Verified by:

[29.19]

RECORD Volts and Amps measurements for 2-BKR-268-1/1 0-A, (Breaker 10).

VOLTS AMPS

Data Package: Page of Date.

6.2 Hydrogen Igniter Functional Tests - Train A (continued)

[29.20]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-1/1 0-A, (Breaker 10).

Watts Calculations Performed by:

Calculations Verified by:

[29.21]

RECORD Volts and Amps measurements for 2-BKR-268-1/11 -A, (Breaker 11).

VOLTS AMPS

[29.22]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-1 /1l-A, (Breaker 11).

Watts Calculations Performed by:

Calculations Verified by:

[29.23]

RECORD Volts and Amps measurements for 2-BKR-268-1/12-A, (Breaker 12).

VOLTS AMPS

Data Package: Page of Date 6.2 Hydrogen Igniter Functional Tests - Train A (continued)

[29.24]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-1/12-A, (Breaker 12).

Watts Calculations Performed by:

Calculations Verified by:

[29.25]

RECORD Volts and Amps measurements for 2-BKR-268-1/13-A, (Breaker 13).

VOLTS AMPS

[29.26]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-1/13-A, (Breaker 13).

Watts Calculations Performed by:

Calculations Verified by:

[29.27]

RECORD Volts and Amps measurements for 2-BKR-268-1/14-A, (Breaker 14).

VOLTS AMPS

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 80 of 123 Data Package: Page of Dat 6.2 Hydrogen Igniter Functional Tests - Train A (continued)

[29.28]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-1/14-A, (Breaker 14).

Watts Calculations Performed by:

Calculations Verified by:

[29.29]

RECORD Volts and Amps measurements for 2-BKR-268-1/15-A, (Breaker 15).

VOLTS AMPS

[29.30]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-1/15-A, (Breaker 15).

Watts Calculations Performed by:

Calculations Verified by:

[29.31]

RECORD Volts and Amps measurements for 2-BKR-268-1/16-A, (Breaker 16).

VOLTS AMPS e

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 81 of 123 6.2 Data Package: Page

-of Hydrogen Igniter Functional Tests - Train A (continued)

[29.32]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-1/16-A, (Breaker 16).

Watts Date.

Calculations Performed by:

Calculations Verified by:

[29.33]

RECORD Volts and Amps measurements for 2-BKR-268-1/17-A, (Breaker 17).

VOLTS AMPS

[29.34]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-1/17-A, (Breaker 17).

Watts Calculations Performed by:

Calculations Verified by:

Data Package: Page

-of 6.2 Hydrogen Igniter Functional Tests - Train A (continued)

Date

[30]

OPEN 2-BKR-268-11-A (Breaker 1).

CV A.

VERIFY Igniter #1 is observed to be OFF.

B.

VERIFY Igniter #32 is observed to be OFF.

[31]

CLOSE 2-BKR-268-1/1-A (Breaker 1).

CV

[32]

OPEN 2-BKR-268-1/2-A (Breaker 2).

CV A.

VERIFY Igniter #2 is observed to be OFF.

B.

VERIFY Igniter #23 is observed to be OFF.

[33]

CLOSE 2-BKR-268-1/2-A (Breaker 2).

CV

[34]

OPEN 2-BKR-268-1/3-A (Breaker 3).

CV A.

B.

VERIFY Igniter #5 is observed to be OFF.

VERIFY Igniter #6 is observed to be OFF.

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 83 of 123 6.2 Data Package: Page

-of Hydrogen Igniter Functional Tests - Train A (continued)

[35]

CLOSE 2-BKR-268-1/3-A (Breaker 3).

Date CV

[36]

OPEN 2-BKR-268-1/4-A (Breaker 4).

CV A.

VERIFY Igniter #7 is observed to be OFF.

B.

VERIFY Igniter #8 is observed to be OFF.

[37]

CLOSE 2-BKR-268-1/4-A (Breaker 4).

CV

[38]

OPEN 2-BKR-268-1/5-A (Breaker 5).

CV A.

VERIFY Igniter #13 is observed to be OFF.

B.

VERIFY Igniter #14 is observed to be OFF.

[39]

CLOSE 2-BKR-268-1/5-A (Breaker 5).

CV

[40]

OPEN 2-BKR-268-1/6-A (Breaker 6).

A.

B.

VERIFY Igniter #15 is observed to be OFF.

VERIFY Igniter #16 is observed to be OFF.

CV

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 84 of 123 Data Package: Page

-of 6.2 Hydrogen Igniter Functional Tests - Train A (continued)

[41]

CLOSE 2-BKR-268-1/6-A (Breaker 6).

Date CV

[42]

OPEN 2-BKR-268-1/7-A (Breaker 7).

CV A.

VERIFY Igniter #21 is observed to be OFF.

B.

VERIFY Igniter #22 is observed to be OFF.

[43]

CLOSE 2-BKR-268-1/7-A (Breaker 7).

CV

[44]

OPEN 2-BKR-268-1/8-A (Breaker 8).

CV A.

VERIFY Igniter #25 is observed to be OFF.

B.

