June 16, 2005 Mr. Mark E. Warner, Site Vice President c/o James M. Peschel Seabrook Station FPL Energy Seabrook, LLC PO Box 300 Seabrook, NH 03874

SUBJECT:

SEABROOK STATION, UNIT NO. 1 - RESPONSE TO GENERIC LETTER 2004-01, REQUIREMENTS FOR STEAM GENERATOR TUBE INSPECTIONS (TAC NO. MC4851)

Dear Mr. Warner:

On August 30, 2004, the Nuclear Regulatory Commission (NRC) issued Generic Letter (GL) 2004-01, Requirements For Steam Generator Tube Inspections. The purpose of GL 2004-01 was to obtain information that would enable the NRC staff to determine whether licensees steam generator (SG) tube inspection programs comply with the existing tube inspection requirements (the plant Technical Specifications in conjunction with Appendix B to Title 10 of the Code of Federal Regulations Part 50).

By letter dated October 29, 2004, FPL Energy Seabrook, LLC responded to GL 2004-01 for Seabrook Station, Unit No. 1 (SS). The NRC staffs review of your response to the GL did not identify any concerns with the inspection practices employed at SS. The staff, therefore, concludes that your SG tube inspection practices are in compliance with the existing tube inspection requirements.

If you have any questions regarding this matter, please contact me at (301) 415-1484.

Sincerely,

/RA/

Victor Nerses, Senior Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-443 cc: See next page

ML051640355 OFFICE PDI-2/PM PDI-2/LA PDI-2/SC NAME VNerses CRaynor DRoberts DATE 6/15/05 6/14/05 6/16/05 Seabrook Station, Unit No. 1 cc:

Mr. J. A. Stall Senior Vice President, Nuclear and Chief Nuclear Officer Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. Peter Brann Assistant Attorney General State House, Station #6 Augusta, ME 04333 Resident Inspector U.S. Nuclear Regulatory Commission Seabrook Nuclear Power Station P.O. Box 1149 Seabrook, NH 03874 Town of Exeter 10 Front Street Exeter, NH 03823 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Office of the Attorney General One Ashburton Place, 20th Floor Boston, MA 02108 Board of Selectmen Town of Amesbury Town Hall Amesbury, MA 01913 Ms. Deborah Bell Federal Emergency Management Agency Region I J.W. McCormack P.O. &

Courthouse Building, Room 401 Boston, MA 02109 Mr. Tom Crimmins Polestar Applied Technology One First Street, Suite 4 Los Altos, CA 94019 Mr. Stephen McGrail, Director ATTN: James Muckerheide Massachusetts Emergency Management Agency 400 Worcester Road Framingham, MA 01702-5399 Philip T. McLaughlin, Attorney General Steven M. Houran, Deputy Attorney General 33 Capitol Street Concord, NH 03301 Mr. Bruce Cheney, Director New Hampshire Office of Emergency Management State Office Park South 107 Pleasant Street Concord, NH 03301 Mr. Gene F. St. Pierre Station Director Seabrook Station FPL Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874 Mr. M. S. Ross, Managing Attorney Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. Rajiv S. Kundalkar Vice President - Nuclear Engineering Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 James M. Peschel Regulatory Programs Manager Seabrook Station FPL Energy Seabrook, LLC PO Box 300 Seabrook, NH 03874

Seabrook Station, Unit No. 1 cc:

David Moore Vice President, Nuclear Operations Support Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Marjan Mashhadi Senior Attorney Florida Power & Light Company 801 Pennsylvania Ave., NW Suite 220 Washington, DC 20004