MONTHYEARML20151K0611997-07-28028 July 1997 Responds to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions. Listed Generic Issues Addressed Project stage: Other ML20211J0721997-09-30030 September 1997 Submits Response to NRC GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions Project stage: Other ML20199B1251997-11-0505 November 1997 Discusses Info Submitted Re 120-day Response to GL 96-06, Assurance of Equipment Operabiltiy & Containment Integrity During DBA Conditions, Per Implementation of Mods.If Commitments Revised,Revised Response Should Be Submitted Project stage: Other ML20216J0921998-03-18018 March 1998 Ack Receipt of 970128,0228,0728 & 0930 Submittals Re GL 96-06, Assurance of Equipment Operability & Ci During DBA Conditions. Addl Info Re Applicable Design Criteria for Piping & Valve & Drawing of Piping Between Valves Requested Project stage: Other ML20216G9451998-04-15015 April 1998 Requests Addl Info Pertaining to GL 96-06 Dtd 980930,which Included Request for Licensees to Evaluate Cooling Water Systems That Serve Containment Air Coolers to Assure Not Vulnerable to Waterhammer & two-phase Flow Conditions Project stage: Other ML20236U5011998-07-23023 July 1998 Special Rept:On 980624,Unit 1 Site Damaged by Tornado & High Winds.Alert Declared by DBNPS Staff,Dbnps Emergency Response Facilities Activiated & Special Insp Team Deployed to Site by Nrc,As Result of Event Project stage: Other ML20238F7971998-08-28028 August 1998 Submits Response to NRC Request for Addl Info Pertaining to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions Project stage: Request ML20205K5641999-04-0707 April 1999 Forwards Response to NRC 980415 RAI Re GL 96-06, Assurance of Equipment Operability & Ci During Design-Basis Accident Conditions. Rept FAI/98-126, Waterhammer Phenomena in Containment Air Cooler Swss, Encl Project stage: Other ML0331404022003-11-20020 November 2003 Letter, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions Project stage: Other ML0400200522003-12-30030 December 2003 Response to RAI Concerning Generic Letter 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions Project stage: Response to RAI ML0505406132005-03-0303 March 2005 Generic Letter 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions (TAC No. M96803) Project stage: Other ML0511002912005-04-15015 April 2005 Response to NRC Request for Additional Information Concerning GL-96-006, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions Project stage: Response to RAI ML0620901032006-07-25025 July 2006 Response to NRC Request for Additional Information Concerning Generic Letter (GL) 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions Project stage: Response to RAI ML0620604832006-07-25025 July 2006 Dale L. Miller/Steven P. Moffitt - NRC Staff'S Notice of Deposition (John Messina) Project stage: Request M061025, COMSECY-07-0018 - Cost Estimate for Davis-Besse Reactor Vessel Head Degradation Display2007-04-20020 April 2007 COMSECY-07-0018 - Cost Estimate for Davis-Besse Reactor Vessel Head Degradation Display Project stage: Request ML0705105802007-04-20020 April 2007 COMSECY-07-0018 - Cost Estimate for Davis-Besse Reactor Vessel Head Degradation Display Project stage: Request ML0711500772007-04-20020 April 2007 Supplemental Information Concerning Generic Letter 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions Project stage: Supplement ML0713604802007-05-31031 May 2007 NRC Receipt of Davis-Besse, Unit 1 Response to GL 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions. (TAC M96803) Project stage: Other 1999-04-07
[Table View] |
Text
April 20, 2007 MEMORANDUM TO: Chairman Klein Commissioner McGaffigan Commissioner Merrifield Commissioner Jaczko Commissioner Lyons FROM: Luis A. Reyes /RA/
Executive Director for Operations
SUBJECT:
COST ESTIMATE FOR DAVIS-BESSE REACTOR VESSEL HEAD DEGRADATION DISPLAY By way of this memorandum, I am informing the Commission of the cost of procuring a model of the Davis-Besse reactor pressure vessel head degradation for display in the NRC headquarters lobby, as requested in staff requirements memorandum, Briefing on Institutionalization and Integration of Agencys Lessons Learned, dated November 21, 2006 (M061025A). The Office of Nuclear Regulatory Research has determined that this model would cost approximately $35K.
The concept includes a display similar to one used in trade shows or museums consisting of a model on a display table that could be viewed and touched from all sides. The display would require a space of approximately 8 ft. by 8 ft. and would cost approximately $35K. All information conveyed by the final display would be from NRC sources previously approved for public release.
The staff will engage a graphics design firm to provide the final design and fabricate the display, and will engage the Office of Administration to determine space availability.
An estimated $35K of FY 2007 funds for this display will be taken from Activity 11AACa, Environmentally-Assisted Degradation of Reactor Pressure Boundary Components and Vessel Internals. The impact of this reprogramming would be to delay testing on irradiated assisted stress corrosion cracking for about one month. Office of Nuclear Reactor Regulation review of licensees aging management programs for reactor internals under the license renewal program will not be impacted by this delay. This delay has been coordinated with the Office of Nuclear Reactor Regulation, Division of Component Integrity.
CONTACT: Eric M. Focht, RES/DFERR 301-415-5222
The Commissioners The Offices of the General Counsel, the Chief Financial Officer, and Administration have reviewed this memorandum and have no objections.
cc: SECY OGC OCA OPA CFO
The Commissioners The Offices of the General Counsel, the Chief Financial Officer, and Administration have reviewed this memorandum and have no objections.
cc: SECY OGC OCA OPA CFO DISTRIBUTION: WITS# 200600478/RES# 2007017 DFERR, r/f ME, r/f CIB M. Evans M. Mayfield M. Cunningham J. Uhle B. Hardies E. Focht M. Virgillo OAR in ADAMS? (Y or N) Y ADAMS ACCESSION NO: ML070510580 TEMPLATE NO.: EDO-004 Publicly Available? (Y or N) N DATE OF RELEASE TO PUBLIC: N/A SENSITIVE? N To receive a copy of this document, indicate in the box: C = Copy without attachment/enclosure E = Copy with attachment/enclosure N = No copy (Parallel Concurrence)
OFFICE RES/DFERR/ME/CIB RES/DFERR/ME/CIB RES/DFERR/ME RES/DFERR NAME E. Focht R. Hardies J. Uhle M. Cunningham DATE 02/22/07 02/26/07 02/26/07 02/28/07 OFFICE OGC OCFO ADM DD:RES NAME K. Cyr /RA/ J. Funches /RA/ T. Hagan /RA/ J. Wiggins e-mail M. Itzkowitz for e-mail L. Barnett for e-mail M. Gray for DATE 03/07/07 03/13/07 03/12/07 03/13/07 OFFICE D:RES EDO NAME B. Sheron /RA/ L. Reyes J. Wiggins for DATE 03/13/07 04/20/07 OFFICIAL RECORD COPY