ML033560466
| ML033560466 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 11/28/2003 |
| From: | Hagar B, Payne D Division of Reactor Safety I, Progress Energy Co |
| To: | |
| References | |
| 71111.05, FOIA/PA-2003-0358 IR-02-011 | |
| Download: ML033560466 (40) | |
See also: IR 05000400/2002011
Text
FIRE PROTECTION BASELINE INSPECTION
SHEARON HARRIS
INPUT FOR INSPECTION REPORT NO.: 50-400/2002-011
INSPECTORS:
Charlie Payne
Team Leader - Fire Protection
Engineering Branch 1, DRS
Bob Hagar
Resident Inspector, Harris
INSPECTION DATES:
Week 1 of onsite inspection - October 21 - 25, 2002.
Week 2 of onsite inspection - November 4 - 8, 2002
Week 3 of onsite inspection - December 16-20, 2002
Type of Inspection: TRIENNIAL FIRE PROTECTION BASELINE INSPECTION: Fire
Protection Features and Post-Fire Safe Shutdown Capability
A.
INSPECTION REPORT INPUT
1.
REACTOR SAFETY
Cornerstones: Initiating Events, Mitigating Systems
1R05
FIRE PROTECTION (71111.05)
.04
Operational Implementation of SSD Capability
The guidelines established by BTP CMEB 9.5-1, Section C.5.b, uSafe Shutdown
Capability," paragraph (1), required that SSCs important to safe shutdown be provided
with fire protection features capable of limiting fire damage to ensure that one train of
systems necessary to achieve and maintain hot shutdown conditions remained free of
fire damage. Options for providing this level of fire protection were delineated in BTP
CMEB 9.5-1, Section C.5.b, 'Safe Shutdown Capability," paragraph (2). Where the
protection of systems whose function was required for hot shutdown did not satisfy BTP
CMEB 9.5-1, Section C.5.b, paragraph (2), an alternative or dedicated shutdown
capability and its associated circuits, was required to be provided that was independent
of the cables, systems, and components in the area. For such areas, BTP CMEB 9.5-1,
Section C.5.c, "Alternative or Dedicated Shutdown Capability," paragraph (3),
specifically required the alternative or dedicated shutdown capability to be physically and
electrically independent of the specific fire areas and capable of accommodating
post-fire conditions where offsite power was available and where offsite power was not
available for 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. BTP CMEB 9.5-1, Section C.5.f, "Ventilation," required that
products of combustion and the means by which they will be removed from each fire
area be established to ensure that smoke and corrosive gases will not affect SSD areas.
a.
Inspection Scope
XD
For fires in fire areas 1-A-BAL, Fire Zones 1-A-4-CHLR and 1-A-4-COM-E, 1-A-EPA,
1-A-BATB, and 1-A-ACP, the team walked down the manual actions described in
procedure AOP-036, Safe Shutdown Following a Fire, to verify that:
The procedures used for SSD were available to the appropriate staff.
The procedures used for SSD were consistent with the SSA methodology and
assumptions.
The procedures were written so that operator actions could be correctly performed
within the times assumed in the SSA.
The training program for operators included SSD capability for a fire event.
Personnel required to achieve and maintain the plant in hot shutdown condition from
the MCR could be provided from normal onsite staff, exclusive of the fire brigade.
Operators had sufficient access to the equipment to perform the required actions.
For each of these manual actions, the team reviewed fire-protection-related licensing-
basis documents, to verify that these actions were described in those documents.
The team also reviewed:
operator and fire brigade staffing, to verify that shift staffing would be adequate to
complete the required manual actions, and
selected fire fighting pre-plan procedures and heating ventilation and air conditioning
(HVAC) systems, to verify that access to remote shutdown equipment and operator
manual actions would not be inhibited by smoke migration from one area to adjacent
plant areas used to accomplish SSD.
In addition, the team reviewed operator training lesson plans and job performance
measures (JPMs) and discussed the training with operators, to verify that SSD activities
had been appropriately included in the training program.
b.
Findings
(1) RELIANCE ON MANUAL ACTIONS
Introduction
An unresolved item was identified for excessive reliance on manual actions to establish
and maintain SSD in case of a fire, instead of physically protecting cables from fire
damage. (no approved deviations)
Description
Analysis
Enforcement
.
(2) INADEQUATE SAFE SHUTDOWN PROCEDURE
Introduction: A Green non-cited violation of TS 6.8.1 with two examples was identified
for failure to establish an adequate written procedure covering fire protection program
implementation, in that the licensee's procedure for safe shutdown following a fire
describes manual actions that cannot reasonably be completed by some NLOs.
Description: The team identified several actions required by AOP-036 that could not
reasonably be completed by all SSD NLOs. Those actions and the challenges
associated with those actions are described below.
For a fire in Fire Area 1 -A-ACP, AOP-36 steps 2.c and 14.a required the NLO to remove
fuses from transfer panel 1 B. Completing these steps would include overcoming the
following challenges:
The subject transfer panel was physically located approximately 20 feet from the
ACP room door. With a fire in the ACP room, the area around the transfer panel
could become uninhabitable before the NLO could complete these steps, because
some smoke from the fire could enter the transfer panel area from around the door
while the door is closed, and because smoke would certainly enter the transfer panel
area when the door is opened by the fire brigade to attack the fire.
To physically reach the subject fuses, the NLO would necessarily place his or her
entire body inside a cabinet with a central access area that is approximately 15
inches wide. The licensee had not ensured that all NLOs were physically capable of
entering that cabinet.
Because the subject fuses were located on a panel approximately seven feet above
floor level, to physically reach the subject fuses, all but the tallest NLOs would
necessarily use a narrow, custom-made wooden step-stool to step up to the shield.
The team noted that the location of the step-stool was not controlled.
Because the subject fuses were also located behind a plexiglass fuse cover that was
held in place by small screws, to physically reach the subject fuses, the NLO would
necessarily raise his or her hands above the level of his or her head, and use a
metal screwdriver to remove the fuse cover. The licensee had not ensured that all
NLOs were physically capable of completing this activity. Furthermore, because this
activity involves manipulating a metal screwdriver inside an energized electrical
cabinet, the team considered this activity to involve a personnel safety hazard.
To identify the correct fuses to be pulled, the NLO must first identify the cabinet in
which the fuses are located, and then identify the fuses themselves, within that
cabinet. The team observed that the subject cabinet was physically adjacent to 4
identical cabinets, that these cabinets were not labeled on the side from which the
NLO would enter, and that the instructions in AOP-036 did not identify the subject
cabinet. Furthermore, the team observed that the labels which uniquely identify the
subject fuses within the cabinet were partially obscured by cables which had been
landed on adjacent terminal blocks.
For a fire in Fire Area 1 -A-BATB (Battery Room B,) AOP-036 steps 1.a through 1.d
provided guidance for responding to spurious opening of the RHR containment recirc
sump suction valves. Opening both train A (1SI-300 and 1SI-310) or both train B (1SI-
301 and 1 SI-31 1) sump suction valves would result in the RWST draining down to the
sumps through normally open RWST to RHR supply valves 1 S1-322 (train A) or 1 SI-323
(train B). The team determined that during a fire in Battery Room B, only train B cables
would be affected. Therefore, train B containment recirc sump suction valves would be
the valves of concern. The train A valves would be unaffected and remain closed.
Step 1.a directed the operator to shut and de-energize both RWST to RHR supply
valves (to A and B RHR Pumps, respectively) to immediately stop the RWST drain
down. The team noted that because only train B would be the affected, only supply
valve 1 SI-323 would need to be shut to halt the drain down. Because the train A sump
suction valves would still be shut, shutting 1 Sl-322 would isolate all water suction
sources to the A RHR Pump.
Step 1.b provided guidance to refill the RWST with the A RHR Pump from the
containment emergency sump. None of the actions listed in step 1.b direct opening the
sump isolation valves. Because the A RHR Pump has no suction flow path, the RWST
would not be refilled using this step. The pump recirc line would prevent pump damage
provided prompt operator action to diagnose the improper system response.
Similarly, for a fire in Fire Area 1-A-EPA, the team found the above procedure
deficiencies were repeated but for the opposite train of RHR (train A cables are exposed
in this fire area). The team also noted that the licensee had identified valves 1Sl-322
and 1 SI-300 as contaminated and had wrapped these valves in yellow polyethylene
plastic for contamination control. However, there was no anti-contamination clothing,
step-off pad or portable radiation monitor pre-staged at this location to allow the SSD
NLO to quickly manipulate either valve in emergency conditions. Additionally, the local
valve position indication for each valve was covered by the yellow polyethylene plastic
which would have precluded an NLO from visually verifying valve position from outside
the contamination control area.
