RAI, Delta Protection Mururoa Single Use Supplied Air Suits (Tac No. MC6995, MC6996, MC6997, MC6998, MC6999, MC7000)
ML051570407
Person / Time
Site: Browns Ferry, Watts Bar, Sequoyah  Tennessee Valley Authority icon.png
Issue date: 06/20/2005
From: Pickett D
NRC/NRR/DLPM/LPD2
To: Singer K
Tennessee Valley Authority
Pickett D, NRR/DLPM, 415-1364
References
TAC MC6995, TAC MC6996, TAC MC6997, TAC MC6998, TAC MC6999, TAC MC7000
Download: ML051570407 (5)


Text

June 20, 2005 Mr. Karl W. Singer Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, Tennessee 37402-2801

SUBJECT:

BROWNS FERRY NUCLEAR PLANT, UNITS 1, 2, AND 3, SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2, AND WATTS BAR NUCLEAR PLANT, UNIT 1 - REQUEST FOR ADDITIONAL INFORMATION RELATED TO DELTA PROTECTION MURUROA SINGLE USE SUPPLIED AIR SUITS (TAC NOS.

MC6995, MC6996, MC6997, MC6998, MC6999, MC7000)

Dear Mr. Singer:

By letter dated May 13, 2005, the Tennessee Valley Authority requested approval to use Delta Protection Mururoa Single Use Supplied Air Suits, Model V4 MTH2 at the Browns Ferry, Sequoyah, and Watts Bar Nuclear Power Plants.

The staff has completed its preliminary review of your request and has determined that the enclosed Request for Additional Information will be necessary to complete our review.

Please contact me at (301) 415-1364 if you have any questions.

Sincerely,

/RA/

Douglas V. Pickett, Senior Project Manager, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-259, 50-260, 50-296, 50-327, 50-328, and 50-390

Enclosure:

Request for Additional Information cc w/encl: See next page

June 20, 2005 Mr. Karl W. Singer Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, Tennessee 37402-2801

SUBJECT:

BROWNS FERRY NUCLEAR PLANT, UNITS 1, 2, AND 3, SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2, AND WATTS BAR NUCLEAR PLANT, UNIT 1 - REQUEST FOR ADDITIONAL INFORMATION RELATED TO DELTA PROTECTION MURUROA SINGLE USE SUPPLIED AIR SUITS (TAC NOS.

MC6995, MC6996, MC6997, MC6998, MC6999, MC7000)

Dear Mr. Singer:

By letter dated May 13, 2005, the Tennessee Valley Authority requested approval to use Delta Protection Mururoa Single Use Supplied Air Suits, Model V4 MTH2 at the Browns Ferry, Sequoyah, and Watts Bar Nuclear Power Plants.

The staff has completed its preliminary review of your request and has determined that the enclosed Request for Additional Information will be necessary to complete our review.

Please contact me at (301) 415-1364 if you have any questions.

Sincerely,

/RA/

Douglas V. Pickett, Senior Project Manager, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-259, 50-260, 50-296, 50-327, 50-328, and 50-390

Enclosure:

Request for Additional Information cc w/encl: See next page DISTRIBUTION:

PUBLIC PDII-2 r/f RidsOgcRp RidsAcrsAcnwMailCenter RidsNrrDlpmLpdii2 RidsNrrPMDPickett RidsNrrLABClayton RidsRgn2MailCenter (SCahill)

SKlementowicz RidsNrrDlpmDpr RidsNrrDssaDpr RPederson RidsNrrPMMChernoff RidsNrrPMEBrown KAlm-Lytz ADAMS Accession No.: ML051570407 NRR-088 OFFICE PDII-2:PM PDII-2:LA DIPM:IPSB PDII-2:SC NAME DPickett BClayton SKlementowicz MMarshall DATE 06 / 09 / 05 06 / 08 / 05 06 / 09 / 05 06 / 20 / 05 OFFICIAL COPY

Page 1 of 2 Mr. Karl W. Singer BROWNS FERRY NUCLEAR PLANT Tennessee Valley Authority SEQUOYAH NUCLEAR PLANT WATTS BAR NUCLEAR PLANT cc:

