Isfsl Annual Radioactive Effluent Release Report - January 2008 Through December 2008
ML090650523
Person / Time
Site: Big Rock Point  File:Consumers Energy icon.png
Issue date: 02/26/2009
From: Lahti L
Entergy Nuclear Operations
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards
References
Download: ML090650523 (3)


Text

Entergy Nuclear Operations, Inc.

Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043 February 26,2009 1 0 CFR 72.44(d)(3)

U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Big Rock Point Dockets 50-1 55 and 72-043 License No. DPR-6 2008 ISFSl Annual Radioactive Effluent Release Report - Big Rock Point

Dear Sir or Madam:

In accordance with 10 CFR 72.44(d)(3), Entergy Nuclear Operations, Inc. is submitting the annual independent spent fuel storage installation (ISFSI) radioactive effluent release report for Big Rock Point for the period from January 2008, through December 2008.

Summaw of Commitments Thi letter contains no new commitments and no revisions to existing commitments.

W m.bbed-L LJd&$,

Laurie A. Lahti Licensing Manager Palisades Nuclear Plant Enclosure (1 )

CC Administrator, Region Ill, USNRC BRP Decommissioning Inspector, USNRC NMSS Project Manager, USNRC

ENCLOSURE INDEPENDENT SPENT FUEL STORAGE INSTALLATION ANNUAL RADIOACTIVE EFFLUENT RELEASE REPORT BIG ROCK POINT January 2008 - December 2008 I. FACILITY DESCRIPTION The Independent Spent Fuel Storage Installation (ISFSI) is located within the owner-controlled area of the Big Rock Point (BRP) site. The storage of spent fuel at BRP meets the requirements of 10 CFR 72, and the Certificate of Compliance No. 72-1 026, issued by the Nuclear Regulatory Commission (NRC).

II. EFFLUENT LIMITS AND CONTROLS The ISFSl operates under effluent control limits as required by 10 CFR 72.1 04.

However, the design of the sealed storage canisters at the ISFSl precludes any gaseous or liquid effluent releases.

Ill. RADIOLOGICAL EFFLUENT RELEASES As noted in Section II, by design, there are no radioactive liquid or gaseous effluents originating from the ISFSl facility. The annual radiological surveillance performed during this reporting period did not indicate any release of radioactivity from the ISFSI.

IV. ISFSl ENVIRONMENTAL MONITORING PROGRAM The BRP Radiological Environmental Monitoring Program (REMP) is described in the Offsite Dose Calculation Manual (ODCM),Section I, Subsection 4.0. The ISFSl Environmental Monitoring Program, which is contained within the BRP REMP, consists of thermoluminescent dosimeters (TLDs) at four locations along the perimeter of the ISFSl site, and three control TLDs 10.5 to 50 miles from the site.

Annual TLDs are read annually and quarterly TLDs are read quarterly as reflected in Table 1. Annual and quarterly measurements are compared to control measurements to evaluate compliance with 10 CFR 72.1 04. The results for the ISFSl TLDs and the average of the control TLDs measured in 2008 are summarized in Section Vl.

Page 1 of 2

V. SAMPLE ANOMALIES The following thermoluminescent dosimeters (TLDs) were found to be missing:

VI. ISFSl ENVIRONMENTAL MEASUREMENTS Location BRP-06 (Boyne City)

BRP-07 (Traverse City)

BRP-06 (Boyne City)

BRP-07 (Traverse City)

BRP ISFSl Environmental TLD Results (mR)

January 2008 - December 2008 Type Annual Annual Quarterly Quarterly VII. CONCLUSIONS TLD NoJLocation BRP-18 1 137 meters NW of ISFSl BRP-19 1 137 meters SW of ISFSl BRP-20 1 137 meters SE of ISFSl BRP-21 1137 meters NE of ISFSl Summary of Control Locations, BRP-05, BRP-06, BRP-07 Based on the above measurements performed during the reporting period, it is concluded that the dose from ISFSl operations does not exceed the limits as defined in 10 CFR 72.104.

Expected Collection Date 01 09 01 09 01 09 01 09 Page 2 of 2 Reason Missing in field.

Missing in field.

Missing in field.

Missing in field.

  • Control location BRP-05 (Petoskey) data only, due to other locations found missing.

lSt Quarter 9.7 rt 0.8 11.8

  • 0.9 12.9
  • 0.9 9.8 rt 0.8 15.6 rt 3.2 2nd Quarter 10.1*0.4 12.9 rt 0.6 12.3 rt 0.5 10.3 rt 0.4 15.1
  • 2.0 3rd Quarter 10.2rt0.6 13.8 rt 0.7 14.5
  • 0.8 10.8 rt 0.6 15.8 rt 2.6 4M Quarter 11.5rt0.5 15.4
  • 1.2 14.9
  • 0.9 12.2 rt 0.6 12.8 rt 0.8*

Annual 41.3k1.8 56.0 rt 2.0 56.6

  • 2.1 41.1 rt 1.4 43.5 rt 1.3"