Because of these challenges, the team considered that not all NLOs could reasonably
be expected to successfully complete the manual actions described in these steps.
LATER: inadequate corrective action for the previous White finding on the ACP room Thermo-
Lag wall?
LATER: other examples?
Analysis This violation was more than minor because it affected the objectives of the
Mitigating Systems cornerstone, in that this violation could affect the availability of
systems that respond to fire events to prevent undesirable consequences. The safety
significance of this violation was very low, because the fire initiation frequency in the
corresponding area is very low, and because failure to remove the subject fuses would
potentially disable only the turbine-driven auxiliary feedwater pump; all other mitigation
capabilities would not be affected.
Enforcement TS 6.8.1 requires, in part, that written procedures shall be established,
implemented, and maintained covering fire protection program implementation. By
reference, FSAR section 9.5.1 incorporates into the FSAR, the licensee's Safe
Shutdown Analysis in Case of Fire (calculation E-5525). In E-5525, Revision 6, Section
VL.B describes the methodology through which manual actions were identified, and
Attachment D lists the manual actions that may need to be taken if safe shutdown
components are damaged as a result of a fire. Those manual actions are incorporated
into AOP-036.
Contrary to the above, the licensee failed to establish an adequate written procedure
covering fire protection program implementation, in that in Attachment 1 of procedure
AOP-036, Safe Shutdown Following a Fire, steps 2.c and 4 of the Safe Shutdown
Manual Operations for fire area 1-A-ACP describe manual actions which cannot
reasonably be completed by some NLOs. Because this failure to implement an
adequate procedure is of very low safety significance and has been entered into the
CAP (AR 80214), this violation is being treated as an NCV, consistent with Section VL.A
of the NRC Enforcement Policy: NCV 50-400/02-1 1-XX
(3) INADEQUATE PROCEDURE (inadequate staffing)
Introduction A Green non-cited violation of TS 6.8.1 was identified for failure to
establish an adequate written procedure covering fire protection program
implementation, in that the licensee's procedure for safe shutdown following a fire
describes more manual actions than can reasonably be completed by normal onsite
staff.
Description: The team found that for each fire area inspected, AOP-036 required
operators to complete a relatively large number of manual actions outside the main
control room. The team determined that the normal shift operating crew included four
non-licensed operators (NLOs). Three NLOs were assigned to the fire brigade and one
NLO was assigned to support safe shutdown manual actions (SSD NLO). The table
below shows, for each fire area reviewed during this inspection, the number of manual
actions required by AOP-036 to be completed outside the main control room to achieve
hot standby conditions.
Number of manual actions
Fire Area / Zone
In AOP-036
In other procedures*
Generic Steps for
10
Many. Depends on
All Fire Areas
decisions made by the
operating crew.
1-A-BAL-B
29
LATER
1 -A-BATB
14
LATER
1-A-EPA
14
LATER
Number of manual actions
Fire Area / Zone
In AOP-036
In other procedures*
1-A-ACP
27
18
- Numbers in this column show how many manual actions were
described in procedures that were called out by AOP-036.
The specific local manual operator actions evaluated by the team for each of these fire
areas are listed in Attachment 1.
The team found that while most of the manual actions in these areas involved one-time
actions (like opening a breaker), others could require the NLO to monitor plant
conditions and make system adjustments over an extended period of time. The manual
actions which could require dedicated NLO attention, and thus possibly detract from the
successful and timely performance of subsequent required local manual operator
actions, include the following:
In Section 3.0 of AOP-036, Step 13.b(3) requires the NLO to establish continuous
communications with the MCR, locally shut 1 CS-228 to isolate the normal charging
flow control valve (FCV) and then to locally control charging flow by throttling the
bypass valve, 1 CS-227. Both valves are in close proximity and located in the
scalloped area of the 248-ft level in the reactor auxiliary building (RAB). This area is
located in the radiation-controlled area (RCA) and radiation levels at these valves
are elevated but within 10 CFR 20 limits. A sound powered phone with a long
extension cord is located in the area to allow the NLO to wait in low dose areas
between valve manipulations if the NLO's radio is not functional. However, local
manual operator actions subsequent to this step could be adversely impacted (e.g.,
Section 3.0, Step 14.b for locally responding to a failed open steam generator
PORV).
In Attachment I of AOP-036, Step 13.c for fire area 1-A-ACP requires the NLO to
locally operate a PORV on the C steam generator, to obtain and maintain the
desired RCS temperature. Because the unit will likely not be at steady state when
this action is undertaken, and because a fire in this area may complicate operator
efforts to stabilize the plant, the NLO who undertakes this action may be required to
monitor RCS temperature and make appropriate adjustments to the PORV position
almost continuously and for some time, until the plant is reasonably stable.
In Attachment 1 of AOP-036, Step 14.b for fire area 1-A-ACP requires the NLO to
throttle 1AF-149 to maintain level in the C steam generator. For the same reasons
as described above, the NLO who undertakes this action may be required to
continue to monitor steam-generator level and make appropriate adjustments to the
position of 1AF-149 almost continuously and for some time, until the plant is
reasonably stable.
The team found that some of the required manual actions would be completed inside
the RCA, while others would be completed outside the RCA. The team also observed
that completing the manual actions in AOP-036, in the order in which they are described
in that procedure, would require the SSD NLO to enter and exit the RCA several times.
The team noted that:
some manual actions involved valves identified as potentially contaminated or
located in contamination areas,
radioactive radon gas can become associated with anyone who passes through the
RCA,
hand or foot contamination as well as radon gas can cause a portal monitor to
alarm, and
anyone who is in a portal monitor when it alarms must wait at the exit point for health
physics (HP) technicians to complete a detailed survey to determine the true cause
of the alarm, before proceeding.
The team noted that the licensee had no emergency dosimeters or rapid ingress/egress
procedures in place for use during plant emergency situations. The team therefore
considered that every time the SSD NLO exited the RCA, that NLO may experience a
portal-monitor alarm, and may therefore be forced to wait for HP technicians to arrive at
the exit and complete a detailed survey before proceeding.
The team considered that the manual actions in AOP-036 could not reasonably be
completed by the available staff, because:
the SSD NLO may be required to complete as many as 39 manual actions,
several manual actions require dedicated operator attention,
some of the manual actions could require a considerable amount of time to
complete,
completing some manual actions could be delayed by RCA portal-monitor alarms,
and
only one NLO would have been available to complete all safe-shutdown manual
actions.
The team therefore considered that procedure to be inadequate.
Analysis: This violation was more than minor because it affected the objectives of the
Mitigating Systems cornerstone, in that this violation could affect the availability of
systems that respond to fire events to prevent undesirable consequences. The safety
significance of this violation was very low, because the fire initiation frequency in the
corresponding area is very low.
Enforcement TS 6.8.1 requires, in part, that written procedures shall be established,
implemented, and maintained covering fire protection program implementation. By
reference, FSAR section 9.5.1 incorporates into the FSAR, the licensee's Safe
Shutdown Analysis in Case of Fire (calculation E-5525). In E-5525, Revision 6, Section
VI.B describes the methodology through which manual actions were identified, and
Attachment D lists the manual actions that may need to be taken if safe shutdown
components are damaged as a result of a fire. Those manual actions are incorporated
into AOP-036.
Contrary to the above, the licensee failed to establish a written procedure covering fire
protection program implementation, in that in Attachment 1 of procedure AOP-036, Safe
Shutdown Following a Fire, the Safe Shutdown Manual Operations for fire area 1 -A-ACP
describe too many manual actions for the available staff to complete. Because this
failure to implement an adequate procedure is of very low safety significance and has
been entered into the CAP (AR 80215), this violation is being treated as an NCV,
consistent with Section VI.A of the NRC Enforcement Policy: NCV 50-400/02-11 -XX
.07.
The guidelines established by BTP CMEB 9.5-1, Section C.5.g, "Lighting and
Communication," paragraph (1), required that fixed self-contained lighting consisting of
fluorescent or sealed-beam units with individual eight hour minimum battery power
supplies should be provided in areas that must be manned for safe shutdown and for
- access and egress routes to and from all fire areas.
a.