Mr. Ashok S. Bhatnagar, Senior Vice President Nuclear Operations Tennessee Valley Authority 6A Lookout Place Chattanooga, TN 37402-2801 Mr. Larry S. Bryant, General Manager Nuclear Engineering Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 Mr. Paul L. Pace, Manager Licensing and Industry Affairs Sequoyah Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Soddy Daisy, TN 37384-2000 Mr. Lawrence E. Nanney, Director Division of Radiological Health Dept. of Environment & Conservation Third Floor, L and C Annex 401 Church Street Nashville, TN 37243-1532 Senior Resident Inspector Sequoyah Nuclear Plant U.S. Nuclear Regulatory Commission 2600 Igou Ferry Road Soddy Daisy, TN 37379 Mr. John C. Fornicola, Manager Nuclear Assurance and Licensing Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 Mr. Fredrick C. Mashburn Senior Program Manager Nuclear Licensing Tennessee Valley Authority 4X Blue Ridge 1101 Market Street Chattanooga, TN 37402-2801 General Counsel Tennessee Valley Authority ET 11A 400 West Summit Hill Drive Knoxville, TN 37902 Chairman Limestone County Commission 310 West Washington Street Athens, AL 35611 State Health Officer Alabama Dept. of Public Health RSA Tower - Administration Suite 1552 P.O. Box 303017 Montgomery, AL 36130-3017 Mr. Michael D. Skaggs Site Vice President Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609 Plant Manager Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609 Mr. Jon R. Rupert, Vice President Browns Ferry Unit 1 Restart Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609 Mr. Robert G. Jones Browns Ferry Unit 1 Plant Restart Manager Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609

Page 2 of 2 Mr. Karl W. Singer BROWNS FERRY NUCLEAR PLANT Tennessee Valley Authority SEQUOYAH NUCLEAR PLANT WATTS BAR NUCLEAR PLANT cc:

Mr. Scott M. Shaeffer Browns Ferry Unit 1 Project Engineer Division of Reactor Projects, Branch 6 U.S. Nuclear Regulatory Commission 61 Forsyth Street, SW.

Suite 23T85 Atlanta, GA 30303-8931 Licensing Manager Licensing and Industry Affairs Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609 Senior Resident Inspector Browns Ferry Nuclear Plant U.S. Nuclear Regulatory Commission 10833 Shaw Road Athens, AL 35611-6970 County Mayor Hamilton County Courthouse Chattanooga, TN 37402-2801 Mr. Randy Douet Site Vice President Sequoyah Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Soddy Daisy, TN 37384-2000 Mr. William R. Lagergren Site Vice President Watts Bar Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, TN 37381 Mr. Paul L. Pace, Manager Licensing and Industry Affairs Watts Bar Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, TN 37381 Mr. Jay Laughlin, Plant Manager Watts Bar Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Spring City, TN 37381 Senior Resident Inspector Watts Bar Nuclear Plant U.S. Nuclear Regulatory Commission 1260 Nuclear Plant Road Spring City, TN 37381 County Executive 375 Church Street Suite 215 Dayton, TN 37321 County Mayor P. O. Box 156 Decatur, TN 37322 Ms. Ann P. Harris 341 Swing Loop Road Rockwood, Tennessee 37854

Enclosure Request for Additional Information Tennessee Valley Authority (TVA)

Request to Use Delta Air Supplied Suits

1. Based on a review of the attachments provided in the licensee's submittal, the manufacturer states (and the European Certification Authority assumes) the V4 MTH2 suit is authorized for single-use only. Please confirm that the suit will be discarded after one use.
2. The use of National Institute for Occupation Safety and Health (NIOSH) equipment requires users to notify both the vendor and other users of any identified defects. Since the V4 MTH2 suits are non-NIOSH approved equipment, the staff requests verification that TVA will take timely action to report any defects experienced with these suits to other U.S. users in the nuclear field. Please describe your plans for notifying other users of potential defects.
3. While the licensee committed to develop implementing procedures (and training lesson plans) for using the suits, please identify any of the manufacturer's technical information (i.e., Instructions for Use) and directions provided, that will not be required by procedures.

For each instruction identified, explain the rationale for not including it in the program's procedures/training (and any other compensating actions).