MONTHYEARML0516603262005-06-10010 June 2005 Response to First Revised Order EA-03-009 and Bulletin 2003-02 Project stage: Other ML0519501232005-07-0707 July 2005 License Amendment Request Regarding Extended Power Uprate Project stage: Request ML0523101552005-08-15015 August 2005 Supplemental Information Related to Small Break (SB) Loss of Coolant Accident (LOCA) Analysis and Post-LOCA Boric Acid Precipitation Analysis Project stage: Request ML0523104332005-08-24024 August 2005 Extended Power Uprate Acceptance Review Results Project stage: Acceptance Review ML0524500902005-09-0202 September 2005 Forthcoming Meeting with R.E. Ginna Nuclear Power Plant, LLC (Ginna, Llc), Regarding Extended Power Uprate Amendment Application Project stage: Meeting ML0529208222005-09-15015 September 2005 Presentation for 09/15/2005 Meeting with R. E. Ginna SBLOCA EPU Results Summary Project stage: Meeting ML0524504522005-09-15015 September 2005 Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for a Hearing - Extended Power Uprate - R.E. Ginna Nuclear Power Plant Project stage: Other ML0525502722005-09-30030 September 2005 Westinghouse Electric Company, Request for Withholding Information from Public Disclosure for R. E. Ginna Nuclear Power Plant Project stage: Withholding Request Acceptance ML0528002232005-09-30030 September 2005 R. E. Ginna, Large Transient Tests Associated with License Amendment Request Regarding Extended Power Uprate Project stage: Request ML0529205102005-10-24024 October 2005 Summary of Meeting with R.E. Ginna Extended Power Uprate Application Project stage: Meeting ML0528501372005-10-25025 October 2005 RAI, Request for Additional Information Extended Power Uprate License Amendment Project stage: RAI ML0529300412005-10-25025 October 2005 Request for Additional Information Related to the Proposed Extended Power Uprate for Ginna Nuclear Power Plant Project stage: RAI ML0530703792005-11-0303 November 2005 Request for Additional Information Extended Power Uprate License Amendment Project stage: RAI ML0530705682005-11-0303 November 2005 Forthcoming Meeting with R.E. Ginna Nuclear Power Plant, LLC (Ginna Llc), Regarding Extended Power Uprate Amendment Application Project stage: Meeting ML0531404202005-11-10010 November 2005 Supplemental Request for Additional Information Extended Power Uprate License Amendment Project stage: RAI ML0536201882005-11-17017 November 2005 Meeting with R. E. Ginna Nuclear Power Plant, LLC, Regarding Extended Power Uprate Amendment Application Project stage: Meeting ML0534803882005-12-0606 December 2005 Response to Requests for Additional Information Regarding Topics Described by Letter Dated October 25. 2005 Project stage: Response to RAI ML0536101852005-12-19019 December 2005 Response to Requests for Additional Information Re Increase of Maximum Steady-State Thermal Power Level Project stage: Response to RAI ML0536400802005-12-22022 December 2005 Response to Request for Additional Information Regarding Topics Described by Letter Dated November 10, 2005 Project stage: Response to RAI ML0535602452005-12-23023 December 2005 Summary of November 17, 2005, Meeting with R. E. Ginna Nuclear Power Plant, LLC, Regarding Extended Power Uprate Application Project stage: Meeting ML0601802622006-01-11011 January 2006 Supplemental Response to Requests for Additional Information Regarding Topics Described by Letters Dated August 24, 2005 and October 28, 2005 Project stage: Supplement ML0609604162006-01-25025 January 2006 R. E. Ginna - Response to Requests for Additional Information Regarding Topics Described in Meeting Minutes Project stage: Response to RAI ML0605403492006-02-16016 February 2006 Response to Requests for Additional Information Regarding Topics Discussed on Conference Calls Project stage: Response to RAI ML0606806582006-03-0909 March 2006 Forthcoming Meeting with R. E. Ginna Nuclear Power Plant, LLC (Ginna