ML080810005
| ML080810005 | |
| Person / Time | |
|---|---|
| Site: | Vogtle |
| Issue date: | 04/09/2008 |
| From: | Lund A NRC/NRR/ADRO/DLR |
| To: | Perry R State of SC, Dept of Natural Resources |
| Leous, JP, DLR/REBB 301-415-2864 | |
| References | |
| Download: ML080810005 (5) | |
Text
April 9, 2008 Mr. Robert Perry South Carolina Department of Natural Resources Office of Environmental Programs 1000 Assembly Street Room 310A, PO Box 167 Columbia, SC 29202
SUBJECT:
VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION REVIEW
Dear Mr. Perry:
The U.S. Nuclear Regulatory Commission (NRC) staff is reviewing an application to renew the operating license for Vogtle Electric Generating Plant, Units 1 and 2 (VEGP), which is located in Burke County, Georgia. VEGP is operated by Southern Nuclear Operating Company, Inc.
(SNC). As part of its review of the proposed action, the NRC staff has prepared a site-specific Supplemental Environmental Impact Statement (SEIS) to its AGeneric Environmental Impact Statement for License Renewal of Nuclear Plants@ (GEIS), NUREG-1437. The SEIS includes analyses of relevant environmental issues pertaining to extended operation and refurbishment activities associated with license renewal. In accordance with the Fisheries and Wildlife Coordination Act, a copy of the draft supplement is enclosed. Pursuant to 36 CFR 800.8(c), we are requesting your comments on the draft supplement and on our preliminary conclusions.
The NRC staff determined that the area of potential effect for a license renewal action is the area at the power plant site and its immediate environs that may be affected by post-license renewal land disturbing operation or projected refurbishment activities associated with the proposed action. Please note, there are no projected refurbishment activities associated with license renewal. In the context of the National Environmental Policy Act of 1969, under which the draft environmental impact statement was prepared, the NRC staff=s preliminary determination is that the impact of license renewal on examined resources is small.
Please note that the period for public comment expires on July 17, 2008. If your office requires additional time, or if there are any other questions regarding this correspondence, please have your representative contact the Environmental Project Manager, Mr. J.P. Leous, at 301-415-2864 or by e-mail at justin.leous@nrc.gov.
Sincerely,
/RA Donnie Ashley for/
Louise Lund, Branch Chief Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-424, 50-425
Enclosures:
As stated
cc w/encl: See next page
April 9, 2008 Mr. Robert Perry South Carolina Department of Natural Resources Office of Environmental Programs 1000 Assembly Street Room 310A, PO Box 167 Columbia, SC 29202
SUBJECT:
VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION REVIEW
Dear Mr. Perry:
The U.S. Nuclear Regulatory Commission (NRC) staff is reviewing an application to renew the operating license for Vogtle Electric Generating Plant, Units 1 and 2 (VEGP), which is located in Burke County, Georgia. VEGP is operated by Southern Nuclear Operating Company, Inc.
(SNC). As part of its review of the proposed action, the NRC staff has prepared a site-specific Supplemental Environmental Impact Statement (SEIS) to its AGeneric Environmental Impact Statement for License Renewal of Nuclear Plants@ (GEIS), NUREG-1437. The SEIS includes analyses of relevant environmental issues pertaining to extended operation and refurbishment activities associated with license renewal. In accordance with the Fisheries and Wildlife Coordination Act, a copy of the draft supplement is enclosed. Pursuant to 36 CFR 800.8(c), we are requesting your comments on the draft supplement and on our preliminary conclusions.
The NRC staff determined that the area of potential effect for a license renewal action is the area at the power plant site and its immediate environs that may be affected by post-license renewal land disturbing operation or projected refurbishment activities associated with the proposed action. Please note, there are no projected refurbishment activities associated with license renewal. In the context of the National Environmental Policy Act of 1969, under which the draft environmental impact statement was prepared, the NRC staff=s preliminary determination is that the impact of license renewal on examined resources is small.
Please note that the period for public comment expires on July 17, 2008. If your office requires additional time, or if there are any other questions regarding this correspondence, please have your representative contact the Environmental Project Manager, Mr. J.P. Leous, at 301-415-2864 or by e-mail at justin.leous@nrc.gov.
Sincerely,
/RA Donnie Ashley for/
Louise Lund, Branch Chief Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-424, 50-425
Enclosures:
As stated cc w/encl: See next page DISTRIBUTION: See next page ADAMS Accession Number: ML080810005 OFFICE LA:DLR PM:DLR:RPB1 DLR:RPB1 OGC BC:DLR:RPB1 NAME SFigueroa JPLeous SHernandez LSubin LLund (DAshley for)
DATE 04/9/08 03/21/08 03/24/08 04/1/08 04/9/08
OFFICIAL RECORD COPY
Letter to R. Perry from L. Lund, dated April 9, 2008 DISTRIBUTION:
SUBJECT:
VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION REVIEW HARD COPY:
DLR R/F E-MAIL:
S. Lee R. Franovich L. Lund E. Benner J. Leous S. Hernandez Bobbie.hurley@earthtech.com D. Ashley S. Lingam G. McCoy S. Shaeffer RidsOGCMailRoom DLR/REBB DLR/REBA R. Hannah
Vogtle Electric Generating Plant, Units 1 and 2 cc:
Mr. Tom E. Tynan Vice President - Vogtle Vogtle Electric Generating Plant 7821 River Road Waynesboro, GA 30830 Mr. N. J. Stringfellow Manager, Licensing Southern Nuclear Operating Company, Inc.
P.O. Box 1295 Birmingham, AL 35201-1295 Mr. Jeffrey T. Gasser Executive Vice President Southern Nuclear Operating Company, Inc.
P.O. Box 1295 Birmingham, AL 35201-1295 Mr. Steven M. Jackson Senior Engineer - Power Supply Municipal Electric Authority of Georgia 1470 Riveredge Parkway, NW Atlanta, GA 30328-4684 Mr. Reece McAlister Executive Secretary Georgia Public Service Commission 244 Washington Street, SW Atlanta, GA 30334 Mr. Harold Reheis, Director Department of Natural Resources 205 Butler Street, SE, Suite 1252 Atlanta, GA 30334 Attorney General Law Department 132 Judicial Building Atlanta, GA 30334 Mr. Laurence Bergen Oglethorpe Power Corporation 2100 East Exchange Place P.O. Box 1349 Tucker, GA 30085-1349 Arthur H. Domby, Esquire Troutman Sanders Nations Bank Plaza 600 Peachtree Street, NE Suite 5200 Atlanta, GA 30308-2216 Resident Inspector Vogtle Plant 8805 River Road Waynesboro, GA 30830 Office of the County Commissioner Burke County Commission Waynesboro, GA 30830 Mr. Stanford M. Blanton, Esq.
Balch & Bingham, LLP P.O. Box 306 Birmingham, AL 35201 Ms. Monica M. Caston Vice President and General Counsel Southern Nuclear Operating Company, Inc.
40 Inverness Center Parkway P.O. Box 1295 Birmingham, AL 35201-1295 Chalmer R. Myer Southern Nuclear Operating Company, Inc.
40 Inverness Center Parkway P.O. Box 1295 Birmingham, AL 35201-1295