January 29, 2004 MEMORANDUM TO: Samson S. Lee, Chief License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation FROM:

Johnny Eads, Project Manager /RA/

License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation

SUBJECT:

FORTHCOMING PUBLIC INFORMATION SESSION FOR THE U.S. NUCLEAR REGULATORY COMMISSION (NRC) STAFF TO DESCRIBE THE LICENSE RENEWAL PROCESS DATE & TIME:

Tuesday, February 17, 2004 7:00 p.m. - 8:30 p.m.

LOCATION:

Waterford Town Hall Auditorium 15 Rope Ferry Road Waterford, Connecticut 06385 PURPOSE:

The NRC received an application from Dominion Nuclear Connecticut, Inc.

dated January 20, 2004 for the renewal of the operating licenses for the Millstone Power Station, Units 2 and 3. The purpose of the meeting is for the NRC staff to provide information describing the license renewal process and how the public can participate. The agenda for the meeting is attached.

Information on the license renewal process is available on the NRC web page at http://www.nrc.gov/reactors/operating/licensing/renewal.html.

CATEGORY 3:*

This is a Category 3 Meeting. The public is invited to participate in this meeting by providing comments and asking questions throughout the meeting.

CONTACT:

Johnny Eads, NRR/DRIP/RLEP 301-415-1471 jhe@nrc.gov

  • Commission's Policy Statement on Enhancing Public Participation in NRC Meetings, 67 Federal Register 36920, May 28, 2002.

ACCOMMODATIONS:

If special equipment or accommodations are needed to attend or present information at the public meeting, then Mr. Eads will need to be contacted no later than February 12, 2004, to provide the NRC staff adequate notice to determine whether the request can be accommodated.

PARTICIPANTS:

Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR).

NRC/NRR F. X. Cameron J. H. Eads F. P. Gillespie P. T. Kuo S. S. Lee et al.

Docket Nos.: 50-336 and 50-423

Attachment:

Agenda cc w/att: See next page ACCOMMODATIONS:

If special equipment or accommodations are needed to attend or present information at the public meeting, then Mr. Eads will need to be contacted no later than February 12, 2004, to provide the NRC staff adequate notice to determine whether the request can be accommodated.

PARTICIPANTS:

Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR).

NRC/NRR F. X. Cameron J. H. Eads F. P. Gillespie P. T. Kuo S. S. Lee et al.

Docket Nos.: 50-336 and 50-423

Attachment:

Agenda cc w/att: See next page DISTRIBUTION:

See next page DOCUMENT NAME: C:\\ORPCheckout\\FileNET\\ML040330844.wpd Accession No: ML040330844 OFFICE LA:RLEP:DRIP PM:RLEP:DRIP SC:RLEP:DRIP NAME YEdmonds JEads SLee DATE 1/29/2004 1/29/2004 1/29/2004 OFFICIAL RECORD COPY

Attachment AGENDA FOR PUBLIC INFORMATION SESSION FOR THE NRC STAFF TO DESCRIBE THE LICENSE RENEWAL PROCESS WATERFORD, CONNECTICUT TOWN HALL AUDITORIUM AGENDA (Times are approximate)

February 17, 2004 I.

Introduction/Opening remarks 7:00 p.m. - 7:15 p.m.

II.

Presentation of the license renewal application process 7:15 p.m. - 8:00 p.m.

III.

Public Questions 8:00 p.m. - 8:30 p.m.

V.

Adjourn 8:30 p.m.

DISTRIBUTION: Forthcoming Public Information Session Millstone Power Station, Units 2 and 3 Dated: January 29, 2004 Accession No: ML040330844 HARD COPY RLEP RF J. Eads E-MAIL:

PUBLIC J. Craig D. Matthews F. Gillespie C. Grimes RidsNrrDe E. Imbro G. Bagchi K. Manoly W. Bateman J. Calvo R. Jenkins P. Shemanski J. Fair S. Black B. Boger D. Thatcher R. Pettis G. Galletti C. Li J. Moore R. Weisman M. Mayfield A. Murphy S. Smith (srs3)

S. Duraiswamy Y. L. (Renee) Li RLEP Staff R. Arrighi F. Cameron M. Jenkins R. Lorson V. Nerses C. Marco R. Pulsifer D. Screnci, RI OPA PMNS

Millstone Power Station, Units 2 and 3 cc:

Lillian M. Cuoco, Esquire Senior Counsel Dominion Resources Services, Inc.

Rope Ferry Road Waterford, CT 06385 Edward L. Wilds, Jr., Ph.D.

Director, Division of Radiation Department of Environmental Protection 79 Elm Street Hartford, CT 06106-5127 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 First Selectmen Town of Waterford 15 Rope Ferry Road Waterford, CT 06385 Mr. P. J. Parulis Manager - Nuclear Oversight Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. W. R. Matthews Senior Vice President - Nuclear Operations Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. John Markowicz Co-Chair Nuclear Energy Advisory Council 9 Susan Terrace Waterford, CT 06385 Mr. Evan W. Woollacott Co-Chair Nuclear Energy Advisory Council 128 Terrys Plain Road Simsbury, CT 06070 Senior Resident Inspector Millstone Power Station c/o U.S. Nuclear Regulatory Commission P. O. Box 513 Niantic, CT 06357 Mr. G. D. Hicks Director - Nuclear Station Safety and Licensing Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Ms. Nancy Burton 147 Cross Highway Redding Ridge, CT 00870 Mr. William D. Meinert Nuclear Engineer Massachusetts Municipal Wholesale Electric Company Moody Street P.O. Box 426 Ludlow, MA 01056 Mr. J. Alan Price Site Vice President Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. Chris Funderburk Director, Nuclear Licensing and Operations Support Dominion Resources Services, Inc.

Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. David W. Dodson Licensing Supervisor Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385

Millstone Power Station, Units 2 and 3 cc Mr. S. E. Scace Assistant to the Site Vice President Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. M. J. Wilson Manager - Nuclear Training Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. A. J. Jordan, Jr.

Director - Nuclear Engineering Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. S. P. Sarver Director - Nuclear Station Operations and Maintenance Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Charles Brinkman, Director Washington Operations Nuclear Services Westinghouse Electric Company 12300 Twinbrook Pkwy, Suite 330 Rockville, MD 20852