VERIFY Igniter #53 is observed to be OFF.

[45]

CLOSE 2-BKR-268-1/8-A (Breaker 8).

CV

[46]

OPEN 2-BKR-268-1/9-A (Breaker 9).

CV A.

B.

VERIFY Igniter #24 is observed to be OFF.

VERIFY Igniter #29 is observed to be OFF.

Data Package: Page

-of 6.2 Hydrogen Igniter Functional Tests - Train A (continued)

[47]

CLOSE 2-BKR-268-1/9-A (Breaker 9).

Date CV

[48]

OPEN 2-BKR-268-1/10-A (Breaker 10).

CV A.

VERIFY Igniter #30 is observed to be OFF.

B.

VERIFY Igniter #31 is observed to be OFF.

[49]

CLOSE 2-BKR-268-1/10-A (Breaker 10).

CV

[50]

OPEN 2-BKR-268-1/11-A (Breaker 11).

CV A.

VERIFY Igniter #35 is observed to be OFF.

B.

VERIFY Igniter #36 is observed to be OFF.

[51]

CLOSE 2-BKR-268-1/11-A (Breaker 11).

CV

[52]

OPEN 2-BKR-268-1/12-A (Breaker 12).

CV A.

B.

VERIFY Igniter #26 is observed to be OFF.

VERIFY Igniter #33 is observed to be OFF.

Data Package: Page

-of 6.2 Hydrogen Igniter Functional Tests - Train A (continued)

[53]

CLOSE 2-BKR-268-1/12-A (Breaker 12).

Date CV

[54]

OPEN 2-BKR-268-1/13-A (Breaker 13).

CV A.

VERIFY Igniter #34 is observed to be OFF.

B.

VERIFY Igniter #42 is observed to be OFF.

[55]

CLOSE 2-BKR-268-1/13-A (Breaker 13).

CV

[56]

OPEN 2-BKR-268-1/14-A (Breaker 14).

CV A.

VERIFY Igniter #49 is observed to be OFF.

B.

VERIFY Igniter #50 is observed to be OFF.

[57]

CLOSE 2-BKR-268-1/14-A (Breaker 14).

CV

[58]

OPEN 2-BKR-268-1/15-A (Breaker 15).

CV A.

B.

VERIFY Igniter #54 is observed to be OFF.

VERIFY Igniter #55 is observed to be OFF.

6.2 Data Package: Page of Hydrogen Igniter Functional Tests - Train A (continued)

[59]

CLOSE 2-BKR-268-1/15-A (Breaker 15).

Date CV

[60]

OPEN 2-BKR-268-1/16-A (Breaker 16).

CV A.

VERIFY Igniter #27 is observed to be OFF.

B.

VERIFY Igniter #28 is observed to be OFF.

[61]

CLOSE 2-BKR-268-1/16-A (Breaker 16).

CV

[62]

OPEN 2-BKR-268-1117-A (Breaker 17).

CV A.

VERIFY Igniter #65 is observed to be OFF.

B.

VERIFY Igniter #66 is observed to be OFF.

[63]

CLOSE 2-BKR-268-1/17-A (Breaker 17).

CV NOTE Breaker 18, 2-BKR-268-1/18-A, is a spare breaker.

[64]

VERIFY each igniter temperature recorded in step6.2[28] is 1741.2 0F or greater. (Acc Crit)

[65]

VERIFY wattages recorded in Step 6.2[29] do not individually exceed 1335.3 watts. (Acc Crit)

6.2 Data Package: Page of Hydrogen Igniter Functional Tests - Train A (continued)

[66]

RECORD Phase-to-Phase bus voltage measurements at Panel 2-DPL-268-1-A, AND VERIFY voltage is between 230.36 VAC and 233.82 VAC.

A.

Date M&TE B.

M&TE A-B3 B-C Cal Due Date VAC (230.36-233.82 VAc)

Cal Due Date VAC (230.36-233.82 VAC)

Cal Due Date C.

M&TE C-A VAC (230.36-233.82 VAc)

Data Package: Page of Date 6.2 Hydrogen Igniter Functional Tests - Train A (continued)

[67]

IF any voltage measurement in 6.2[66] is NOT 230.26 to 233.82 VAC, THEN ADJUST potentiometer R13 in 2-DXF-268-268-1-A on control board Al A for Phase A, Al B for Phase B, and Al C for Phase C so that each phase is 230.26 to 233.82 VAc, AND RECORD as-left voltages for each phase below:

A.

Phase A to Phase B:

VAC B.

Phase B to Phase C:

VAC C.

Phase C to Phase A:

VAC

6.2 Data Package: Page of Hydrogen Igniter Functional Tests - Train A (continued)

(68]

RECORD Phase-to-Neutral bus voltage measurements at Panel 2-DPL-268-1 -A, AND VERIFY voltage is between 132 and 135 VAC.

A.

Date _

M&TE Cal Due Date VAC (132 - 135 VAC)

A-NEUTRAL B.

M&TE B-NEUTRAL C.

Cal Due Date VAC (132-135 VAC)

Cal Due Date VAC (032 - 135 VA)

M&TE C-NEUTRAL

[69]

PLACE Handswitch 2-HS-268-73, H2 IGNITERS GROUP A, in the OFF position.