Llc), Regarding Extended Power Uprate Amendment Application Project stage: Meeting ML0607901132006-03-20020 March 2006 Cancellation - Forthcoming Meeting with R.E. Ginna Nuclear Power Plant, LLC Regarding Extended Power Uprate Amendment Application Project stage: Meeting ML0609403122006-03-24024 March 2006 R. E. Ginna - Response to BOP Systems Questions Discussed on March 2, 2006 Conference Call Project stage: Request MN 06-019, NRC Slides for Annual Assessment Public Meeting with R. E. Ginna Nuclear Power Plant, LLC to Discuss CY2005 Performance2006-04-0404 April 2006 NRC Slides for Annual Assessment Public Meeting with R. E. Ginna Nuclear Power Plant, LLC to Discuss CY2005 Performance Project stage: Request ML0609000892006-04-0404 April 2006 Public Meeting Notice for Ginna Station Annual Assessment to Discuss CY2005 Performance Project stage: Request ML0609300252006-04-0404 April 2006 Notice of Meeting with R. E. Ginna Nuclear Power Plant, LLC (Ginna Llc), Regarding Extended Power Uprated Amendment Application Project stage: Meeting ML0608003152006-04-0606 April 2006 R. E. Ginna Nuclear Power Plant - Draft Environmental Assessment and Finding of No Significant Impact Related to Proposed Extended Power Uprate Project stage: Draft Other ML0608003472006-04-0606 April 2006 R. E. Ginna Nuclear Power Plant Draft Environmental Assessment and Finding of No Significant Impact Related to the Proposed License Amendment to Increase to Maximum Reactor Power Level Project stage: Draft Other ML0613503752006-05-0909 May 2006 R. E. Ginna, Response to Requests for Additional Information Regarding Topics Discussed on Conference Calls for Extended Power Uprate (EPU) Project stage: Response to RAI ML0613706272006-05-12012 May 2006 Comment (1) of Kimberly A. Merchant on Draft Environmental Assessment and Findings of No Significant Impact Related to Proposed Extended Power Uprate Project stage: Draft Other ML0613601522006-05-12012 May 2006 Summary of May 9, 2006, Annual Assessment Meeting with Constellation Energy, R. E. Ginna Nuclear Power Plant, LLC Project stage: Request ML0614503812006-05-19019 May 2006 R. E. Ginna Final Response to Requests for Additional Information Regarding Topics Discussed on Conference Calls for Extended Power Uprate (EPU) Project stage: Response to RAI ML0613204402006-06-26026 June 2006 R. E. Ginna Nuclear Power Plant - Final Environmental Assessment and Finding of No Significant Impact Related to Proposed Extended Power Uprate Project stage: Other ML0616002502006-06-26026 June 2006 Final Environmental Assessment and Finding of No Significant Impact Related to Proposed Extended Power Uprate Project stage: Other ML0619205922006-07-11011 July 2006 Amendment 97, Renewed Facility Operating License Page No. 3 Regarding 16.8 Percent Power Uprate Project stage: Other ML0619205942006-07-11011 July 2006 R. E. Ginna, Tech Spec Pages for Amendment 97 Regarding 16.8 Percent Power Uprate Project stage: Other ML0613801032006-07-11011 July 2006 R. E. Ginna, License Amendment, 16.8 Percent Power Uprate Project stage: Other ML0613802492006-07-11011 July 2006 Table of Contents, Safety Evaluation Related to Extended Power Uprate at R. E. Ginna Nuclear Power Plant Project stage: Approval ML0629101322006-10-12012 October 2006 License Amendment Request: Spent Fuel Pool Storage Capacity Project stage: Request 2005-09-02
[Table View] |
Similar Documents at Ginna |
|---|
|
Text
November 3, 2005 MEMORANDUM TO:
Richard J. Laufer, Chief Plant Licensing Branch A Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (NRR)
FROM:
Patrick D. Milano, Senior Project Manager /RA/
Plant Licensing Branch A Division of Operating Reactor Licensing, NRR
SUBJECT:
FORTHCOMING MEETING WITH R.E. GINNA NUCLEAR POWER PLANT, LLC (GINNA LLC), REGARDING EXTENDED POWER UPRATE AMENDMENT APPLICATION (TAC NO. MC7382)
DATE & TIME:
Thursday, November 17, 2005 8:30 a.m. - 4:00 p.m.