Inspection Scope
The team reviewed the design and operation of, and examined the manufacturer's
information for the direct current (DC) emergency lighting system self-contained, battery
powered units (ELUs) as described in UFSAR Sections 9.5.1.2.2.e and 9.5.3. During
plant walk downs of selected areas where operators performed local manual actions
defined in the post-fire SSD procedure, the team inspected area emergency lighting
units (ELUs) for operability and checked the aiming of lamp heads to determine if
adequate illumination was available to correctly and safely perform the actions required
by the procedures. The team inspected emergency lighting features along access and
egress pathways used during SSD activities for adequacy and personnel safety. The
locations and identification numbers on the ELUs were compared to design drawings to
confirm the as-built configuration. The team also checked if these battery power
supplies were rated with at least an 8-hour capacity. In addition, the team reviewed
licensee periodic maintenance tests to verify that the ELUs were being maintained in an
operable manner.
b.
Findings
Introduction A violation was identified for failure to provide fixed, self-contained lighting
with individual eight-hour-minimum battery power supplies in areas that must be
manned for safe shutdown.
Description In the areas in which the team walked down safe shutdown manual actions,
the team identified that the local manual operator actions listed in Attachment 2 would
not be illuminated by fixed, self-contained lighting with individual eight-hour-minimum
battery power supplies.
The team determined that the licensee had not requested exemptions from the
requirement to provide such lighting.
Analysis The team determined that this violation was more than minor because it
affected the objectives of the Mitigating Systems cornerstone, in that this violation could
affect the availability of systems that respond to fire events to prevent undesirable
consequences.
The team noted that the fire initiation frequency in the ACP room was LATER. The
team reviewed site lighting drawings, and found that the manual actions listed in
Attachment 3 were in the vicinity of flourescent lighting that would be powered from a
diesel generator during a SSD scenario.
The team considered the risk significance of this violation to be very low, because the
fire initiation frequency in this area is low, and because NLOs routinely carry flashlights
that could be used to illuminate the areas in which the actions must be completed.
Enforcement FSAR section 9.5.1 states that Branch Technical Position (BTP) 9.5-1 is
used in the design of the fire protection program for safety-related systems and
equipment and for other plant areas containing fire hazards that could adversely affect
safety-related systems. BTP 9.5-1, Section C.5.g, uLighting and Communication,"
paragraph (1), required that fixed self-contained lighting consisting of fluorescent or
sealed-beam units with individual eight-hour-minimum battery power supplies should be
provided in areas that must be manned for safe shutdown and for access and egress
routes to and from all fire areas.
Contrary to the above, the licensee failed to provide fixed self-contained lighting
consisting of fluorescent or sealed-beam units with individual eight-hour-minimum
battery power supplies in the vicinity of the components associated with the following
manual actions identified above. Because this failure to provide the subject lighting is of
very low safety significance and has been entered into the CAP (AR 79047), this
violation is being treated as an NCV, consistent with Section VI.A of the NRC
Enforcement Policy: NCV 50-400/02-1 1-XX
List of Inspection Documents Reviewed
PROCEDURES
AOP-036, Safe Shutdown Following a Fire, Rev. 21
AOP-038, Rapid Downpower, Rev. 2
EOP-EPP-004, Reactor Trip Response, Rev. 10
EOP-Guide-1, Path 1 Guide, Rev. 14
MST-10277, Electrical Power Feed Switchover for RHR Inlet Isolation Valve 1 RH-1 (1 RH-
OP-i 10, Section 8.3, Venting the SI Accumulators, Rev. 18
JOB PERFORMANCE MEASURES (JPMs) AND LESSON PLANS
LOCAL MANUAL OPERATOR ACTION STEPS
REVIEWED FOR ACHIEVING HOT STANDBY
Summary of Number of Local Manual Action Steps to be Performed Outside of the Control
Room to Achieve and Maintain Hot Standby
Number of Manual Action Ste
Fire Area / Zone
Generic Steps
Area Specific
Total Steps
in AOP-36 for
Steps in AOP-036
by Fire
All Fire Areas
and Other
Area/Zone
Procedures
Referenced by
1 -A-BAL-B
10
29
39
1-A-BATB
10
14
24
1 -A-EPA
10
14
24
1-A-ACP
10
45
55
Listing of AOP-036 Manual Action Steps Reviewed for Safe Shutdown Following a Fire
Section 3.0 Actions (Generic Steps for All Fire Areas/Zones):
Step 12.c RNO
MONITOR AFW pump suction pressure indicators as an alternative to
CST level indication: (Refer to Attachment 4, AFW Suction Pressure vs.
CST level)
I
- PI-2271 (at TDAFW Pump)
Step 13.b(3)
Locally PERFORM the following (248' RAB):
(a) SHUT 1CS-228, Normal Charging FCV Inlet Isolation Valve.
(b) THROTTLE 1CS-227, Normal Charging FCV Bypass, as necessary to
control charging flow.
Step 13.c RNO
ESTABLISH flow through the Hi Head Si Line, as follows:
(1) .(MCR
action)
(2) .(MCR
action)
(3) OPEN ONE of the following breakers:
1B31 -SB 4C, 1SI-3 BIT Outlet
.
(4) WHEN directed by MCR, THEN locally THROTTLE the de-energized
valve to maintain PRZ level:
Attachment 2
2
1 S-3, BIT Outlet Isolation
1SI-4, BIT Outlet Isolation
Stepl 4.b
UNLOCK and SHUT the affected manual block valve(s): (Steam Tunnel
Platform El. 280)
1 MS-59, SG A PORV Manual Block
1MS-61, SG B PORV Manual Block
1 MS-63, SG C PORV Manual Block
AOP-36 Attachment 1 (Area Specific) Actions For Fire Area: 1-A-BATB:
Step 1
IF RHR suction valves spuriously open resulting in RWST drain down,
THEN PERFORM the following recommended actions, as required:
Step 1.a
ISOLATE the Containment Recirc Sumps from the RWST, as follows:
(1) SHUT the following valves:
(2) DE-ENERGIZE the following valves:
- 1SI-322 at breaker 1A31-SA-6E (RAB 286)
- 1 SI-323 at breaker 1 B31 -SB-6E (RAB 286)
Step 1.b
REFILL the RWST with A RHR Pump, as follows:
(1) SHUT 1SI-327, Low Head SI Train B to Hot Leg Crossover Isol Vlv.
(2) OPEN the following valves to align RHR HX outlet flow to the RWST:
(3) USE the RHR Pump as needed.
Step 1.d
WHEN RHR Pumps are no longer required to fill the RWST,
THEN:
(1) SHUT the following valves to isolate RHR HX outlet flow from the
RWST:
(2) OPEN 1SI-327, Low Head SI Train B to Hot Leg Crossover Isol Vlv.
Step 2
PERFORM the following to prevent spurious valve opening:
Attachment 2
3
Step 2.a
VERIFY the following valves are SHUT:
(RAB 286)
Step 2.b
DE-ENERGIZE the following valves:
- 1 SI-301 at breaker 1 B21 -SB-11 B (RAB 286)
- 1 SI-311 at breaker 1 B21 -SB-7A (RAB 286)
AOP-36 Attachment 1 (Area Specific) Actions For Fire Area: 1-A-EPA:
Step 7
IF RHR suction valves spuriously open resulting in RWST drain down,
THEN PERFORM the following recommended actions, as required:
Step 7.a
ISOLATE the Containment Recirc Sumps from the RWST, as follows:
(1) SHUT the following valves:
1 SI-322, RWST To RHR Pump A-SA (RAB 286)
. 1 SI-323, RWST To RHR Pump B-SB (RAB 286)
(2) DE-ENERGIZE the following valves:
- 1SI-322 at breaker 1A31-SA-6E (RAB 286)
- 1 SI-323 at breaker 1 B31-SB-6E (RAB 286)
Step 7.b
REFILL the RWST with B RHR Pump, as follows:
(1) SHUT 1SI-326, Low Head SI Train A to Hot Leg Cross-over Isol Vlv.
(2) OPEN the following valves to align RHR HX outlet flow to the RWST:
(3) USE the RHR Pump as needed.
Step 7.c
IF charging is required in the interim,
THEN USE the Boric Acid Tanks.