WBN Unit 2 PERMANENT HYDROGEN MITIGATION SYSTEM 2-PTI-268-01 Rev. 0000 Page 91 of 123 Data Package: Page

-of Date 6.3 Hydrogen Igniter Functional Tests - Train B NOTE Subsections 6.2 and 6.3 may be performed concurrently

[1]

VERIFY prerequisites listed in Section 4.0 for Subsection 6.3 have been completed.

[2]

ENSURE the following PHMS Supply Breaker, Breaker 2-BKR-268-2-B, PERMANENT HYDROGEN MITIGATION SYSTEM 2-DXF-268-2-B, at Compt 12C of Board 2B1-B, is in the ON position.

CV NOTE Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B is located at COL A12V, EL 782'.

[3]

PLACE Breaker 2-BKR-268-2/1 -B, Breaker 1, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the ON position.

CV

[4]

PLACE Breaker 2-BKR-268-2/2-B, Breaker 2, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the ON position.

CV

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 92 of 123 Data Package: Page

-of Date 6.3 Hydrogen Igniter Functional Tests - Train B (continued)

[5]

PLACE Breaker 2-BKR-268-2/3-B, Breaker 3, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the ON position.

cv

[6]

PLACE Breaker 2-BKR-268-2/4-B, Breaker 4, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the ON position.

Cv

[7]

PLACE Breaker 2-BKR-268-2/5-B, Breaker 5, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the ON position.

Cv

[8]

PLACE Breaker 2-BKR-268-2/6-B, Breaker 6, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the ON position.

Cv

[9]

PLACE Breaker 2-BKR-268-2/7-B, Breaker 7, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the ON position.

Cv

[10]

PLACE Breaker 2-BKR-268-2/8-B, Breaker 8, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the ON position.

Cv

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 93 of 123 Data Package: Page of Date 6.3 Hydrogen Igniter Functional Tests - Train B (continued)

[11]

PLACE Breaker 2-BKR-268-2/9-B, Breaker 9, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the ON position.

Cv

[12]

PLACE Breaker 2-BKR-268-2/10-B, Breaker 10, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the ON position.

Cv

[13]

PLACE Breaker 2-BKR-268-2/1 1-B, Breaker 11, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the ON position.

Cv

[14]

PLACE Breaker 2-BKR-268-2/12-B, Breaker 12, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the ON position.

.Cv

[15]

PLACE Breaker 2-BKR-268-2/13-B, Breaker 13, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the ON position.

Cv

[16]

PLACE Breaker 2-BKR-268-2/14-B, Breaker 14, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the ON position.

Cv

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 94 of 123 Data Package: Page of Date 6.3 Hydrogen Igniter Functional Tests - Train B (continued)

[17]

PLACE Breaker 2-BKR-268-2/15-B, Breaker 15, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the ON position.

Cv

[18]

PLACE Breaker 2-BKR-268-2/16-B, Breaker 16, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the ON position.

Cv

[19]

PLACE Breaker 2-BKR-268-2/17-B, Breaker 17, at Hydrogen Mitigation Distribution Panel 2-DPL-268-2-B, in the ON position.

Cv NOTE Breaker 18, 2-BKR-268-1/18-A, is a spare breaker.

CAUTION The following steps energize the hydrogen igniters creating fire and safety hazard.

0 Before the following steps, inspect each igniter to ensure no flammable material is within 2 feet of the igniters.

a All entrances to the Unit 2 reactor building must be posted with personnel to brief those entering the building after operations announce that the igniters will be energized.

[20]

NOTIFY operations to announce that Hydrogen Igniter Heaters will be energized in the Containment, AND RECEIVE concurrence to proceed.

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 95 of 123 Data Package: Page

-of 6.3 Hydrogen Igniter Functional Tests - Train B (continued)

[21]

PLACE Handswitch 2-HS-268-74, H2 IGNITERS GROUP B, at MRC Panel 2-M-10, in the ON position, AND RECORD time.

Time

[22]

RECORD Phase-to-Phase bus voltage measurements at Panel 2-DPL-268-2-B, AND Date VERIFY voltage is between 230.36 VAC and 233.82 VAc.

A.

M&TE Cal Due Date A-B VAC (230.36-233.82 VAC)

B.

M&TE B-C Cal Due Date VAC (230.36-233.82 VAC)

Cal Due Date C.

M&TE C-A VAc (230.36-233.82 VAc)

Data Package: Page

-of Date 6.3 Hydrogen Igniter Functional Tests - Train B (continued)

[23]

IF any voltage measurement in 6.3[22] is NOT 230.26 to 233.82 VAc, THEN ADJUST potentiometer R13 in 2-DXF-268-268-2-B on control board AlA for Phase A, Al B for Phase B, and Al C for Phase C so that each phase is 230.26 to 233.82 VAC, AND RECORD as-left voltages for each phase below:

A.

Phase A to Phase B:

VAC B.

Phase B to Phase C:

VAC C.

