Response to NRC Request Regarding Modification of the Core Shroud Stabilizer Assemblies
ML080320304
Person / Time
Site: Hatch Southern Nuclear icon.png
Issue date: 01/31/2008
From: David Jones
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
nl-08-0150
Download: ML080320304 (2)


Text

David H. Jones Southern Nuclear Vice President Operating Company, Inc.

Engineering 40 Inverness Center Parkway Birmingham. Alabama 35242 Tel 205.992.5984 Fax 205.992.0341 SOUTHERNA COMPANY January 31,2008 Energy to Serve }Our'WorM'"

Docket No.:

50-321 NL-08-0150 U. S. Nuclear RegUlatory Commission ATrN: Document Control Desk Washington, D. C. 20555-0001 Edwin I. Hatch Nuclear Plant Response to NRC Request Regarding Modification of the Core Shroud Stabilizer Assemblies Ladies and Gentlemen:

By letter dated August 14, 2007 pursuant to 10 CFR 50.55a(a)(3)(i), Southern Nuclear Operating Company (SNC) requested NRC approval of a proposed modification to each of the four core shroud stabilizer assemblies. During the upcoming 2008 Refueling Outage (1 RF023), SNC proposes to replace the Hatch Unit 1 stabilizer assembly upper supports and tie rod top nuts with an improved design. By letter dated November 29, 2007 the NRC requested additional information regarding this submittal. By letter dated December 18, 2007 SNC provided responses to these questions. Per telephone conversation on January 29,2008 the NRC requested additional information. The SNC responses were provided in a letter dated January 30, 2008. Per telephone conversation on January 31, 2008 the NRC requested the inclusion of the proposed augmented inspection with the alternative request as described below.

The core shroud stabilizers are not included under the ASME Code Section XI definition for repair or replacement. As such, the design details of the proposed modification and the proposed augmented inspection requirements are being submitted to the NRC for review and approval as an alternative repair pursuant to 10 CFR 50.55a(a)(3)(i). The original submittal, dated August 14, 2007 contains the basis for concluding that the design modification provides an acceptable level of quality and safety. The details of the proposed augmented inspection requirements are described in Enclosure 2 of the SNC letter dated January 30, 2008 and supplement the inspection requirements described in Enclosure 1, Section 7.2 of the August 14, 2007 submittal.

U. S. Nuclear Regulatory Commission NL-08-0150 Page 2 This letter contains no NRC commitments. If you have any questions, please advise.

DHJ/MNW/daj cc: Southern Nuclear Operating Company Mr. J. T. Gasser, Executive Vice President Mr. D. R. Madison, Vice President - Hatch RTYPE: CHA02.004 U. S. Nuclear Regulatory Commission Mr. V. M. McCree, Acting Regional Administrator Mr. R. E. Martin, NRR Project Manager - Hatch Mr. J. A. Hickey, Senior Resident Inspector - Hatch