March 4, 2005 Mr. Mark B. Bezilla Vice President-Nuclear, Davis-Besse FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State Route 2 Oak Harbor, OH 43449-9760

SUBJECT:

CLOSURE OF TAC NO. MC2644 REGARDING LICENSING BASIS FOR THE SERVICE WATER SYSTEM DISCHARGE FLOW PATH FOR THE DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1

Dear Mr. Bezilla:

By letter dated April 2, 2004, you submitted information concerning your evaluation of the licensing basis for the service water system discharge flow path for the Davis-Besse Nuclear Power Station, Unit 1.

As stated in your letter of April 2, 2004, the issue concerning the licensing basis arose during an NRC inspection and was documented in NRC Inspection Report 50-346/2003-010, dated March 5, 2004, as a violation (50-346/2003-010-01) of very low safety significance (Green).

You then directly replied to the violation by letter dated April 5, 2004, accepting the violation and describing your corrective actions.

By letter dated December 14, 2004, from NRC Region III (J. Grobe), the NRC acknowledged receipt of your April 5, 2004, letter (and unrelated letter dated June 18, 2004) and stated that We have reviewed your corrective actions and have no further questions at this time. These corrective actions will be examined during future inspections.

Because your letter of April 2, 2004, originated as a result of the inspection and violation discussed in your letter of April 5, 2004, which has been replied to by NRC letter dated December 14, 2004, and since any additional NRC followup will be through the NRC inspection program, we conclude that your letter of April 2, 2004, does not require a reply. Therefore, we are closing TAC No. MC2644.

M. Bezilla If you have any questions regarding this matter, I may be reached at 301-415-3027.

Sincerely,

/RA/

Jon B. Hopkins, Senior Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-346 cc: See next page

ML050260676 Nrr-106 OFFICE PDIII-2/PM PDIII-2/LA RGN3 PDIII-2/SC NAME JHopkins DClarke CLipa GSuh DATE 3/4/05 2/1/05 3/3/05 3/4/05

Davis-Besse Nuclear Power Station, Unit 1 cc:

Mary E. O'Reilly FirstEnergy Corporation 76 South Main St.

Akron, OH 44308 Manager - Regulatory Affairs FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State - Route 2 Oak Harbor, OH 43449-9760 Director, Ohio Department of Commerce Division of Industrial Compliance Bureau of Operations & Maintenance 6606 Tussing Road P.O. Box 4009 Reynoldsburg, OH 43068-9009 Regional Administrator U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60523-4351 Michael A. Schoppman Framatome ANP 24 Calabash Court Rockville, MD 20850 Resident Inspector U.S. Nuclear Regulatory Commission 5503 North State Route 2 Oak Harbor, OH 43449-9760 Barry Allen, Plant Manager FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State - Route 2 Oak Harbor, OH 43449-9760 Dennis Clum Radiological Assistance Section Supervisor Bureau of Radiation Protection Ohio Department of Health P.O. Box 118 Columbus, OH 43266-0118 Carol OClaire, Chief, Radiological Branch Ohio Emergency Management Agency 2855 West Dublin Granville Road Columbus, OH 43235-2206 Zack A. Clayton DERR Ohio Environmental Protection Agency P.O. Box 1049 Columbus, OH 43266-0149 State of Ohio Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Attorney General Office of Attorney General 30 East Broad Street Columbus, OH 43216 President, Board of County Commissioners of Ottawa County Port Clinton, OH 43252 President, Board of County Commissioners of Lucas County One Government Center, Suite 800 Toledo, OH 43604-6506 David Lochbaum, Nuclear Safety Engineer Union of Concerned Scientists 1707 H Street NW, Suite 600 Washington, DC 20006 The Honorable Dennis J. Kucinich United States House of Representatives Washington, D.C. 20515 The Honorable Dennis J. Kucinich United States House of Representatives 14400 Detroit Avenue Lakewood, OH 44107 Mr. James P. Riccio Nuclear Policy Analyst Greenpeace 702 H. Street, NW, Suite 300 Washington, DC 20001

Davis-Besse Nuclear Power Station, Unit 1 cc:

Paul Gunter Director Nuclear Watchdog Project Nuclear Information & Resource Service 1424 16th Street NW Suite 401 Washington, DC 20009 Mr. Lew W. Myers Chief Operating Officer FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State Route 2 Oak Harbor, OH 43449-9760