Progress Energy Input to NFPA 805 Pilot Planning Meeting NRC Region II Atlanta, GA August 11, 2005
Page 2 Progress Energy Input to NFPA 805 Pilot Planning Meeting Progress Energy (PE) Attendees:
Z Paul Gaffney, Chief Electrical/I&C Engineer Z Jeff Ertman, NFPA 805 Transition Project Manager Z John Caves, PSA Supervisor Z Tony Maness, HNP Site NFPA 805 Project Lead Z Dave Corlett, HNP Licensing Supervisor Z Ken Heffner, Lead Licensing Engineer
Page 3 NFPA 805 Pilot Planning Meeting Progress Energy Pilot & NFPA 805 Goals O Focus on Nuclear Safety O Restore Fire Protection Compliance O Clean up licensing basis
Page 4 NFPA 805 Pilot Planning Meeting Progress Energy Objectives O Communicate PE transition plans O Identify key pilot observations O Identify milestones O Identify resources for the observation visits such as location, personnel needed, materials needed, and duration O Handling of deficiencies
Page 5 NFPA 805 Pilot Planning Meeting Overview PE Schedule 2005 2011 2006 2007 2008 2009 2010 2012 Harris Triennial Harris Triennial 3 Plant Triennials 3 Plant Triennials Start Transition NRC Pilot Schedule Meeting Atlanta, August 11th Note: NFPA Fundamental Elements, Radioactive Release, Non-Power Operations and Nuclear Safety Analyses (Area Transition) are developed as an iterative process with final iteration in the Transition Report and LAR.
Submit LAR Receive RAIs FE & RR Harris Receive LA Complete SSA Area Transition Non-Power Ops Upgrade PRA Prepare LAR Transition Report Done Implement Amendment Robinson Submit LAR Receive RAIs FE & RR Receive LA Complete SSA Area Transition Non-Power Ops Upgrade PRA Prepare LAR Transition Report Done Implement Amendment Crystal River Submit LAR Receive RAIs FE & RR Receive LA Complete SSA Area Transition Upgrade PRA Prepare LAR Transition Report Done Implement Amendment Non-Power Ops Submit LAR FE & RR Complete SSA Non-Power Ops Upgrade PRA Prepare LAR Transition Report Implement Amendment Brunswick Area Transition
Page 6 NFPA 805 Pilot Planning Meeting PE Status SSA Validation Schedule
Page 7 NFPA 805 Pilot Planning Meeting Key Pilot Interactions O NSPA (SSA) Transition - Comparison to NEI 00-01 Z Multiple circuit failures Z Recovery Action evaluations T-H & HRA O Chapter 3 Transition O Internal Events PRA / Fire PRA O Fire Modeling O Radioactive release during firefighting activities O Non-power operations O RI change evaluation process O Fire Protection Performance Monitoring O CAP tracking of FP deficiencies for resolutions under NFPA 805 / Enforcement Discretion
Page 8 NFPA 805 Pilot Planning Meeting PE NFPA 805 Transition Project Approach O Through 2005 Z Detailed planning, procedure/process development, and team assembly Z NEI 00-01 comparison and finalize Fire NSPA criteria and methodology in late 2005 Z Fire PRA Gap review O Continue work HNP SSA Validation Z NRC Triennial Inspection Z Prioritize open SSA Validation issues O Scheduled to start PRA work and Chapter 3 Transition in early 1Q2006
Page 9
Page 10 NFPA 805 Pilot Planning Meeting PE NFPA 805 Transition Project Team
Page 11 NFPA 805 Pilot Planning Meeting O Break
Page 12 NFPA 805 Pilot Planning Meeting PE Transition Plan Overview O Guidance Documents Used Z NEI 04 Guidance for Implementing a Risk-Informed, Performance-Based Fire Protection Program under 10CFR50.48(c)
Z NEI 00-01, Guidance for Post-Fire Safe Shutdown Circuit Analysis Z NUREG/CR-6850, Fire PRA Methodology for Nuclear Power Facilities
Page 13 NFPA 805 Pilot Planning Meeting Project Plan - Overview Work Flow Project Initiation Nuclear Safety Performance Criteria, Complete SSA Validation, Fire Area Transition, Non-Power Operations, Fire PRA Input Develop Fire PRA, Develop Fire Induced Risk Model, Recovery Actions (HRA),
Multiple Spurious Operations Fundamental Program Elements Transition, Fire Related Radioactive Release Monitoring, Fire PRA Input Upgrade Internal Events PRA, Input SSA Equipment Scope Fire Protection Program Transition Existing PRA NFPA 805 Change Evaluations Performance Calculations - Fire Modeling, etc.