Phase C to Phase A:

VAC

6.3 Data Package: Page

-of Hydrogen Igniter Functional Tests - Train B (continued)

[24]

RECORD Phase-to-Neutral bus voltage measurements at Panel 2-DPL-268-2-B, and VERIFY voltage is between 132 and 135 VAc.

A.

Date M&TE A-NEUTRAL Cal Due Date VAC (132.- 135 VAc)

B.

M&TE B-NEUTRAL Cal Due Date VAC (132 - 135 VAC)

C.

M&TE C-NEUTRAL Cal Due Date VAC (1,: 2 - 135 VAc)

Data Package: Page

-of Hydrogen Igniter Functional Tests - Train B (continued)

Date 6.3 1) 2)

3) 4)

NOTE The following step verifies both igniters are energized by measuring a current greater than 7.4 amperes at the breaker.

If the current reading is between 3.7 and 4.4 amperes one igniter is considered to be operable.

Current readings between 4.4 and 7.4 indicate a fault of an indeterminable nature and will require further troubleshooting to resolve.

Breaker #18 is a spare breaker.

[25]

VERIFY 7.4 amperes or greater measured at each breaker (#1 through #17 in any order) at Panel 2-DPL-268-2-B after a minimum of 5 minutes from time recorded in Step 6.3[21].

M&TE Cal Due Date BREAKER NUMBER AMPERES BREAKER NUMBER AMPERES 1

10 2

11 3

12 4

13 5

14 6

15 7

16 8

17 9

[26]

PLACE Handswitch 2-HS-268-74, H2 IGNITERS GROUP B, in the OFF position, AND RECORD time:

Time

Data Package: Page

-of Date 6.3 Hydrogen Igniter Functional Tests - Train B (continued)

[27]

WHEN the hydrogen igniters have been allowed to cool for at least 30 minutes, THEN PLACE Handswitch 2-HS-268-74, H2 IGNITERS GROUP B, in the ON position, AND RECORD time.

Time

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 100 of 123 Data Package: Page of Date 6.3 Hydrogen Igniter Functional Tests - Train B (continued)

NOTES

1)

Measurements of igniter temperatures are by line-of-sight view (profile or oblique) using optical thermography and should indicate a stabilized temperature. Directly head-on (end) views of the hydrogen igniter may measure lower than actual temperature and should be avoided. See Appendix C, Temperature Conversion Chart, for conversion from °C to OF if required.

2)

Steps 6.3[28] and 6.3[29] are performed concurrently by breaker number.

3)

Igniter Component ID numbers are typical of the following example: ( #3 is 2-HTR-268-0003 and #68 is 2-HTR-268-0068).

[28]

WHEN the hydrogen igniters have warmed up 5 minutes to allow the current to the igniters to stabilize, THEN MEASURE and RECORD each of the following hydrogen igniter heater temperatures (in any order by breaker number) using an optical infrared thermometer or a contact thermometer. (See Figures 1 thru 5 for igniter locations)

HYDROGEN TEMPERATURE HYDROGEN TEMPERATURE BREAKER IGNITER IGNITER NUMBER HEATER HEATER

  1. 3 OF
  1. 48 OF BKR #1
  1. 4 OF
  1. 37 OF BKR #2
  1. 9 OF
  1. 10 OF BKR #3
  1. 11 OF
  1. 12 OF BKR #4
  1. 17 OF
  1. 18 OF BKR #5
  1. 19 OF
  1. 20 OF BKR #6
  1. 38 OF
  1. 39 OF BKR #7
  1. 43 OF
  1. 44 OF BKR #8
  1. 41 OF
  1. 59 OF BKR #9
  1. 45 OF
  1. 46 OF BKR #10
  1. 40 OF
  1. 47 OF BKR #11
  1. 51 OF
  1. 52 OF BKR #12
  1. 56 OF_
  1. 57 OF BKR #13
  1. 58 OF
  1. 60 OF BKR #14
  1. 61 OF
  1. 62 OF BKR #15
  1. 63 OF
  1. 64 OF BKR #16
  1. 67 OF
  1. 68 OF BKR#17 M&TE Cal Due Date

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 101 of 123 Data Package: Page

-of Date 6.3 Hydrogen Igniter Functional Tests - Train B (continued)

NOTES

1)

The following step is performed concurrently with Step 6.3[28] in a manner to obtain measurements as close as possible to the time when igniter temperatures are measured by indicated breaker number.

2)

Power Factor of 1.0 is assumed for calculation.

[29]

CALCULATE total load wattage for each Panel 2-DPL-268-2-B Breaker as follows: (Acc Crit)

VOLTMETER M&TE Cal Due Date AMMETER M&TE Cal Due Date

[29.1]

RECORD Volts and Amps measurements for 2-BKR-268-2/1-B, (Breaker 1).

VOLTS AMPS

[29.2]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-2/1 -B, (Breaker 1).

Watts Calculations Performed by:

Calculations Verified by:

[29.3]

RECORD Volts and Amps measurements for 2-BKR-268-2/2-B, (Breaker 2).

VOLTS AMPS

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 102 of 123 Data Package: Page of Date 6.3 Hydrogen Igniter Functional Tests - Train B (continued)

[29.4]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-2/2-B, (Breaker 2).