LOCATION:
U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike, Room O-8 B6 Rockville, Maryland PURPOSE:
Working-level meeting to discuss the plans and status for the Ginna LLC response to the Nuclear Regulatory Commission (NRC) staffs requests for additional information (RAIs) regarding loss-of-coolant accident analyses, long-term cooling, civil and structural issues, and large transient testing supporting the power uprate application dated July 7, 2005 (Agencywide Documents Access and Management System (ADAMS), Accession No. ML051950123). The discussion will center, in part, on issues presented in the NRC staffs RAIs dated October 25, October 28, and November 3, 2005 (ADAMS Nos. ML052850137, ML052930431, and ML053070379). The meeting agenda is enclosed.
CATEGORY 1*:
This is a Category 1 Meeting: The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.
Certain portions of this meeting will be closed to the public because the staff has determined that the information is proprietary in nature.
MEETING CONTACTS: Patrick Milano, NRR Richard Guzman, NRR 301-415-1457 301-415-1030 pdm@nrc.gov rvg@nrc.gov
- Commission's Policy Statement on Enhancing Public Participation in NRC Meetings,"
(67 FR 36920), May 28, 2002
R. Laufer PARTICIPANTS:
Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR).
NRC LICENSEE/CONTRACTOR P. Milano, NRR G. Wrobel, Ginna LLC R. Guzman, NRR D. Wilson, Ginna LLC S. Miranda, NRR M. Finley, Ginna LLC L. Ward, NRR D. Dominicis, Westinghouse C-I Wu, NRR et al.
P. Prescott, NRR et al.
Docket No. 50-244
Enclosure:
Agenda cc w/encl: See next page
ML053070568 OFFICE LPLA:PM LPLA:LA LPLA:BC NAME PMilano SLittle RLaufer DATE 11/03/05 11/03/05 11/03/05
Enclosure MEETING AGENDA WORKING-LEVEL MEETING TO DISCUSS INFORMATION AND OTHER SUPPORTING ANALYSES REGARDING APPLICATION FOR EXTENDED POWER UPRATE R.E. GINNA NUCLEAR POWER PLANT, LLC R.E. GINNA NUCLEAR POWER PLANT DOCKET NO. 50-244 Schedule Discussion Topics 8:30 - 8:45 a.m.
Introductory Remarks/Introductions 8:45 - 9:30 a.m.
Overview of status of the plans and schedule to respond to the staffs questions regarding the Ginna loss-of-coolant accident (LOCA), long-term cooling, and boron precipitation analyses 9:30 - 10:30 a.m.
Specific LOCA Analysis Items and Response to RAI Questions 10:30 - 11:45 a.m.
Other Supporting Analysis Items and RAI Questions 11:45 a.m. - 12:30 p.m.
Lunch Break 12:30 - 12:45 p.m.
Overview of Status and Plans regarding Testing and Civil and Structural Items 12:45 - 2:00 p.m.
Civil and Structural RAI Questions 2:00 - 3:30 p.m.
Large Transient Testing RAI Questions 3:30 - 4:00 p.m.
Additional Questions/Comments and Summary
R.E. Ginna Nuclear Power Plant cc:
Mr. Michael J. Wallace President R.E. Ginna Nuclear Power Plant, LLC c/o Constellation Energy 750 East Pratt Street Baltimore, MD 21202 Mrs. Mary G. Korsnick Vice President R.E. Ginna Nuclear Power Plant R. E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, NY 14519 Mr. John M. Heffley Senior Vice President and Chief Nuclear Officer Constellation Generation Group 1997 Annapolis Exchange Parkway Suite 500 Annapolis, MD 21401 Kenneth Kolaczyk, Sr. Resident Inspector R.E. Ginna Nuclear Power Plant U.S. Nuclear Regulatory Commission 1503 Lake Road Ontario, NY 14519 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Peter R. Smith, President New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Carey W. Fleming, Esquire Senior Counsel - Nuclear Generation Constellation Generation Group, LLC 750 East Pratt Street, 17th Floor Baltimore, MD 21202 Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, NY 10271 Ms. Thelma Wideman, Director Wayne County Emergency Management Office Wayne County Emergency Operations Center 7336 Route 31 Lyons, NY 14489 Ms. Mary Louise Meisenzahl Administrator, Monroe County Office of Emergency Preparedness 1190 Scottsville Road, Suite 200 Rochester, NY 14624 Mr. Paul Eddy New York State Department of Public Service 3 Empire State Plaza, 10th Floor Albany, NY 12223