Step 7.d
WHEN RHR Pumps are no longer required to fill the RWST,
THEN:
(1) SHUT the following valves to isolate RHR HX outlet flow from the
RWST:
(2) OPEN 1 SI-326, Low Head SI Train A to Hot Leg Cross-over Isol Vlv.
Attachment 2
4
Step 8
PERFORM the following to prevent spurious valve opening:
Step 8.a
VERIFY the following valves are SHUT:
. 1SI-300, CV Sump 1A To RHR Pmp 1A-SA CIV (RAB 286)
. 1SI-310, CV Sump 1A To RHR Pmp 1A-SA Downstrm Iso Vlv
(RAB 286)
Step 8.b
DE-ENERGIZE the following valves:
. 1SI-300 at breaker 1A21-SA-7C (RAB 286)
- 1 SI-310 at breaker 1 A21 -SA-9B (RAB 286)
AOP-36 Attachment 1 (Area Specific) Actions for Fire Area 1-A-BAL:
Step 1
PERFORM the following to prevent spurious valve operations:
Step 1.a
VERIFY the following valves are OPEN
. 1CS-214, Charging/SI Pumps Miniflow Isol (RAB 236 near Boric Acid
Pumps)
. 1CS-1 69, CSIP Suction Header Xconn (RAB 247 above CSIPs)
.1 CS-218, CSIP Discharge Header Xconn (RAB 247 above CSIPs)
. 1CC-252, CCW From RCP Thermal Barrier FCV (RAB 236 Scalloped
Area)
Step 1.b
DE-ENERGIZE the following valves:
. 1CS-214 at breaker 1A35-SA-4C (RAB 261)
. 1CS-169 at breaker 1A35-SA-4B (RAB 261)
1 CS-218 at breaker 1 B35-SB-14D (RAB 261)
1 CC-252 at breaker 1 E12-6B (RAB 261)
Step 5
CAUTION
. The following step will inhibit all automatic and manual safeguards functions
since a fire in this area could cause spurious actuations as well as disable
controls for resetting Si.
- Removal of Output Relay Power Fuses from both trains of SSPS will
generate a Reactor Trip signal. The Reactor should be shut down prior to
performing the following step.
Attachment 2
5
OBTAIN SSPS Key 96
AND DEFEAT both trains of SSPS by removing the listed fuses in the front
of the listed SSPS Output Cabinets:
- Train A, Output Cabinet No. 1, Output Relay Power fuses
- Train A, Output Cabinet No. 2, fuses 61 and 62
- Train B, Output Cabinet No. 1, Output Relay Power fuses
- Train B, Output Cabinet No. 2, fuses 61 and 62
Step 20
IF the following valves cannot be shut due to fire damage to their control
cables,
THEN:
Step 20.a
STOP ALL CSIPs.
Step 20.b
SHUT EITHER of the following valves:
- 1CS-170, A CSIP Suction X-conn
- 1CS-1 68, C CSIP Suction X-conn with A CSIP
Step 20.c
SHUT EITHER of the following valves:
- 1CS-1 69, C CSIP Suction X-conn with B CSIP
- 1CS-171, B CSIP Suction X-conn
Step 20.d
VERIFY SHUT.1CS-214, Charging/SI Pumps Miniflow Isol.
Step 21
IF BOTH of the following occur due to fire damage to their control cables:
THEN ALIGN flow to the cooling tower, as follows:
Step 21.a
VERIFY OPEN 1 SW-275, ESW Return Header A to NSW.
Step 21.b
WHEN time permits,
THEN:
(1) DE-ENERGIZE 1 SW-270, ESW Header A Return to Aux Reservoir, at
breaker 1A35-SA-9C (RAB 261).
(2) OPEN 1 SW-270 locally (RAB 261).
(3) WHEN 1SW-270 is open,
THEN SHUT 1 SW-276, ESW to NSW Discharge Hdr.
Attachment 2
6
Step 22
IF BOTH 1SW-270 AND 1SW-276 shut,
THEN CROSS-CONNECT ESW Discharge Headers as follows:
Step 22.a
VERIFY OPEN 1SW-274, ESW Return Header B to NSW.
Step 22.b
VERIFY OPEN 1 SW-275, ESW Return Header A to NSW.
Step 22.c
VERIFY OPEN 1SW-271, ESW Header B Return to Aux Reservoir.
Step 22.d
WHEN time permits,
THEN:
(1) DE-ENERGIZE 1 SW-270, ESW Header A Return to Aux Reservoir, at
breaker 1A35-SA-9C (RAB 261).
(2) OPEN 1 SW-270 locally (RAB 261).
(3) WHEN 1 SW-270 has been opened,
THEN SHUT 1SW-274, ESW Return Header B to NSW.
AOP-36 Attachment 1 (Area Specific) Actions for Fire Area 1-A-ACP:
Step lb
SECURE Rod Drive MG sets using OP-1 04, Rod Control System
OP-1 04
Step Number
Description
7.3.2.02
Place GENERATOR CIRCUIT BREAKER CONTROL
switch 1A to TRIP
7.3.2.03
Place MOTOR CIRCUIT BREAKER CONTROL switch 1A
to TRIP
7.3.2.04
Open Reactor Trip Breakers, if not already open.
7.3.2.05
Place GENERATOR CIRCUIT BREAKER CONTROL
switch 1 B to TRIP
Place MOTOR CIRCUIT BREAKER CONTROL switch 1 B
to TRIP
Step 2
If BOTH MDAFW pumps are disabled, THEN:
Attachment 2
7
Step 2c
Obtain a transfer panel key 33, 34, 35, 36, 99 or 106 (MCR or ACP key
locker)...
... and de-energize the TDAFW Pump Trip and Throttle Valve by removing
fuses 1A-i1/1 976 and 1A-12/1976
Step 2d
De-energize 1 MS-70 by opening disconnect switch on DP-1 A2-SA-2B.
Step 2f
IF TDAFW Pump is NOT operating properly, THEN locally...
...VERIFY OPEN TDAFW Pump Trip and Throttle Valve
...VERIFY OPEN 1MS-70, Main Steam B to Aux FW Turbine
Step 2g
IF MCB CST level indication is NOT available,
THEN locally monitor AFW pump suction pressure using Attachment 4.
Step 4
REMOVE the fuse for 1 BD-30 SA at panel ARP-1 9A
REMOVE the fuse for 1 BD-49 SA at panel ARP-1 9A
Step 6
OPEN the power supply breaker for 1 CS-235 at breaker 1 B31 -SB-1 OA
Step 7
ISOLATE AND VENT IA to 1 CH-279
Step 7a
SHUT "1 IA-871 -11"
Step 7b
OPEN air filter drain petcocks on Instrument Air Filter
Step 7c
CHECK 1 CH-279, AH-12 1 ASA valve OPEN
Step 8
OPEN the power supply breaker for 1 CS-1 71 at breaker 1 B35-SB-4D
Step 9
Locally VERIFY OPEN 1CS-1 71, B CSIP Suction X-Conn valve
Locally VERIFY OPEN 1CS-235, Charging Line Isolation valve
Step 10
Locally verify shut 1 BD-30, SG 1 B Blowdown Isolation valve
Locally verify shut 1 BD-49, SG 1 C Blowdown Isolation valve
Step 13
IF SG C PORV cycles erroneously, THEN:
Step 13c
IF SG C PORV manuaVautomatic station does not function properly,
THEN locally OPERATE SG C PORV using OP-126 for desired cooldown
rate.
Step Number
Description
8.2.1.2.01
Obtain pliers, flashlight, head set, extension cord
Attachment 2
8
8.2.1.2.02
Open Servo Valve Solenoid feeder breaker PP-1A312-SA-
3
Open Servo Valve Solenoid feeder breaker PP-1 B312-SB-
3
Open Servo Valve Solenoid feeder breaker IDP-1A-SIII-1 1
8.2.1.2.03
Remove the cover from the side of the PORV
8.2.1.2.04
Establish communications with the Control Room
8.2.1.2.07
To throttle open the PORV,
8.2.1 .2.07a
Rotate Solenoid B manual override approximately 3/4 turn
in the clockwise direction
8.2.1.2.07b
As directed by the Control Room, slowly rotate Solenoid A
manual override approximately 3/4 turn in the clockwise
direction
8.2.1.2.07c
When the PORV is at its desired position, place Solenoid A
manual override back to its original position
8.2.1.2.08
To partially shut the PORV,
8.2.1.2.08a
Check Solenoid A manual override in the fully
counterclockwise position.