Risk Evaluations Transition Report LAR Program Implementation Project Plan Review Program Elements Detailed Project Instructions
Page 14 NFPA 805 Pilot Planning Meeting PE Transition Plan - Key Interactions O SSA and NSPA O Chapter 3 Transition O Internal Events PRA / Fire PRA O Fire Modeling O Non - Power Ops & Radioactive Release O Change process & NFPA 805 Implementation O Performance Monitoring O CAP tracking of FP deficiencies
Page 15 NFPA 805 Pilot Planning Meeting SSA and NSPA O Tasks and approximate timing:
Z 1.2 - Existing SSA / NEI 00-01 Methodology Comparison - November 2005 Z 4.1.7 - SSA Transient Analysis/Operation Considerations - April 2006 Z 4.2 - NSPA Fire Area-by-fire Area Transition sample results - July 2006 Z 4.5 - NSPA Recovery Actions - November 2006 O Discussion of resources
Page 16 NFPA 805 Pilot Planning Meeting Chapter 3 Transition O Tasks and approximate timing:
Z 2.1.1 - Non Fire Area specific elements -
March 2006 Z 2.1.2 - Fire Area specific FP elements -
January 2007 O Discussion of resources
Page 17 NFPA 805 Pilot Planning Meeting Internal Events PRA / Fire PRA O Tasks and approximate timing:
Z 1.3.2.4 - Fire PRA Gap review - November 2005 Z 6.2 - Internal Events PRA Gap Assessment - January 2006 Z 7.4 - Fire PRA Component Mapping - June 2006 Z 7.10 - Circuit Failure Mode Analysis - September 2006 Z 7.6 - Fire Induced PRA Model - February 2007 Z 7.12 - Human Reliability Analysis - June 2007 Z 7.13 - Fire Risk Quantification - September 2007 Z 7.14 - Uncertainty Analysis - November 2007 O Discussion of resources
Page 18 NFPA 805 Pilot Planning Meeting Fire Modeling O Tasks and approximate timing:
Z 4.1.8 - SSA Validation Recovery Action Feasibility - February 2006 Z 7.11 - Detailed Fire Modeling for Fire PRA -
September 2006 O Discussion of resources
Page 19 NFPA 805 Pilot Planning Meeting Non - Power Ops and Radioactive Release O Tasks and approximate timing:
Z 3.2.3 - Identify changes to Fire Brigade training - July 2006 Z 5.2.4 - Revision to site outage risk review process - October 2006 O Discussion of resources
Page 20 NFPA 805 Pilot Planning Meeting Change Process & Implementation O Tasks and approximate timing:
Z 1.3.2.8 - Change Process Procedure -
October 2005 Z 8.1.1 - Change Process Products - (TBD)
XFundamental Element Performance Based Evaluation (if any)
XBarrier (such as Heymc) Change Evaluation XRecovery Action Change Evaluation XSample of other unique type Change Evaluations Z 13.0 - Program Implementation O Discussion of resources
Page 21 NFPA 805 Pilot Planning Meeting Performance Monitoring, CAP Tracking O Tasks and approximate timing:
Z Task 9.2.6 - Establish Performance Monitoring Procedure and scope -
Z Review of CAP tracking of FP deficiencies during transition - October 2005 Z Other items??
O Discussion of resources
Page 22 NFPA 805 Pilot Planning Meeting Summarize Results O Conceptual Observation Schedule O Resources Identified