Crystal River Unit 3 Crystal River Unit 3 NRC Public Meeting April 8 2008 April 8, 2008 1

Enclosure

Crystal River Unit 3 Crystal River Unit 3 Safety Performance Safety Performance Measure Actual Goal z Human Performance 3

< 4 z Injury Rate 0 17

< 0 20 z Injury Rate 0.17

< 0.20 z Radiation Exposure 185

< 140 z INPO Index 88.1

> 90.8 2

Enclosure

Crystal River Unit 3 Crystal River Unit 3 Production Production Measure Actual Goal z Capability Factor 2007 89.2

> 87 z Capability Factor 2 Yr Avg 91 2

> 92 2 z Capability Factor 2 Yr Avg 91.2

> 92.2 3

Enclosure

Crystal River Unit 3 Crystal River Unit 3 Refuel 15 Refuel 15 z Completed with No Injuries z Completed in 32 Days z Completed in 32 Days z Large Scope - Plant Improvements 10-Year ISI Measurement Uncertainty Power Uprate (approx 12 MWe)

Transformer Replacements Alloy 600 Mitigation Condenser Cleaning System N-1 for S/G Replacement z Exposure Higher than Anticipated 4

p g

p z March 2008 Outage Enclosure

Crystal River Unit 3 Crystal River Unit 3 Future Future z Steam Generator Replacement (2009) p

(

)

z License Renewal Submittal (2009) z Power Uprate - Three Phase Implementation z Dry Fuel Storage z Progress Energy Commitment - Excellence in O

ti Operations z Involvement with New Plants 5

Enclosure

Crystal River Unit 3 Crystal River Unit 3 Crystal River Unit 3 y

Closing Remarks Closing Remarks 6