Watts Calculations Performed by:

Calculations Verified by:

[29.5]

RECORD Volts and Amps measurements for 2-BKR-268-2/3-B, (Breaker 3).

VOLTS AMPS

[29.6]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-2/3-B, (Breaker 3).

Watts Calculations Performed by:

Calculations Verified by:

[29.7]

RECORD Volts and Amps measurements for 2-BKR-268-2/4-B, (Breaker 4).

VOLTS AMPS

6.3 Data Package: Page

-of Date Hydrogen Igniter Functional Tests - Train B (continued)

[29.8]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-2/4-B, (Breaker 4).

Watts Calculations Performed by:

Calculations Verified by:

[29.9]

RECORD Volts and Amps measurements for 2-BKR-268-2/5-B, (Breaker 5).

VOLTS AMPS

[29.10]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-2/5-B, (Breaker 5).

Watts Calculations Performed by:

Calculations Verified by:

[29.11]

RECORD Volts and Amps measurements for 2-BKR-268-2/6-B, (Breaker 6).

VOLTS AMPS

Data Package: Page of Date 6.3 Hydrogen Igniter Functional Tests - Train B (continued)

[29.12]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-2/6-B, (Breaker 6).

Watts Calculations Performed by:

Calculations Verified by:

[29.13]

RECORD Volts and Amps measurements for 2-BKR-268-2/7-B, (Breaker 7).

VOLTS AMPS

[29.14]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-2/7-B, (Breaker 7).

Watts Calculations Performed by:

Calculations Verified by:

[29.15]

RECORD Volts and Amps measurements for 2-BKR-268-2/8-B, (Breaker 8).

VOLTS AMPS

6.3 Data Package: Page

-of Hydrogen Igniter Functional Tests - Train B (continued)

[29.16]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-2/8-B, (Breaker 8).

Watts Date Calculations Performed by:

Calculations Verified by:

[29.17]

RECORD Volts and Amps measurements for 2-BKR-268-2/9-B, (Breaker 9).

VOLTS AMPS

[29.18]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-2/9-B, (Breaker 9).

_Watts Calculations Performed by:

Calculations Verified by:

[29.19]

RECORD Volts and Amps measurements for 2-BKR-268-2/1 0-B, (Breaker 10).

VOLTS AMPS

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 106 of 123 6.3 Data Package: Page

-of Hydrogen Igniter Functional Tests - Train B (continued)

[29.20]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-2/1 0-B, (Breaker 10).

Watts Date Calculations Performed by:

Calculations Verified by:

[29.21]

RECORD Volts and Amps measurements for 2-BKR-268-2/1 I-B, (Breaker 11).

VOLTS AMPS

[29.22]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-2/1 I-B, (Breaker 11).

Watts Calculations Performed by:

Calculations Verified by:

[29.23]

RECORD Volts and Amps measurements for 2-BKR-268-2/12-B, (Breaker 12).

VOLTS AMPS

Data Package: Page of Date 6.3 Hydrogen Igniter Functional Tests - Train B (continued)

[29.24]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-2/12-B, (Breaker 12).

Watts Calculations Performed by:

Calculations Verified by:

[29.25]

RECORD Volts and Amps measurements for 2-BKR-268-2/13-B, (Breaker 13).

VOLTS AMPS

[29.26]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-2/13-B, (Breaker 13).

Watts Calculations Performed by:

Calculations Verified by:

[29.27]

RECORD Volts and Amps measurements for 2-BKR-268-2/14-B, (Breaker 14).

VOLTS AMPS

6.3 Data Package: Page

-of Hydrogen Igniter Functional Tests - Train B (continued)

[29.28]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-2/14-B, (Breaker 14).

Watts Date Calculations Performed by:

Calculations Verified by:

[29.29]

RECORD Volts and Amps measurements for 2-BKR-268-2/15-B, (Breaker 15).

VOLTS AMPS

[29.30]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-2/15-B, (Breaker 15).

Watts Calculations Performed by:

Calculations Verified by:

[29.31]

RECORD Volts and Amps measurements for 2-BKR-268-2/16-B, (Breaker 16).

VOLTS AMPS

6.3 Data Package: Page of Hydrogen Igniter Functional Tests - Train B (continued)

[29.32]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-2/16-B, (Breaker 16).

Watts Date Calculations Performed by:

Calculations Verified by:

[29.33]

RECORD Volts and Amps measurements for 2-BKR-268-2/17-B, (Breaker 17).

VOLTS AMPS

[29.34]

MULTIPLY Volts and Amps measurements recorded in previous step, AND RECORD total load wattage for 2-BKR-268-2/17-B, (Breaker 17).

Watts Calculations Performed by:

Calculations Verified by:

Data Package: Page

-of Hydrogen Igniter Functional Tests - Train B (continued)

Date 6.3

[30]

OPEN 2-BKR-268-2/1-B (Breaker 1).

CV A.

VERIFY Igniter #3 is observed to be OFF.

B.

VERIFY Igniter #48 is observed to be OFF.