8.2.1 .2.08b
As directed by the Control Room slowly rotate Solenoid B
manual override to its original position by rotating it
approximately 3/4 turn in the counterclockwise direction,
until the PORV starts to shut.
8.2.1.2.08c
When the PORV is at the desired position, rotate Solenoid
B manual override approximately 3/4 turn in the clockwise
direction.
Step 14
IF FCV-2071C, Aux FW C Regulator 1AF-131, spuriously CLOSES, THEN
Step 1 4a
REMOVE fuse 1 A-5/1952 at Transfer Panel 1 B
Step 14b
THROTTLE 1AF-149, Stm Turb Aux FW C Isolation, to maintain SG C level
E
AOP-36 Attachment 2 Actions For SSD 1 Equipment Powered by SSD 2:
Step 2
IF control power is lost to 1 CS-231, Charging Flow controller,
Attachment 2
9
THEN PERFORM the following locally:
Step 2.a
SHUT 1CS-228, Normal Charging FCV Inlet Isolation Valve.
Step 2.b
MAINTAIN 25% to 60% PRZ level (charging flow) using 1CS-227, Normal
Charging FCV Bypass.
I
I AOP-36 Attachment 3 Actions For SSD 2 Equipment Powered by SSD 1:
This attachment was reviewed but contained no hot standby local manual
operator actions.
Attachment 2
10
LOCAL MANUAL OPERATOR ACTION STEPS
REVIEWED FOR ACHIEVING COLD SHUTDOWN
(Safe Shutdown Following a Fire, Rev. 21)
Attachment 1, SSD Emergency Manual Operations: Fire Area: 1-A-EPA
Step 4.b
WHEN manpower is available,
THEN:
(1) DE-ENERGIZE the following valves:
- 1 SI-246, Si Accumulator A Discharge, at breaker 1A21 -SA-5C
- 1 SI-248, SI Accumulator C Discharge, at breaker 1A21-SA-3D
Attachment 2, SSD 1 Equipment Powered by SSD 2:
Step 6
IF 1 RH-30, RHR Heat Xchg A Out Flow Cont, OR 1 RH-20, RHR Hx Xchg
A Byp Flow Cont, cannot be controlled due to loss of control power,
THEN:
Step 6.a
ISOLATE 1 RH-20 air supply, 1 IA-1 28-12, to cause it to fail closed.
Step 6.d
VERIFY RHR is cooling the RCS by trending temperature using ONE of
the following methods:
- .....(MCR action)
- Local temperature indication TI-5551A (RHR Heat Exchanger Outlet)
Attachment 2
11
Attachment 2
MANUAL ACTIONS DESCRIBED IN AOP-036
WITHOUT REQUIRED LIGHTING
Section 3.0, for All Fire Areas
Step #
Description
13.a(7)
Open 1 CS-526, BA Tk Supply to CSIP Isol. VIv.
Attachment 1, for Fire Area 1-A-ACP
Step #
Description
1.b
Secure Rod Drive MG sets using OP-104, Rod Control System
2.c
Obtain a transfer panel key 33, 34, 35, 36, 99 or 106 (MCR or ACP key
locker) and de-energize the TDAFW Pump Trip and Throttle Valve by
removing 2 fuses
2.d
De-energize 1MS-70 by opening disconnect switch on DP-1A2-SA-2B.
2.f
Locally verify open TDAFW Pump Trip and Throttle Valve and 1 MS-70,
Main Steam B to Aux FW Turbine
2.g
Locally monitor AFW pump suction pressure
4
Remove the fuses for 1 BD-30 SA and 1 BD-49 SA at panel ARP-1 9A
6
Open the power supply breaker for 1 CS-235 at breaker 1 B31 -SB-1 OA
9
Locally verify open 1 CS-235
14.a
Remove fuse 1 A-5/1952 at Transfer Panel 1 B
Attachment 1, for Fire Area 1-A-BATB
Step #
Description
1.b(1)
Shut 1SI-327, Low Head Si Train B to Hot Leg Crossover Isol. Vlv.
1.d(2)
Open 1 SI-327, Low Head SI Train B to Hot Leg Crossover Isol. Vlv.
Attachment 1, for Fire Area 1-A-EPA
Attachment 2
12
Step #
Description
7.b(1)
Shut 1SI-326, Low Head SI Train A to Hot Leg Crossover Isol. VWv.
7.d(2)
Open 1 S3-326, Low Head SI Train A to Hot Leg Crossover Isol. VWv.
Attachment 1, for Fire Area 1-A-BAL SSA Area 1-A-BAL-B
Step #
Description
21 .b(2)
Open 1 SW-270 locally (RAB 261).
22.c
Verify open 1 SW-271, ESW Header B Return to Aux. Reservoir.
22.d(2)
Open 1 SW-270 locally (RAB 261). (Same as step 21 .b(2) above but for
different plant conditions.)
Attachment 2
13
Attachment 3
MANUAL ACTIONS DESCRIBED IN AOP-036
WITH DIESEL-POWERED FLOURESCENT LIGHTING
Section 3.0, for All Fire Areas
Step #
Description
1 2.c
Monitor AFW pump suction pressure indicators as an alternative to CST
RNO
level indication: (Refer to Attachment 4, AFW Suction Pressure vs. CST
level)
- PI-2271 (at TDAFW Pump)
13.b(3)
(a) Shut 1CS-228, Normal Charging FCV Inlet Isolation Valve.
(b) Throttle 1 CS-227, Normal Charging FCV Bypass, as necessary to
control charging flow.
13.c
(3) Open one of the following breakers:
RNO
- 1B31-SB-4C, 1S1-3 BIT Outlet
- 1A31-SA-4C, 1SI-4 BIT Outlet
13.c
When directed by MCR, then locally throttle the de-energized valve to
RNO
maintain PRZ level:
- 1SI-3, BIT Outlet Isolation
- 1S1-4, BIT Outlet Isolation
Attachment 1, for Fire Area 1-A-ACP
Step #
Description
1.b
Secure rod drive MG sets using OP-104
2.c
Obtain a transfer panel key 33, 34, 35, 36, 99 or 106 (MCR or ACP key
locker) and de-energize the TDAFW Pump Trip and Throttle Valve by
removing 2 fuses
2.f
Locally verify open TDAFW pump trip and throttle valve & 1 MS-70
2.g
Locally monitor AFW pump suction pressure
4
Remove the fuses for 1 BD-30 SA and 1 BD-49 SA at panel ARP-1 9A
Attachment 1, for Fire Area 1-A-BATB
Step #
Description
Attachment 2
14
1.a(2)
(2) DE-ENERGIZE the following valves:
- 1SI-322 at breaker 1A31-SA-6E (RAB 286)
1.b(2)
(2) OPEN the following valves to align RHR HX outlet flow to the RWST:
1.d(1)
(1) SHUT the following valves to isolate RHR HX outlet flow from the
RWST:
Attachment 1, for Fire Area 1-A-EPA
Step #
Descrigtion
4.b(1)
DE-ENERGIZE the following valves:
- 1 SI-246, SI Accumulator A Discharge, at breaker 1A21-SA-5C
- 1SI-248, SI Accumulator C Discharge, at breaker 1A21-SA-3D
7.a(2)
(2) DE-ENERGIZE the following valves:
- 1SI-322 at breaker 1A31-SA-6E (RAB 286)
- 1 SI-323 at breaker 1 B31 -SB-6E (RAB 286)
7.b(2)
(2) OPEN the following valves to align RHR HX outlet flow to the RWST:
7.d(l)
(1) SHUT the following valves to isolate RHR HX outlet flow from the
RWST:
AOP-36 Attachment I (, for Fire Area 1-A-BAL, SSA Area 1-A-BAL-B
Steo #
Description
1.a
VERIFY the following valves are OPEN
. 1CS-214, Charging/SI Pumps Miniflow Isol. (RAB 236 near Boric Acid
Pumps)
Attachment 2
15
5
OBTAIN SSPS Key 96 AND DEFEAT both trains of SSPS by removing
the listed fuses in the front of the listed SSPS Output Cabinets:
. Train A, Output Cabinet No. 1, Output Relay Power fuses
- Train A, Output Cabinet No. 2, fuses 61 and 62
. Train B, Output Cabinet No. 1, Output Relay Power fuses
. Train B, Output Cabinet No. 2, fuses 61 and 62
16.b(1)
DE-ENERGIZE the following valves:
- 1SI-246, SI AccumulatorA Discharge, at breaker 1A21-SA-5C (RAB 286)
- 1S1-247, SI Accumulator B Discharge, at breaker 1 B21 -SB-5C (RAB 286)
- 1 SI-248, SI Accumulator C Discharge, at breaker 1 A21 -SA-3D (RAB 286)
22.a
VERIFY OPEN 1SW-274, ESW Return Header B to NSW.
