UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II SAM NUNN ATLANTA FEDERAL CENTER 61 FORSYTH STREET, SW, SUITE 23T85 ATLANTA, GEORGIA 30303-8931 March 30, 2009 Mr. Ashok S. Bhatnagar Senior Vice President Nuclear Generation Development and Construction Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
SUBJECT:
MEETING ANNOUNCEMENT - PUBLIC MEETING WATTS BAR NUCLEAR UNIT 2, DOCKET NO. 50-391
Dear Mr. Bhatnagar:
This letter confirms a Category 3 public meeting which has been scheduled for April 14, 2009, at 06:30 p.m. - 8:00 p.m. (EST). The enclosed meeting notice provides additional details. The purpose of the meeting is to provide opportunities to discuss the annual assessment of the Watts Bar Nuclear Unit 2 Construction Project with the public. The NRC will be available to ensure the publics issues and concerns are understood and considered.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Should you have any questions concerning this meeting, please contact me at (404) 562-6347.
Sincerely,
/RA/
Robert C. Haag, Chief Construction Projects Branch 3 Division of Construction Projects Docket No.: 50-391
Enclosure:
As stated
TVA 2
cc w/ encl:
Gordon P. Arent, Manager New Generation Licensing Nuclear Generation Development and Construction Watts Bar Nuclear Plant P.O. Box 2000 Spring City, TN 37381 Masoud Bajestani, Vice President Watts Bar Unit Two Watts Bar Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, TN 37381 Michael K. Brandon, Manager Licensing and Industry Affrairs Watts Bar Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, TN 37381 County Executive 375 Church Street Suite 215 Dayton, TN 37321 County Mayor P.O. Box 156 Decatur, TN 37322 Mr. Ashok S. Bhatnagar Senior Vice President Nuclear Generation Development and Construction Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 John Fornicola, General Manager Nuclear Assurance Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 General Counsel Tennessee Valley Authority 6A West Tower 400 West Summit Hill Drive Knoxville, TN 37902 Greg A. Boerschig, Plant Manager Watts Bar Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, TN 37381 Lawrence E. Nanney, Director Tennessee Department of Environmental Health and Conservation Division of Radiological Health 3rd Floor, L&C Annex 401 Church Street Nashville, TN 37243-1532 Larry E. Nicholson, General Manager Performance Improvement Tennessee Valley Authority 4X Blue Ridge 1101 Market Street Chattanooga, TN 37402-2801 Michael D. Skaggs Site Vice President Watts Bar Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, TN 37381 cc cont: (See next page)
TVA 3
cc cont:
Mr. Frederick C. Mashburn, Acting Manager Corporate Nuclear Licensing and Industry Affairs Tennessee Valley Authority 4K Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 Senior Resident Inspector Tennessee Valley Authority Watts Bar Nuclear Plant U.S. NRC 1260 Nuclear Plant Road Spring City, TN 37381-2000 Mr. Thomas Coutu, Vice President Nuclear Support Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 Michael Purcell Senior Licensing Manager Nuclear Power Group Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 Mr. Preston D. Swafford Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402
ML090890761 P SUNSI REVIEW COMPLETE OFFICE RII:DCP SIGNATURE ANI NAME AIssa DATE 3/30/2009 E-MAIL COPY?
YES NO
Letter to Ashok S. Bhatnagar from Robert C. Haag dated March 27, 2009
SUBJECT:
MEETING ANNOUNCEMENT - PUBLIC MEETING HOUSE WATTS BAR NUCLEAR UNIT 2, DOCKET NO. 50-391 Distribution w/encl:
PMNS Headquarters Operation Officer RIDSNRRDIRS R. Raghavan, NRR P. Milano, NRR Region II Administrators Secretary Region II DCP Division Secretary Region II Division Directors and Deputies Region II Counsel Region II State Liaison Officer Region II Public Affairs Officer Region II Resource Management Branch Region II Receptionist Region II Regional Coordinator OEDO L. Slack, RII EICS OE Mail PUBLIC
Enclosure MEETING NOTICE
SUBJECT:
PUBLIC MEETING WATTS BAR NUCLEAR UNIT 2, DOCKET NO. 50-391 FACILITY:
Watts Bar Nuclear Plant Unit 2 Construction Project DOCKET:
50-391 DATE & TIME:
Tuesday, April 14, 2009 06:30 p.m. - 08:00 p.m. (EST)
LOCATION:
Magnuson Hotel, Andrew Johnson Room 1421 Murray's Chapel Rd Sweetwater, TN 37874 PURPOSE:
The purpose of the meeting is to provide opportunities to discuss the annual assessment of the Watts Bar Nuclear Plant Unit 2 Construction Project with the public. The NRC's Policy Statement, "Enhancing Public Participation in NRC Meetings," effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC Web site, www.nrc.gov. The NRC provides reasonable accommodation to individuals with disabilities where appropriate. If you need a reasonable accommodation to participate in this meeting, or need this meeting notice or the transcript or other information from the meeting in another format (e.g., braille, large print), please notify the NRC's meeting contact.
Determinations on requests for reasonable accommodation will be made on a case-by-case basis.
CATEGORY:
This is a Category 3 meeting: The public is invited to fully participate in this meeting. The NRC will be available to ensure the publics issues and concerns are understood and considered by the NRC.
NRC OFFICE(S)
Region II PARTICIPATING:
OTHER None ORGANIZATIONS PARTICIPATING:
PARTICIPANTS:
NRC (partial list)
R. Haag, Chief, Construction Projects Branch 3, Division of Construction Projects (DCP)
W. Bearden, Senior Resident Inspector, Watts Bar Nuclear Plant Unit 2 A. Issa, Construction Project Engineer, DCP MEETING Robert C. Haag, NRC, RII CONTACT:
(404) 562-6347 Robert.Haag@nrc.gov