Letter Sequence Other |
|---|
|
|
MONTHYEARML0618607302006-07-0505 July 2006 Proposed Technical Specifications Change Revision of Main Control Room and Emergency Switchgear Room Air Conditioning System Requirements Project stage: Request ML0706505242007-02-26026 February 2007 Proposed Technical Specifications Change Temporary 45-Day and 14-Day Allowed Outage Times to Replace Main Control Room and Emergency Switchgear Room Air Conditioning System Chilled Water Piping Project stage: Request ML0709600372007-04-0505 April 2007 Proposed Technical Specifications Change Re Temporary 45-Day and 14-Day Allowed Outage Times to Replace Main Control Room and Emergency Switchgear Room Air Conditioning System Chilled Water Piping Project stage: Request ML0711700902007-05-0303 May 2007 Request for Additional Information Regarding the Proposal to Revise Technical Specifications for Temporary 45-Day and 14-Day Allowed Outage Times (TAC Nos. MD46222 and MD4623) Project stage: RAI ML0713503562007-05-14014 May 2007 License Renewal Commitment, Pressurizer Surge Line Weld Inspection Plan Summary Project stage: Other ML0715502022007-05-31031 May 2007 Proposed Technical Specifications Change, Temporary 45-Day and 14-Day Allowed Outage Times to Replace Main Control Room and Emergency Switchgear Room Air Conditioning System Chilled Water Piping, Response to NRC RAI Project stage: Request ML0714902312007-05-31031 May 2007 Request for Additional Information Regarding the Proposal to Revise Technical Specification for Temporary 45-Day and 14-Day Allowed Outage Times to Replace Chilled Water Piping...(Tac Nos. MD4622 and MD4623) Project stage: RAI ML0717602122007-06-0505 June 2007 MCR &Esgr Chilled Water Piping Replacement Project stage: Other ML0718403872007-07-0303 July 2007 MCR and ESGR Chilled Water Piping Replacement (Risk Assessment RAI) Project stage: RAI ML0719401282007-07-12012 July 2007 MCR and ESGR Chilled Water A/C System Piping Replacement Project stage: Other ML0719303632007-07-12012 July 2007 MCR and ESGR e-mail Surry RAI Response for La Project stage: RAI ML0719701832007-07-13013 July 2007 Proposed Technical Specification Change, Temporary 45-Day and 14-Day Allowed Outage Times to Replace Main Control Room and Emergency Switchgear Room Air Conditioning System Chilled Water Piping Additional Information Backup Cooling Project stage: Other ML0720600222007-07-20020 July 2007 Temporary 45-Day and 14-Day Allowed Outage Times to Replace Main Control Room and Emergency Switchgear Room Air Conditioning System Chilled Water Piping, Response to Request for Additional Information Project stage: Response to RAI ML0726811712007-09-25025 September 2007 Proposed Technical Specifications Change Supplement Re Operable Definition Modification for Air Handling Units While in Temporary 45-Day Allowed Outage Times Project stage: Request ML0733212712007-11-28028 November 2007 Proposed Additional Technical Specifications Change, Operable Definition Modification for Air Handling Units While in Temporary 45-day Allowed Outage Times to Perform Required Surveillances Project stage: Request ML0801505442008-01-14014 January 2008 Revisions to Proposed Technical Specifications Changes, Temporary 45-day and 14-day Allowed Outage Times to Replace MCR and ESGR Air Conditioning System Chilled Water Piping and Operable Definition Modification to Perform Project stage: Request ML0802401202008-01-23023 January 2008 Tech Spec Pages for Amendments 258 and 257 Regarding Replacement of Main Control Room and Emergency Switchgear Room Air-Conditioning System Chilled Water Piping Project stage: Other ML0734802872008-01-23023 January 2008 Issuance of Amendments 258 and 257 Regarding Replacement of Main Control Room and Emergency Switchgear Room Air-Conditioning System Chilled Water Piping Project stage: Approval 2007-06-05
[Table View] |
Similar Documents at Surry |
|---|
|
Text
From:
Siva Lingam To:
gary.D.Miller@Dom.com Date:
6/5/2007 10:04:51 AM
Subject:
Surry 1 & 2 - MCR and ESGR Chilled Water Piping Replacement We have reviewed the Surry RAI response you provided via letter dated May 31, 2007 (Serial No. 07-0381), and need two additional pieces of information not provided.
- 1. In response to RAI #1, the licensee discussed the assumed equipment impacts to a loss of switchgear room cooling as failure of various electrical busses. However, the licensee did not identify the assumed impacts to a loss of control room cooling. The licensee stated that no alternate cooling was modeled (item D), so if control room cooling from the chillers is lost, does the PRA model simply assume core damage? If not, what is modeled as the plant impact?
- 2. In response to RAI #1, the licensee identified the acceptance criteria for chilled water and room coolers. However, it is not clear if the PRA model includes only the five chillers in the scope of the TS, or if the nonsafety chillers are also considered. The licensee stated that no alternate cooling was modeled (item D), which would imply that other chillers or cooling methods are not credited. A clarification as to the specific scope of the chilled water and MCR/ESGR cooling system PRA models, both for initiating events and mitigation, is requested.
Siva P. Lingam Project Manager (NRR/DORL/LPL2-1)
North Anna and Surry Nuclear Stations Location: O8-D5 Mail Stop: O8-G9 Telephone: 301-415-1564 Fax: 301-415-1222 E-mail address: spl@nrc.gov CC:
Andrew Howe Mail Envelope Properties (46656D83.481 : 13 : 35786)
Subject:
Surry 1 & 2 - MCR and ESGR Chilled Water Piping Replacement Creation Date 6/5/2007 10:04:51 AM From:
Siva Lingam Created By:
SPL@nrc.gov Recipients Action Date & Time Dom.com Transferred 6/5/2007 10:05:25 AM gary.D.Miller (gary.D.Miller@Dom.com) nrc.gov OWGWPO04.HQGWDO01 Delivered 6/5/2007 10:04:58 AM AJH1 CC (Andrew Howe)
Opened 6/5/2007 10:21:33 AM Post Office Delivered Route Dom.com
OWGWPO04.HQGWDO01 6/5/2007 10:04:58 AM nrc.gov Files Size Date & Time MESSAGE 2035 6/5/2007 10:04:51 AM Options Auto Delete:
No Expiration Date:
None Notify Recipients:
Yes Priority:
Standard ReplyRequested:
No Return Notification:
None Concealed
Subject:
No Security:
Standard To Be Delivered:
Immediate Status Tracking:
Delivered & Opened