22.d(3)
WHEN 1SW-270 has been opened,
THEN SHUT 1SW-274, ESW Return Header B to NSW.
Attachment 2, Safe Shutdown 1 Equipment Powered by Safe Shutdown 2
Step #
Description
2
IF control power is lost to 1 CS-231, Charging Flow controller,
THEN PERFORM the following locally:
a. SHUT 1 CS-228, Normal Charging FCV Inlet Isolation Valve.
b. MAINTAIN 25% to 60% PRZ level (charging flow) using 1 CS-227, Normal
Charging FCV Bypass.
6.a
ISOLATE 1 RH-20 air supply, 1 IA-1 28-12, to cause it to fail closed.
6.d
VERIFY RHR is cooling the RCS by trending temperature using ONE of
the following methods:
. Local temperature indication TI-5551A (RHR Heat Exchanger Outlet)
Attachment 3, Safe Shutdown 2 Equipment Powered by Safe Shutdown 1
Step #
Description
4.b
(1) OPEN feeder breaker 1A21-SA-5C, Accum lA-SA Disch Iso (RAB
286).
(2) OPEN feeder breaker 1 A21 -SA-3D, Accum 1 C-SA Disch Iso (RAB 286).
Attachment 2
16
6.d
VERIFY RHR is cooling the RCS by trending temperature using ONE of
the following methods:
. Local temperature indication TI-5551A (RHR Heat Exchanger Outlet)
Attachment 2
LOCAL MANUAL OPERATOR ACTION STEPS
REVIEWED FOR ACHIEVING HOT STANDBY
Summary of Number of Local Manual Action Steps to be Performed Outside of the Control
Room to Achieve and Maintain Hot Standby
l_______
_ Number of Manual Action Steps
Fire Area / Zone
Generic Steps
Area Specific
Total Steps
in AOP-36 for
Steps in AOP-036
by Fire
All Fire Areas
and Other
Area/Zone
Procedures
Referenced by
1-A-BAL-B
10
29
39
1 -A-BATB
10
14
24
1-A-EPA
10
14
24
1-A-ACP
10
45
55
Listing of AOP-036 Manual Action Steps Reviewed for Safe Shutdown Following a Fire
AOP-36 Section 3.0 Actions (Generic Steps for All Fire Areas/Zones):
Step 12.c RNO
MONITOR AFW pump suction pressure indicators as an alternative to
CST level indication: (Refer to Attachment 4, AFW Suction Pressure vs.
CST level)
- P1-2271 (at TDAFW Pump)
Step 13.b(3)
Locally PERFORM the following (248' RAB):
(a) SHUT ICS-228, Normal Charging FCV Inlet Isolation Valve.
(b) THROTTLE 1 CS-227, Normal Charging FCV Bypass, as necessary to
control charging flow.
Step 13.c RNO
ESTABLISH flow through the Hi Head Si Line, as follows:
(1).....(MCR action)
(2).....(MCR action)
(3) OPEN ONE of the following breakers:
(4) WHEN directed by MCR, THEN locally THROTTLE the de-energized
valve to maintain PRZ level:
Attachment 2
2
1 S-3, BIT Outlet Isolation
1SI-4, BIT Outlet Isolation
Stepl4.b
UNLOCK and SHUT the affected manual block valve(s): (Steam Tunnel
Platform El. 280)
1 MS-59, SG A PORV Manual Block
1 MS-61, SG B PORV Manual Block
1 MS-63, SG C PORV Manual Block
AOP-36 Attachment 1 (Area Specific) Actions For Fire Area 1-A-BATB:
Step 1
IF RHR suction valves spuriously open resulting in RWST drain down,
THEN PERFORM the following recommended actions, as required:
Step 1.a
ISOLATE the Containment Recirc Sumps from the RWST, as follows:
(1) SHUT the following valves:
(2) DE-ENERGIZE the following valves:
- 1 SI-322 at breaker 1 A31 -SA-6E (RAB 286)
- 1 SI-323 at breaker 1 B31-SB-6E (RAB 286)
Step 1.b
REFILL the RWST with A RHR Pump, as follows:
(1) SHUT 1 SI-327, Low Head SI Train B to Hot Leg Crossover Isol Vlv.
(2) OPEN the following valves to align RHR HX outlet flow to the RWST:
(3) USE the RHR Pump as needed.
Step 1.d
WHEN RHR Pumps are no longer required to fill the RWST,
THEN:
(1) SHUT the following valves to isolate RHR HX outlet flow from the
RWST:
- 1 SI-448, Low Head Si Recirc to RWST Root Isol Vlv
(2) OPEN 1 SI-327, Low Head SI Train B to Hot Leg Crossover Isol Vlv.
Step 2
PERFORM the following to prevent spurious valve opening:
Attachment 2
3 .
Step 2.a
VERIFY the following valves are SHUT:
(RAB 286)
Step 2.b
DE-ENERGIZE the following valves:
- 1 SI-301 at breaker 1 B21-SB-11 B (RAB 286)
1 SI-311 at breaker 1 B21 -SB-7A (RAB 286)
AOP-36 Attachment 1 (Area Specific) Actions For Fire Area 1-A-EPA:
Step 7
IF RHR suction valves spuriously open resulting in RWST drain down,
THEN PERFORM the following recommended actions, as required:
Step 7.a
ISOLATE the Containment Recirc Sumps from the RWST, as follows:
(1) SHUT the following valves:
1 SI-323, RWST To RHR Pump B-SB (RAB 286)
(2) DE-ENERGIZE the following valves:
- 1SI-322 at breaker 1A31-SA-6E (RAB 286)
- 1 SI-323 at breaker 1 B31 -SB-6E (RAB 286)
Step 7.b
REFILL the RWST with B RHR Pump, as follows:
(1) SHUT 1 SI-326, Low Head SI Train A to Hot Leg Cross-over Isol Vlv.
(2) OPEN the following valves to align RHR HX outlet flow to the RWST:
- 1 SI-448, Low Head Si Recirc to RWST Root Isol Vlv
(3) USE the RHR Pump as needed.
Step 7.c
IF charging is required in the interim,
THEN USE the Boric Acid Tanks.
Step 7.d
WHEN RHR Pumps are no longer required to fill the RWST,
THEN:
(1) SHUT the following valves to isolate RHR HX outlet flow from the
RWST:
- 1 SI-448, Low Head Si Recirc to RWST Root Isol Vlv
(2) OPEN 1 SI-326, Low Head Si Train A to Hot Leg Cross-over Isol VIv.
Attachment 2
4
Step 8
PERFORM the following to prevent spurious valve opening:
Step 8.a
VERIFY the following valves are SHUT:
(RAB 286)
Step 8.b
DE-ENERGIZE the following valves:
- 1SI-300 at breaker 1A21-SA-7C (RAB 286)
- 1SI-310 at breaker 1A21-SA-9B (RAB 286)
AOP-36 Attachment 1 (Area Specific) Actions for Fire Area 1-A-BAL:
Step 1
PERFORM the following to prevent spurious valve operations:
Step l.a
VERIFY the following valves are OPEN
- 1CS-214, Charging/SI Pumps Minif low Isol (RAB 236 near Boric Acid
Pumps)
Area)
Step 1.b
DE-ENERGIZE the following valves:
- 1CS-214 at breaker 1A35-SA-4C (RAB 261)
- 1 CS-169 at breaker 1 A35-SA-4B (RAB 261)
- 1 CS-218 at breaker 1 B35-SB-14D (RAB 261)
- 1 CC-252 at breaker 1 E12-6B (RAB 261)
Step 5
CAUTION
. The following step will inhibit all automatic and manual safeguards functions
since a fire in this area could cause spurious actuations as well as disable
controls for resetting SI.
- Removal of Output Relay Power Fuses from both trains of SSPS will
generate a Reactor Trip signal. The Reactor should be shut down prior to
performing the following step.