[31]

CLOSE 2-BKR-268-2/1-B (Breaker 1).

CV

[32]

OPEN 2-BKR-268-2/2-B (Breaker 2).

A.

VERIFY Igniter #4 is observed to be OFF.

B.

VERIFY Igniter #37 is observed to be OFF.

[33]

CLOSE 2-BKR-268-2/2-B (Breaker 2).

CV

[34]

OPEN 2-BKR-268-2/3-B (Breaker 3).

CV A.

B.

VERIFY Igniter #9 is observed to be OFF.

VERIFY Igniter #10 is observed to be OFF.

Data Package: Page

-of 6.3 Hydrogen Igniter Functional Tests - Train B (continued)

[35]

CLOSE 2-BKR-268-2/3-B (Breaker 3).

[36]

OPEN 2-BKR-268-2/4-B (Breaker 4).

Date A.

VERIFY Igniter #11 is observed to be OFF.

B.

VERIFY Igniter #12 is observed to be OFF.

[37]

CLOSE 2-BKR-268-2/4-B (Breaker 4).

[38]

OPEN 2-BKR-268-2/5-B (Breaker 5).

CV CV CV CV CV CV A.

VERIFY Igniter #17 is observed to be OFF.

B.

VERIFY Igniter#18 is observed to be OFF.

[39]

CLOSE 2-BKR-268-2/5-B (Breaker 5).

[40]

OPEN 2-BKR-268-2/6-B (Breaker 6).

A.

VERIFY Igniter #19 is observed to be OFF.

B.

VERIFY Igniter #20 is observed to be OFF.

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 112 of 123 Data Package: Page

-of 6.3 Hydrogen Igniter Functional Tests - Train B (continued)

[41]

CLOSE 2-BKR-268-2/6-B (Breaker 6).

Date.

cv

[42]

OPEN 2-BKR-268-2/7-B (Breaker 7).

CV A.

VERIFY Igniter #38 is observed to be OFF.

B.

VERIFY Igniter #39 is observed to be OFF.

[43]

CLOSE 2-BKR-268-2/7-B (Breaker 7).

CV

[44]

OPEN 2-BKR-268-2/8-B (Breaker 8).

CV A.

VERIFY Igniter #43 is observed to be OFF.

B.

VERIFY Igniter #44 is observed to be OFF.

[45]

CLOSE 2-BKR-268-2/8-B (Breaker 8).

CV

[46]

OPEN 2-BKR-268-2/9-B (Breaker 9).

CV A.

B.

VERIFY Igniter #41 is observed to be OFF.

VERIFY Igniter #59 is observed to be OFF.

Data Package: Page

-of Date 6.3 Hydrogen Igniter Functional Tests - Train B (continued)

[47]

CLOSE 2-BKR-268-2/9-B (Breaker 9).

CV

[48]

OPEN 2-BKR-268-2/1 0-B (Breaker 10).

A.

VERIFY Igniter #45 is observed to be OFF.

B.

VERIFY Igniter #46 is observed to be OFF.

[49]

CLOSE 2-BKR-268-2/10-B (Breaker 10).

CV

[50]

OPEN 2-BKR-268-2/11 1-B (Breaker 11).

CV A.

VERIFY Igniter #40 is observed to be OFF.

B.

VERIFY Igniter #47 is observed to be OFF.

[51]

CLOSE 2-BKR-268-2/11-B (Breaker 11).

CV

[52]

OPEN 2-BKR-268-2/12-B (Breaker 12).

CV A.

VERIFY Igniter #51 is observed to be OFF.

B.

VERIFY Igniter #52 is observed to be OFF.

[53]

CLOSE 2-BKR-268-2/12-B (Breaker 12).

CV

Data Package: Page

-of Date 6.3 Hydrogen Igniter Functional Tests - Train B (continued)

[54]

OPEN 2-BKR-268-2/13-B (Breaker 13).

CV A.

VERIFY Igniter #56 is observed to be OFF.

B.

VERIFY Igniter #57 is observed to be OFF.

[55]

CLOSE 2-BKR-268-2/13-B (Breaker 13).

CV

[56]

OPEN 2-BKR-268-2/14-B (Breaker 14).

CV A.

VERIFY Igniter #58 is observed to be OFF.

B.

VERIFY Igniter #60 is observed to be OFF.

[57]

CLOSE 2-BKR-268-2/14-B (Breaker 14).

CV

[58]

OPEN 2-BKR-268-2/15-B (Breaker 15).

CV A.

VERIFY Igniter #61 is observed to be OFF.

B.

VERIFY Igniter #62 is observed to be OFF.

[59]

CLOSE 2-BKR-268-2/15-B (Breaker 15).

CV

Data Package: Page

-of 6.3 Hydrogen Igniter Functional Tests - Train B (continued)

[60]

OPEN 2-BKR-268-2/16-B (Breaker 16).

A.

VERIFY Igniter #63 is observed to be OFF.

B.

VERIFY Igniter #64 is observed to be OFF.

[61]

CLOSE 2-BKR-268-2/16-B (Breaker 16).

[62]

OPEN 2-BKR-268-2/17-B (Breaker 17).

