Nebraska Public Power District, Cooper Nuclear Station Safeguards Plan, Guard Training and Qualification Plan, and Contingency Plan, Revision 0
ML042570124
Person / Time
Site: Cooper Entergy icon.png
Issue date: 09/08/2004
From: Edington R
Nebraska Public Power District (NPPD)
To:
Document Control Desk, Office of Nuclear Reactor Regulation, Office of Nuclear Security and Incident Response
References
EA-03-086, NLS2004114, TAC MC2908
Download: ML042570124 (4)


Text

Nebraska Public Power District Always theie when you need us SAFEGUARDS INFORMATION NLS2004114 September 8, 2004 Via Overnight Delivery U.S. Nuclear Regulatory Commission ATTN: Documcnt Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738

Subject:

Nebraska Public Power District, Cooper Nuclear Station Safeguards Plan, Guard Training and Qualification Plan, and Contingency Plan, Revision 0 The purpose of this letter is to transmit the Cooper Nuclear Station (CNS) Safeguards Plan, Guard Training and Qualification Plan, and Contingency Plan (Plan), Revision 0. This version of the Plan incorporates Nebraska Public Power District's (NPPD) responses to the Nuclear Regulatory Commission's (NRC) Requests for Additional Infonnation (RAIs) (references I through 6) regarding the CNS Plan. In order to standardize our approach with the industry approach, NPPD's April 29, 2004, response to Order EA-03-086 was based on Nuclear Energy Institute (NEI) 03-12, Revision 1, "Template for the Security Plan, Training and Qualification Plan, Safeguards Contingency Plan," as approved by the Nuclear Regulatory Commission (NRC). When template language was involved in the RAI's, and where appropriate, NPPD committed to and has adopted the revised language agreed upon by the industry Security Working Group representatives and the NRC. Site Specific questions in the RAIs have also been addressed.

In addition to incorporating language as indicated above, NPPD has made one additional change as discussed with Messrs. Brian Benney and Dennis Gordon of the NRC staff and Mike Hamm of NPPD. NPPD has increased the number of anned response members in the Plan, Section 13; Appendix C, Section 4.2; and Appendix C, Section 7.

NOTE: The Attachment to this letter contains "Safeguards Information." Upon separation from this letter, this letter becomes "DECONTROLLED."

SAFEGUARDS INFORMATION COOPER NUCLEAR STATION P.O. Box 98 / Brownville, NE 68321-0098 Telephone: (402) 825-3811 / Fax: (402) 825-5211 www nppd com

(\\

/t

-1

NLS20041 14 Page 2 If you have any questions or require additional information, please contact Ms. Norena Robinson at 402-825-5691.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 8th day of September 2004.

Sincerely, Randall K. Edington Vice President - Nuclear and Chief Nuclear Officcr

/nr

Enclosure:

CNS Safeguards Plan, Guard Training and Qualification Plan, and Contingency Plan, Revision 0

References:

I)

U.S. Nuclear Regulatory Commission letter dated June 21, 2004, to Mr. Randall K. Edington, Nebraska Public Power District, "Cooper Nuclear Station - Request for Additional Information, Regarding Security Plan Sections 10-19 (TAC No. MC2908)

2)

U.S. Nuclear Regulatory Commission letter dated July 9, 2004, to Mr. Randall K. Edington, Nebraska Public Power District, "Cooper Nuclear Station - Request for Additional Information, RE: Training and Qualification Plan (TAC No. MC2908)

3)

U.S. Nuclear Regulatory Commission letter dated June 25, 2004, to Mr. Randall K. Edington, Nebraska Public Power District, "Cooper Nuclear Station - Request for Additional Information, Regarding Security Plan Sections 1-9 (TAC No. MC2908)

4)

Nebraska Public Power District letter (NLS2004086) dated June 29, 2004, from Randall K. Edington to U.S. Nuclear Regulatory Commission, "Response to Request for Additional Information."

5)

Nebraska Public Power District letter (NLS2004095) dated July 15, 2004, from Randall K. Edington to U.S. Nuclear Regulatory Commission, "Response to Request for Additional Information."

NOTE: The Attachment to this letter contains "Safeguards Information." Upon separation from this letter, this letter becomes "DECONTROLLED."

SAFEGUARDS INFORMATION

NLS20041 14 Page 3

6)

Nebraska Public Power District letter (NLS2004098) dated July 26, 2004, from Randall K. Edington to U.S. Nuclear Regulatory Commission, "Response to Request for Additional Information."

cc:

Michelle Honcharik wv/o enclosure Project Manager Regional Adminiistrator wv/o enclosure U.S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive Arlington, TX 76011 Brian Benney, Project Manager w/enclosure Security Plan Review Team Project Directorate 11 Division of Licensing Project Management Office of Nuclear Reactor Regulation Sr. Resident Inspector wv/o enclosure Cooper Nuclear Station NPG Distribution w/o enclosure CNS Records wv/o attachment NOTE: The Attachment to this letter contains "Safeguards Information." Upon separation from this letter, this letter becomes "DECONTROLLED."

SAFEGUARDS INFORMATION

I ATTACHMENT 3 LIST OF REGULATORY COMMITMENTSO I

Correspondence Number:

NLS20041 14 The following table identifies those actions committed to by Nebraska Public Power District (NPPD) in this document. Any other actions discussed in the submittal represent intended or planned actions by NPPD. They are described for information only and are not regulatory commitments. Please notify the Licensing & Regulatory Affairs Manager at Cooper Nuclear Station of any questions regarding this document or any associated regulatory commitments.

COMMITTED DATE COMMITMENT OR OUTAGE None 4

t 4.

4-1

PROCEDURE 0.42 l

REVISION 15 7