Attachment 2
5
OBTAIN SSPS Key 96
AND DEFEAT both trains of SSPS by removing the listed fuses in the front
of the listed SSPS Output Cabinets:
- Train A, Output Cabinet No. 1, Output Relay Power fuses
- Train A, Output Cabinet No. 2, fuses 61 and 62
- Train B, Output Cabinet No. 1, Output Relay Power fuses
- Train B, Output Cabinet No. 2, fuses 61 and 62
Step 20
IF the following valves cannot be shut due to fire damage to their control
cables,
- 1 CS-1 66, VCT Outlet (1 -LCV-115E)
THEN:
Step 20.a
STOP ALL CSIPs.
Step 20.b
SHUT EITHER of the following valves:
- 1 CS-170, A CSIP Suction X-conn
- 1CS-1 68, C CSIP Suction X-conn with A CSIP
Step 20.c
SHUT EITHER of the following valves:
- 1CS-1 69, C CSIP Suction X-conn with B CSIP
- 1CS-171, B CSIP Suction X-conn
Step 20.d
VERIFY SHUT 1CS-214, Charging/SI Pumps Miniflow Isol.
Step 21
IF BOTH of the following occur due to fire damage to their control cables:
THEN ALIGN flow to the cooling tower, as follows:
Step 21.a
VERIFY OPEN 1 SW-275, ESW Return Header A to NSW.
Step 21.b
WHEN time permits,
THEN:
(1) DE-ENERGIZE 1 SW-270, ESW Header A Return to Aux Reservoir, at
breaker 1A35-SA-9C (RAB 261).
(2) OPEN 1 SW-270 locally (RAB 261).
(3) WHEN 1SW-270 is open,
THEN SHUT 1SW-276, ESW to NSW Discharge Hdr.
Attachment 2
6
Step 22
IF BOTH 1 SW-270 AND 1 SW-276 shut,
THEN CROSS-CONNECT ESW Discharge Headers as follows:
Step 22.a
VERIFY OPEN lSW-274, ESW Return Header B to NSW.
Step 22.b
VERIFY OPEN 1 SW-275, ESW Return Header A to NSW.
Step 22.c
VERIFY OPEN 1SW-271, ESW Header B Return to Aux Reservoir.
Step 22.d
WHEN time permits,
THEN:
(1) DE-ENERGIZE 1SW-270, ESW Header A Return to Aux Reservoir, at
breaker 1A35-SA-9C (RAB 261).
(2) OPEN 1SW-270 locally (RAB 261).
(3) WHEN 1 SW-270 has been opened,
THEN SHUT 1 SW-274, ESW Return Header B to NSW.
AOP-36 Attachment 1 (Area Specific) Actions for Fire Area 1-A-ACP:
Step lb
SECURE Rod Drive MG sets using OP-104, Rod Control System
OP-1 04
Step Number
Description
7.3.2.02
Place GENERATOR CIRCUIT BREAKER CONTROL
switch 1A to TRIP
7.3.2.03
Place MOTOR CIRCUIT BREAKER CONTROL switch 1A
to TRIP
7.3.2.04
Open Reactor Trip Breakers, if not already open.
7.3.2.05
Place GENERATOR CIRCUIT BREAKER CONTROL
switch 1 B to TRIP
Place MOTOR CIRCUIT BREAKER CONTROL switch 1 B
to TRIP
Step 2
If BOTH MDAFW pumps are disabled, THEN:
Attachment 2
7
Step 2c
Obtain a transfer panel key 33, 34, 35, 36, 99 or 106 (MCR or ACP key
locker)...
... and de-energize the TDAFW Pump Trip and Throttle Valve by removing
fuses lA-1 1/1 976 and 1A-12/1976
Step 2d
De-energize 1 MS-70 by opening disconnect switch on DP-1A2-SA-2B.
Step 2f
IF TDAFW Pump is NOT operating properly, THEN locally...
...VERIFY OPEN TDAFW Pump Trip and Throttle Valve
...VERIFY OPEN 1 MS-70, Main Steam B to Aux FW Turbine
Step 2g
IF MCB CST level indication is NOT available,
THEN locally monitor AFW pump suction pressure using Attachment 4.
Step 4
REMOVE the fuse for 1 BD-30 SA at panel ARP-1 9A
REMOVE the fuse for 1 BD-49 SA at panel ARP-1 9A
Step 6
OPEN the power supply breaker for 1 CS-235 at breaker 1 B31 -SB-1 OA
Step 7
ISOLATE AND VENT IA to 1CH-279
Step 7a
SHUT m1 IA-871 -l1 "
Step 7b
OPEN air filter drain petcocks on Instrument Air Filter
Step 7c
CHECK 1CH-279, AH-12 1ASA valve OPEN
Step 8
OPEN the power supply breaker for 1 CS-171 at breaker 1 B35-SB-4D
Step 9
Locally VERIFY OPEN 1 CS-171, B CSIP Suction X-Conn valve
Locally VERIFY OPEN 1CS-235, Charging Line Isolation valve
Step 10
Locally verify shut 1 BD-30, SG 1 B Blowdown Isolation valve
Locally verify shut 1 BD-49, SG 1 C Blowdown Isolation valve
Step 13
IF SG C PORV cycles erroneously, THEN:
Step 13c
IF SG C PORV manuaVautomatic station does not function properly,
THEN locally OPERATE SG C PORV using OP-126 for desired cooldown
rate.
Step Number
Description
8.2.1.2.01
Obtain pliers, flashlight, head set, extension cord
Attachment 2
8
8.2.1.2.02
Open Servo Valve Solenoid feeder breaker PP-iA312-SA-
3
Open Servo Valve Solenoid feeder breaker PP-1 B312-SB-
3
Open Servo Valve Solenoid feeder breaker IDP-1A-SIll-1 1
8.2.1.2.03
Remove the cover from the side of the PORV
8.2.1.2.04
Establish communications with the Control Room
8.2.1.2.07
To throttle open the PORV,
8.2.1.2.07a
Rotate Solenoid B manual override approximately 3/4 turn
in the clockwise direction
8.2.1.2.07b
As directed by the Control Room, slowly rotate Solenoid A
manual override approximately 3/4 turn in the clockwise
direction
8.2.1.2.07c
When the PORV is at its desired position, place Solenoid A
manual override back to its original position
8.2.1.2.08
To partially shut the PORV,
8.2.1.2.08a
Check Solenoid A manual override in the fully
counterclockwise position.
8.2.1.2.08b
As directed by the Control Room slowly rotate Solenoid B
manual override to its original position by rotating it
approximately 3/4 turn in the counterclockwise direction,
until the PORV starts to shut.
8.2.1.2.08c
When the PORV is at the desired position, rotate Solenoid
B manual override approximately 3/4 turn in the clockwise
direction.
Step 14
IF FCV-2071C, Aux FW C Regulator 1AF-131, spuriously CLOSES, THEN
Step 14a
REMOVE fuse 1 A-5/1952 at Transfer Panel 1 B
Step 14b
THROTTLE 1AF-149, Stm Turb Aux FW C Isolation, to maintain SG C level
AOP-36 Attachment 2 Actions For SSD I Equipment Powered by SSD 2:
Step 2
IF control power is lost to 1 CS-231, Charging Flow controller,
THEN PERFORM the following locally:
Attachment 2
9
Step 2.a
SHUT 1 CS-228, Normal Charging FCV Inlet Isolation Valve.
Step 2.b
MAINTAIN 25% to 60% PRZ level (charging flow) using 1CS-227, Normal
Charging FCV Bypass.
AOP-36 Attachment 3 Actions For SSD 2 Equipment Powered by SSD 1:
This attachment was reviewed but contained no hot standby local manual
operator actions.
LOCAL MANUAL OPERATOR ACTION STEPS
REVIEWED FOR ACHIEVING COLD SHUTDOWN
AOP-36 Attachment 1 (Area Specific) Actions for Fire Area 1-A-EPA:
Step 4.b
WHEN manpower is available,
THEN:
(1) DE-ENERGIZE the following valves:
- 1SI-246, SI Accumulator A Discharge, at breaker 1A21-SA-5C
- 1S1-248, SI Accumulator C Discharge, at breaker 1A21-SA-3D
Attachment 2, SSD 1 Equipment Powered by SSD 2:
Step 6
IF 1 RH-30, RHR Heat Xchg A Out Flow Cont, OR 1 RH-20, RHR Hx Xchg
A Byp Flow Cont, cannot be controlled due to loss of control power,
THEN:
Step 6.a
ISOLATE 1 RH-20 air supply, 1 IA-1 28-12, to cause it to fail closed.
