Ltr. 12/18/2009 Fermi Re NRC Predecisional Enforcement Conference Summary
ML093521312
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 12/18/2009
From: Hironori Peterson
Operations Branch III
To: Jennifer Davis
Detroit Edison
References
EA-09-267, IR-09-010
Download: ML093521312 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 December 18, 2009 EA-09-267 Mr. Jack M. Davis Senior Vice President and Chief Nuclear Officer Detroit Edison Company Fermi 2 - 210 NOC 6400 North Dixie Highway Newport, MI 48166

SUBJECT:

NRC PREDECISIONAL ENFORCEMENT CONFERENCE

SUMMARY

FERMI POWER PLANT, UNIT 2

Dear Mr. Davis:

This letter transmits to you a summary of the Predecisional Enforcement Conference held on December 14, 2009, at the U.S. Nuclear Regulatory Commission (NRC) Region III office. The purpose of the conference was to discuss the apparent violation identified in NRC Inspection Report No. 05000341/2009010(DRS).

In accordance with the NRC Enforcement Manual, the statements and information provided during the Predecisional Enforcement Conference will assist the NRC in making an enforcement decision. You will be advised by separate correspondence of the results of our deliberations on this matter. No response regarding the apparent violation is required at this time.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the NRCs Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

Hironori Peterson, Chief Operations Branch Docket No. 50-341 License No. NPF-43

Enclosure:

Predecisional Enforcement Conference Summary cc w/encl:

Distribution via ListServ

Enclosure PREDECISIONAL ENFORCEMENT CONFERENCE

SUMMARY

Licensee:

Detroit Edison Company Facility:

Fermi 2 License No.: NPF-43 Docket No.:

Docket No. 50-341 EA-09-267 On December 14, 2009, representatives of the Detroit Edison Company met with NRC personnel in the Region III office located in Lisle, Illinois, to discuss the apparent violation identified in NRC Inspection Report No. 05000341/2009010(DRS). The conference was held at the request of Detroit Edison.

The licensee summarized the apparent violation and provided its perspective on the violation, including the significance level and its corrective actions.

The NRC attendance list is attached to this summary. The slides presented at the conference are available in ADAMS (Accession # ML093480219).

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the NRCs Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

Enclosure Predecisional Enforcement Meeting Attendance List Licensee:

Joseph Plona Fermi Site Vice President Todd Conner Fermi Plant Manager James W. Davis Manager, Nuclear Training Rodney Johnson Manager, Licensing NRC:

Cynthia Pederson Deputy Regional Administrator Anne Boland Division Director, DRS Gary Shear Deputy Division Director, DRP Steven Orth Enforcement Officer Gerry Gulla Enforcement Specialist - HQ John J. McHale IOLB Branch Chief - NRR Hironori Peterson Branch Chief, Operator Licensing Raymond K Walton Operations Engineering Inspector Jared Heck Regional Council Prema Chandrathil Public Affairs Officer, Region III Diana Betancourt Reactor Engineer, DRP Jasmine Gilliam Reactor Engineer, DRS Magdalena Gryglak Enforcement Specialist Paul Pelke Enforcement Specialist

EA-09-267 Mr. Jack M. Davis Senior Vice President and Chief Nuclear Officer Detroit Edison Company Fermi 2 - 210 NOC 6400 North Dixie Highway Newport, MI 48166

SUBJECT:

NRC PREDECISIONAL ENFORCEMENT CONFERENCE

SUMMARY

FERMI POWER PLANT, UNIT 2

Dear Mr. Davis:

This letter transmits to you a summary of the Predecisional Enforcement Conference held on December 14, 2009, at the U.S. Nuclear Regulatory Commission (NRC) Region III office. The purpose of the conference was to discuss the apparent violation identified in NRC Inspection Report No.

05000341/2009010(DRS).

In accordance with the NRC Enforcement Manual, the statements and information provided during the Predecisional Enforcement Conference will assist the NRC in making an enforcement decision. You will be advised by separate correspondence of the results of our deliberations on this matter. No response regarding the apparent violation is required at this time.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the NRCs Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

Hironori Peterson, Chief Operations Branch Docket No. 50-341 License No. NPF-43

Enclosure:

Predecisional Enforcement Conference Summary cc w/encl:

Distribution via ListServ DISTRIBUTION:

See next page DOCUMENT NAME: R:\\Ltrs to licensees\\Detroit Edison - Fermi\\Ferm 2009\\FER 121809 PEC Summary EA-09-267.doc Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII E

RIII E

RIII E

RIII E

NAME RWalton:jb PPelke SOrth PP for HPeterson DATE 12/17/09 12/17/09 12/18/09 12/18/09 OFFICIAL RECORD COPY

Letter to Jack M. Davis from Hironori Peterson dated December 18, 2009.

SUBJECT:

NRC PREDECISIONAL ENFORCEMENT CONFERENCE

SUMMARY

FERMI POWER PLANT, UNIT 2 DISTRIBUTION:

ADAMS (PARS)

RidsSecyMailCenter.Resource OCADistribution Bill Borchardt Bruce Mallett Roy Zimmerman Belkys Sosa Marvin Itzkawitz Catherine Scott Eric Leeds Bruce Boger Mark Satorius Cynthia Pederson Daniel Holody Carolyn Evans Steven Orth William Jones Gerald Gulla Marcy Ann Ashley Holly Harrington Hubert Bell Guy Caputo Mona Williams James Lynch Viktoria Mitlyng Prema Chandrathil Harral Logaras Jared Heck Allan Barker Patricia Lougheed Paul Pelke Magdalena Gryglak OEMAIL Resource OEWEB Resource Susan Bagley RidsNrrPMPrairieIsland RidsNrrDorlLpl3-1 Resource RidsNrrDirsIrib Resource Carole Ariano Linda Linn DRPIII DRSIII ROPreports Resource OEWEB