Date CV CV CV CV A.

VERIFY Igniter #67 is observed to be OFF.

B.

VERIFY Igniter #68 is observed to be OFF.

[63]

CLOSE 2-BKR-268-2/17-B (Breaker 17).

NOTE Breaker 18, 2-BKR-268-2/18-B, is a spare breaker.

[64]

VERIFY each igniter temperature recorded in Step 6.3[28] is 1741.2 0F or greater. (Acc Crit)

[65]

VERIFY wattages recorded in Step 6.3[29] do not individually exceed 1335.3 watts. (Acc Crit)

Data Package: Page

-of 6.3 Hydrogen Igniter Functional Tests - Train B (continued)

[66]

RECORD Phase-to-Phase bus voltage measurements at Panel 2-DPL-268-2-B, AND VERIFY voltage is between 230.36 VAC and 233.82 VAC.

A.

Date M&TE B.

M&TE A-B3 B-C Cal Due Date VAc (230.36-233.82 VAC)

Cal Due Date VAC (230.36-233.82 VAC)

Cal Due Date C.

M&TE C-A VAC (230.36-233.82 VAC)

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 117 of 123 Data Package: Page of Date 6.3 Hydrogen Igniter Functional Tests - Train B (continued)

[67]

IF any voltage measurement in 6.3[66] is NOT 230.26 to 233.82 VAC, THEN ADJUST potentiometer R13 in 2-DXF-268-268-2-B on control board AlA for Phase A, AlB for Phase B, and A1C for Phase C so that each phase is 230.26 to 233.82 VAc, AND RECORD as-left voltages for each phase below:

A.

Phase A to Phase B:

VAC B.

Phase B to Phase C:

VAC C.

Phase C to Phase A:

VAC

6.3 Data Package: Page

-of Hydrogen Igniter Functional Tests - Train B (continued)

[68]

RECORD Phase-to-Neutral bus voltage measurements at Panel 2-DPL-268-2-B, AND VERIFY voltage is between 132 and 135 VAc.

A.

Date M&TE A-NEUTRAL Cal Due Date VAC (132 - 135 VAC)

B.

M&TE B-NEUTRAL C.

Cal Due Date VAC (032 - 135 VA)

Cal Due Date VAC (03 2 - 135 VAc)

M&TE C-NEUTRAL

[69]

PLACE Handswitch 2-HS-268-74, H2 IGNITERS GROUP B, in the OFF position.

Data Package: Page of Date 7.0 POST PERFORMANCE ACTIVITIES

[1]

NOTIFY the Shift Manager (SM) of the test completion and System alignment.

[2]

VERIFY that Post-test calibration of the M&TE used to record quantitative acceptance criteria has been satisfactorily performed and the results RECORDED on Measuring and Test Equipment (M&TE) Log.

Cv 8.0 RECORDS A.

QA Records Completed Test Package B.

Non QA Records None

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 120 of 123 Appendix A (Pagel of 1)

TEST PROCEDURESIINSTRUCTIONS REFERENCE REVIEW Data Package: Page

-of Date NOTES

1)

Additional copies of this table may be made as necessary.

2)

Initial and date indicates review has been completed for impact.

PROCEDURE/

INITIAL AND DATE.

INSTRUCTION REVISIONCHANGES (N/A for no change)

WBN2-83-4001 FSAR Section 6.2.5A Table 14.2-1 Sht 40 of 89 2-TSD-268-01 WBN-VTM-N431-0090 WBN-VTM-P319-0010

Appendix B (Page I of 1)

TEMPORARY CONDITION LOG Data Package: Page

-of Date NOTE These steps will be N/A'd if no temporary condition existed. Additional copies of this table may be made as necessary.

TEMPORARY PERFORMED RETURNED TO NORMAL ITEM CONDITION Step Perf. By/Date Step Returned By/Date NUMBER DESCRIPTION Number CV By/Date Number CV By/Date

Table 1 (Page I of 2)

TEMPERATURE CONVERSION CHART Data Package: Page

-of Date NOTE The relation between degrees Fahrenheit and degrees Centigrade (Celsius) is expressed by the following formula:OC = 5/9 (OF - 32) or OF = 9/5 (°C) + 32 DEGREES DEGREES DEGREES DEGREES DEGREES DEGREES

(°C)

(OF)

(OC)

(OF)

(°C)

