UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 6, 2010 LICENSEE:
Entergy Operations, Inc.
FACILITIES: Palisades Nuclear Plant SUB..IECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON FEBRUARY 24,2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC. REGARDING PROGRESS ON NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805 TRANSITION ACTIVITIES A teleconference was held between representatives of Entergy Nuclear Operations, Inc. (ENO) and the Nuclear Regulatory Commission (NRC) staff to discuss progress on the Palisades Nuclear Plant (PNP) National Fire Protection Association (NFPA) 805 transition activities. ENO submitted "Palisades NFPA 805 Project Milestones" table (see Enclosure 1) which provides the list of NFPA 805 transition activities and their status. The licensee reported that further schedule delays have occurred due to increase in the work scope and the availability of the resources. Also, based on the published schedule for the second NFPA 805 Pilot Plant (Oconee) safety evaluation, the licensee has also changed the final completion date for the project from September 30, 2010, to December 31, 2010. Enclosure 2 provides the list of all attendees.
Background
On December 9, 2008 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML083260577), NRC staff granted additional enforcement discretion to Palisades. ENO in its letter dated November 25, 2008 (ADAMS Accession No. ML083370155) made a commitment to conduct a monthly teleconference with the NRC staff to discuss progress on the PNP NFPA 805 transition activities.
Mahesh Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255
Enclosures:
1: Table - Palisades NFPA 805 Project Milestones 2: Table - List of Attendees cc w/encls: Distribution via ListServ
2/24/2010 Palisades NFPA 805 Project Milestones NEI Task No.
Title Milestone Date' Status2 Start Date.
Task 1:
Transition of Nuclear Safety Performance Criteria INEI 04-02 Table B-2) 09/24/10 See Comments Task 2:
Fundamental Fire Protection Program & Desig Elements (NEI 04-02 Table B-1) 09/23/10 See Comments Task 3:
Radioactive Release Transition (NEI 04-02 Table G-1) 09/23/10 See Comments Task 4:
Nuclear Safety Analysis Transition (NEI 04-02 Table B-3) 11/01/10 See Comments ST 4.1.1 Off-Site Power Cable Selection and Analysis 11/01/10 See Comments ST4.1.2 Other Power Cable Selection and Analysis Complete ST 4.1.3 Subsequent Cable/Instrument Identification &
Analysis 06/18/10 See Comments Task 5:
Non-Power Operational Modes Transition IINEI 04-02 Table F-1) 09/23/10 See Comments Task 6:
Internal Events PRA 11/12/10 See Comments OS/24/10 03/15/10 ST 6.2.1 Prepare LERF Model Complete ST 6.2.2 Update Flooding Analysis Complete ST6.3 Thermal Hvdraulic Analvsis for MSO/HRA 09/17/10 See Comments ST6.4 Internal Events PRA Peer Review Complete Task 7:
Fire PRA 10/12/10 See Comments ST 7.6.4 R3 Internal Events Model Complete ST7.7 Quantification Risk Screening Complete ST7.8 Scoping for Fire Modeling Complete ST 7.9/10 Circuit Failure Mode Likelihood Analysis Complete ST 7.12 Post Fire HRA 08/27/10 See Comments ST 7.13 Seismic Fire Interaction Assessment Complete ST 7.14 Fire Risk Quantification 08/06/10 See Comments ST 7.15 Uncertainty and Sensitivity Analysis 08/06/10 See Comments ST 7.17.4 In-Process Fire PRA Peer Review Complete ST 7.17.5 Final Fire PRA Peer Review 06/25/10 On Track Task 8:
NFPA 805 Fire Risk / Change Evaluations 09/23/10 See Comments ST 8.1 Fire Risk / Change Evaluations 09/23/10 See Comments ST 8.2 Non-Compliance Risk Evaluations 09/23/10 See Comments Task 9:
Palisades Mapping of Post Transition Procedures & Document Revisions 03/28/12 See Comments Task 10:
Transition Report 11/15/10 See Comments Task 11:
License Amendment Request (LAR) 12/31/10 See Comments Notes:
1 The current schedule (805 T1-6H 15FEB10) dates were validated to be on or before these dates unless otherwise noted.
2 "On Track" means that the task current percentage completed is ~ the expected completion percent and the expected completion date for the task is projected to be met 3 Start dates provided are estimates and may vary contingent upon predecessor completion and available resources at that time. Even if this start date IS adjusted, the completion date is still expected to be met unless indicated otherwise.
Comments:
~ The LAR submittal has received Entergy Management approval. The other task dates have been adjusted support this date.
~ Task 9 has been removed from the Pre-LAR tasks and placed in the Post LAR tasks.
E:IPaiisadeslPLPIEnforcement ExtensionlNRC Conf callslMilestone ItrslNRC Milestones 02-24-10.xls
TELEPHONE CONFERENCE CALL ON NFPA 805 TRANSITION PROGRESS BETWEEN U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC.
LIST OF PARTICIPANTS FEBRUARY 24,2010 PARTICIPANTS TITLE/POSITION AFFILIATIONS U.S. NUCLEAR REGULATORY COMMISSION (NRC)
Mahesh Chawla Proiect Manaaer HEADQUARTERS Alex Klein Branch Chief Harrv Barrett Senior Fire Protection Enaineer ENTERGY Paula Anderson Licensing Manager Jim Kuemin Licensing Engineer Tom Swiecicki Fire Protection Lead Chad Main Project Manager Brian Bogan PRA Lead Roger Stobert Contract Project Manager NFPA 805 Ron Penna Program Engineering Supervisor Pablo Guardado Corporate Engineer
ML083370155) made a commitment to conduct a monthly teleconference with the NRC staff to discuss progress on the PNP NFPA 805 transition activities.
Mahesh Chawla, Project Manager IRAJ Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255
Enclosures:
1: Table - Palisades NFPA 805 Project Milestones 2: Table - List of Attendees cc w/encls: Distribution via Listserv Distribution:
PUBLIC LPL3-1 r/f RidsRgn3MailCenter Resource AKlein, NRR JGeissner, Rill RidsNrrDorLpl3-1 Resource RidsNrrPMANO Resource MVaaler, NRR TTaylor, Rill RidsNrrPMPalisades Resource RidsNrrLABTully Paul Lain, NRR HBarrett RidsAcrsAcnw_MailCtr Resource RidsOgcRp Resource JEliegood, Rill SBagley, EDO R-1I1 CTucci, NRR ADAMS Accession No' ML100890209 OFFICE LPL3-1/PM LPL3-1/LA DRNAFPB/BC LPL3-1/BC NAME MChawla BTuily AKlein RPascarelli DATE 04/02/10 04/01/10 04/06/10 04/06/10