Step 6.d
VERIFY RHR is cooling the RCS by trending temperature using ONE of
the following methods:
- ..... (MCR action)
- Local temperature indication TI-5551A (RHR Heat Exchanger Outlet)
Attachment 2
MANUAL ACTIONS DESCRIBED IN AOP-036
WITHOUT REQUIRED EMERGENCY LIGHTING
AOP-36, Section 3.0, for All Fire Areas
Step #
Description
13.a(7)
Open 1CS-526, BA Tk Supply to CSIP Isol. Vlv.
AOP-36, Attachment 1, for Fire Area 1-A-ACP
Step#
Description
1.b
Secure Rod Drive MG sets using OP-104, Rod Control System
2.c
Obtain a transfer panel key 33, 34, 35, 36, 99 or 106 (MCR or ACP key
locker) and de-energize the TDAFW Pump Trip and Throttle Valve by
removing 2 fuses
2.d
De-energize 1 MS-70 by opening disconnect switch on DP-1A2-SA-2B.
2.f
Locally verify open TDAFW Pump Trip and Throttle Valve and 1 MS-70,
Main Steam B to Aux FW Turbine
2.g
Locally monitor AFW pump suction pressure
4
Remove the fuses for 1 BD-30 SA and 1 BD-49 SA at panel ARP-19A
6
Open the power supply breaker for 1 CS-235 at breaker 1 B31 -SB-1 OA
9
Locally verify open 1CS-235
14.a
Remove fuse 1 A-5/1952 at Transfer Panel 1 B
AOP-36, Attachment 1, for Fire Area 1-A-BATB
Ste#0
l Description
1.b(1)
Shut 1SI-327, Low Head SI Train B to Hot Leg Crossover Isol. Vlv.
1.d(2)
Open 1SI-327, Low Head SI Train B to Hot Leg Crossover Isol. VIv.
I
AOP-36, Attachment 1, for Fire Area 1-A-EPA
Step #
Description
7.b(i)
Shut 1SI-326, Low Head SI Train A to Hot Leg Crossover Isol. Viv.
7.d(2)
Open 1 SI-326, Low Head SI Train A to Hot Leg Crossover Isol. Vlv.
Attachment 3
2
AOP-36, Attachment 1, for Fire Area 1-A-BAL SSA Area 1-A-BAL-B
Step #
Description
21.b(2)
Open 1 SW-270 locally (RAB 261).
22.c
Verify open 1 SW-271, ESW Header B Return to Aux. Reservoir.
22.d(2)
Open 1SW-270 locally (RAB 261). (Same as step 21.b(2) above but for
different plant conditions.)
MANUAL ACTIONS DESCRIBED IN AOP-036
WITHOUT REQUIRED BATTERY-BACKED EMERGENCY LIGHTING
BUT WITH DIESEL-POWERED FLOURESCENT LIGHTING
AOP-36, Section 3.0, for All Fire Areas
Step #
Descrintion
12.c
Monitor AFW pump suction pressure indicators as an alternative to CST
RNO
level indication: (Refer to Attachment 4, AFW Suction Pressure vs. CST
level)
- PI-2271 (at TDAFW Pump)
13.b(3)
(a) Shut 1CS-228, Normal Charging FCV Inlet Isolation Valve.
(b) Throttle 1 CS-227, Normal Charging FCV Bypass, as necessary to
control charging flow.
13.c
(3) Open one of the following breakers:
RNO
- 1 B31 -SB-4C,1SI-3 BIT Outlet
- 1A31-SA-4C,1SI-4 BIT Outlet
13.c
When directed by MCR, then locally throttle the de-energized valve to
RNO
maintain PRZ level:
- 1SI-3, BIT Outlet Isolation
- 1SI-4, BIT Outlet Isolation
AOP-36, Attachment 1, for Fire Area 1-A-ACP
Step #
Description
1.b
Secure rod drive MG sets using OP-104
2.c
Obtain a transfer panel key 33, 34, 35, 36, 99 or 106 (MCR or ACP key
locker) and de-energize the TDAFW Pump Trip and Throttle Valve by
removing 2 fuses
Attachment 3
3
2.f
Locally verify open TDAFW pump trip and throttle valve & 1 MS-70
2.g
Locally monitor AFW pump suction pressure
4
Remove the fuses for 1 BD-30 SA and 1 BD-49 SA at panel ARP-1 9A
AOP-36, Attachment 1, for Fire Area 1-A-BATB
Step #
Description
1.a(2)
(2) DE-ENERGIZE the following valves:
- 1SI-322 at breaker 1A31-SA-6E (RAB 286)
- 1SI-323 at breaker 1B31-SB-6E (RAB 286)
1.b(2)
(2) OPEN the following valves to align RHR HX outlet flow to the RWST:
1.d(1)
(1) SHUT the following valves to isolate RHR HX outlet flow from the
RWST:
AOP-36, Attachment 1, for Fire Area 1-A-EPA
Step #
Description
4.b(1)
DE-ENERGIZE the following valves:
- 1 SI-246, SI Accumulator A Discharge, at breaker 1A21 -SA-5C
- 1SI-248, SI Accumulator C Discharge, at breaker 1A21-SA-3D
7.a(2)
(2) DE-ENERGIZE the following valves:
- 1SI-322 at breaker 1A31-SA-6E (RAB 286)
- 1 SI-323 at breaker 1 B31 -SB-6E (RAB 286)
7.b(2)
(2) OPEN the following valves to align RHR HX outlet flow to the RWST:
7.d(1)
(1) SHUT the following valves to isolate RHR HX outlet flow from the
RWST:
Attachment 3
4
AOP-36, Attachment 1, for Fire Area 1-A-BAL-B
Step #
Description
1.a
VERIFY the following valves are OPEN
- 1CS-214, Charging/SI Pumps Miniflow Isol. (RAB 236 near Boric Acid
Pumps)
5
OBTAIN SSPS Key 96 AND DEFEAT both trains of SSPS by removing
the listed fuses in the front of the listed SSPS Output Cabinets:
- Train A, Output Cabinet No. 1, Output Relay Power fuses
- Train A, Output Cabinet No. 2, fuses 61 and 62
- Train B, Output Cabinet No. 1, Output Relay Power fuses
- Train B, Output Cabinet No. 2, fuses 61 and 62
16.b(l)
DE-ENERGIZE the following valves:
- 1 SI-246, SI Accumulator A Discharge, at breaker 1 A21 -SA-5C (RAB 286)
- 1 SI-247, SI Accumulator B Discharge, at breaker 1 B21 -SB-5C (RAB 286)
- 1 SI-248, SI Accumulator C Discharge, at breaker 1 A21 -SA-3D (RAB 286)
22.a
VERIFY OPEN 1SW-274, ESW Return Header B to NSW.
22.d(3)
WHEN 1SW-270 has been opened,
THEN SHUT 1 SW-274, ESW Return Header B to NSW.
AOP-36, Attachment 2, Safe Shutdown 1 Equipment Powered by Safe Shutdown 2
Step #
Description
2
IF control power is lost to 1CS-231, Charging Flow controller,
THEN PERFORM the following locally:
a. SHUT 1CS-228, Normal Charging FCV Inlet Isolation Valve.
b. MAINTAIN 25% to 60% PRZ level (charging flow) using 1 CS-227, Normal
Charging FCV Bypass.
6.a
ISOLATE 1 RH-20 air supply, 1 IA-1 28-12, to cause it to fail closed.
6.d
VERIFY RHR is cooling the RCS by trending temperature using ONE of
the following methods:
- Local temperature indication TI-5551A (RHR Heat Exchanger Outlet)
Attachment 3
5
AOP-36, Attachment 3, Safe Shutdown 2 Equipment Powered by Safe Shutdown I
Step #
Description
4.b
(1) OPEN feeder breaker 1A21-SA-5C, Accum 1A-SA Disch Iso (RAB
286).
(2) OPEN feeder breaker 1 A21 -SA-3D, Accum 1 C-SA Disch iso (RAB 286).
6.d
VERIFY RHR is cooling the RCS by trending temperature using ONE of
the following methods:
. Local temperature indication TI-5551A (RHR Heat Exchanger Outlet)
Attachment 3