(OF) 862 °C= 1583.6 OF 887 °C = 1628.6 °F 912 °C = 1673.6 IF 863 °C = 1585.4 OF 888 °C = 1630.4 °F 913 °C = 1675.4 OF 864 °C = 1587.2 OF 889 °C = 1632.2 OF 914 °C = 1677.2 OF 865 °C = 1589.0 OF 890 °C = 1634.0 OF 915 °C = 1679.0 IF 866 °C = 1590.8 'F 891 °C = 1635.8 OF 916 °C = 1680.8 OF 867 'C = 1592.6 OF 892 C =1637.6 OF 917 'C = 1682.6 OF 868 °C = 1594.4 OF 893 OC = 1639.4 OF 918 IC = 1684.4 OF 869 C =1596.2 OF 894 C =1641.2 IF 919 °C = 1686.2 OF-870 °C = 1598.0 OF 895 °C = 1643.0 OF 920 °C = 1688.0 OF 871 C =1599.8 OF 896 °C = 1644.8 °F 921 °C = 1689.8 OF 872 C =1601.6 OF 897 °C = 1646.6 IF 922 °C = 1691.6 IF 873 °C = 1603.4 OF 898 °C = 1648.4 OF 923 °C = 1693.4 OF 874 OC = 1605.2 OF 899 °C = 1650.2 OF 924 °C = 1695.2 IF 875 °C = 1607.0 OF 900 °C = 1652.0 OF 925 °C = 1697.0 OF 876 °C = 1608.8 OF 901 OC = 1653.8 OF 926 OC = 1698.8 OF 877 °C = 1610.6 OF 902 °C = 1655.6 OF 927 °C = 1700.6 IF 878 °C = 1612.4 OF 903 °C = 1657.4 OF 928 °C = 1702.4 OF 879 °C = 1614.2 IF 904 °C = 1659.2 IF 929 °C = 1704.2 OF 880 °C = 1616.0 IF 905 °C = 1661.0 OF 930 °C = 1706.0 OF 881 °C = 1617.8 OF 906 °C = 1662.8 OF 931 °C = 1707.8 OF 882 0C = 1619.6 OF 907 °C = 1664.6 °F 932 °C = 1709.6 IF, 883 °C = 1621.4 OF 908 °C = 1666.4 OF 933 °C = 1711.4 OF 884 °C = 1623.2 IF 909 °C = 1668.2 OF 934 °C = 1713.2 OF 885 °C = 1625.0 OF 910 °C = 1670.0 OF 935 'C = 1715.0 OF 886 °C = 1626.8 OF 911 °C = 1671.8 OF 936 °C = 1716.8 OF

WBN PERMANENT HYDROGEN MITIGATION 2-PTI-268-01 Unit 2 SYSTEM Rev. 0000 Page 123 of 123 Table 1 (Page 2 of 2)

TEMPERATURE CONVERSION CHART Data Package: Page of Date NOTE The relation between degrees Fahrenheit and degrees Centigrade (Celsius) is expressed by the following formula:°C = 5/9 (OF - 32) or OF = 9/5 (°C) + 32 DEGREES DEGREES DEGREES DEGREES DEGREES DEGREES

(°C)

(OF)

(°C)

(OF)

(0C)

(OF) 937 °C = 1718.6 OF 962 °C = 1763.6 OF 987 °C = 1808.6 °F 938 OC = 1720.4 OF 963 'C = 1765.4 IF 988 °C = 1810.4 °F 939 OC = 1722.2 OF 964 °C = 1767.2 OF 989 OC = 1812.2 OF 940 OC = 1724.0 OF 965 °C = 1769.0 OF 990 0C = 1814.0 OF 941 °C = 1725.8 OF 966 °C = 1770.8 OF 991 °C = 1815.8 OF 942 °C = 1727.6 °F 967 °C = 1772.6 OF 992 OC = 1817.6 IF 943 °C = 1729.4 OF 968 °C = 1774.4 OF 993 °C 1819.4 OF 944 °C = 1731.2 IF 969 'C = 1776.2 °F 994 C= 1821.2 IF 945 OC = 1733.0 OF 970 °C = 1778.0 OF 995 °C = 1823.0 IF 946 °C = 1734.8 OF 971 °C = 1779.8 IF 996 °C = 1824.8 °F 947 °C = 1736.6 OF 972 °C = 1781.6 IF 997 C= 1826.6 IF 948 °C = 1738.4 IF 973 °C = 1783.4 OF 998 IC = 1828.4 OF 949 °C = 1740.2 IF 974 °C = 1785.2 OF 999 OC = 1830.2 IF 950 °C = 1742.0 OF 975 °C = 1787.0 OF 1000 °C = 1832.0 OF 951 °C = 1743.8 OF 976 °C = 1788.8 IF 1001 IC = 1833.8 IF 952 °C = 1745.6 OF 977 'C = 1790.6 IF 1002 °C = 1835.6 OF 953 °C = 1747.4 OF 978 °C = 1792.4 OF 1003 °C = 1837.4 OF 954 °C = 1749.2 OF 979 °C = 1794.2 OF 1004 °C = 1839.2 OF 955 °C = 1751.0 OF 980 °C = 1796.0 OF 1005 °C = 1841.0 OF 956 °C = 1752.8 OF 981 °C = 1797.8 OF 1006 °C = 1842.8 OF 957 °C = 1754.6 OF 982 °C = 1799.6 OF 1007 °C = 1844.6 OF 958 °C = 1756.4 OF 983 °C = 1801.4 OF 1008 °C = 1846.4 OF 959 °C = 1758.2 OF 984 °C = 1803.2 OF 1009 °C C

1848.2 °F 960 °C = 1760.0 OF 985 °C = 1805.0 OF 1010 OC = 1850.0 OF 961 °C =.1761.8 OF 986 'C = 1806.8 IF 1011 -C = 1851.8 OF