Entergy Nuclear Operations, Inc.
'F'En terg Pilgrim Station yJ 600 Rocky Hill Road Plymouth, MA 02360 William J. Riggs Director, Nuclear Assessment April 14, 2003 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
SUBJECT:
Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station Docket 50-293 License No. DPR-35 Pilgrim Station 2003 On-Line and Refueling Outage (RFO) - 14 Inservice Inspection (ISI) Plan LETTER NUMBER:
2.03.045
Dear Sir or Madam:
This letter provides the Pilgrim Nuclear PowerStation (PNPS) Inservice Inspection (ISI) Plan for 2003, on-line and Refueling Outage-14 (RFO-14) examinations. On-line ISI examinations began in March 2003. RFO-14 is currently scheduled to start on April 19, 2003. The scope of examinations includes the following:
- 1. Attachment A provides the ASME code required inspections that have been scheduled for examination on-line prior to RFO-1 4 during the third inservice inspection interval in accordance with the 1989 Edition of ASME Xl and the Pilgrim Inservice Inspection Program.
- 2. Attachment B provides the ASME code required inspections that have been scheduled for examination in RFO-14 during the third inservice inspection interval in accordance with the 1989 Edition of ASME Xl for piping and the 1992 Edition with 1992 Addenda for IWE containment examinations. Examinations of Category C, D, and E austenitic stainless steel piping welds in RFO-1 4 will be scheduled in accordance with the NRC Safety Evaluation issued on September 15, 2000 for BWRVIP-75, "Technical Basis for Revisions to Generic Letter 88-01 Inspection Schedules," in lieu of Generic Letter 88-01 inspection schedule requirements. Pilgrim Station meets the requirements of the BWRVIP-75 Safety Evaluation including the open items identified by the NRC in the Safety Evaluation. Additionally, Pilgrim will comply with ASME Xl Appendix VIII to the fullest extent possible allowed by current technology.
- 3. Attachment C provides examination planned for reactor vessel internals. Examinations include those planned to follow the BWRVIP Guidelines and those recommended by industry and internal initiatives.
2431 203045
Entergy Nuclear Operations, Inc.
Letter Number: 2.03.045 Pilgrim Nuclear Power Station Page 2
- 4. Pilgrim will be inspecting piping for the effects of Flow Accelerated Corrosion (FAC) both on-line (2 points) and during RFO-14 (70 points).
- 5. Ultrasonic examinations of three Salt Service Water Piping Spools for wall thickness determination in accordance with Specification M-591 will be conducted online starting in March 2003.
- 6. Pilgrim will be inspecting 15 non-safety-related pipe supports and performing one leakage examination in accordance with Entergy Specification M-593, Augmented Inspection of Pressure Boundary Only (PBO) Piping and Components.
If you have any questions regarding the information contained in this letter, please contact Bryan Ford at 508-830-8403.
Sincerely, Attachment A:
ASME Xi Inservice Inspection Plan for 2003 Online Examinations Prior to RFO-14 (3 pages)
Attachment B:
ASME XI Inservice Inspection Plan for RFO-14 Examinations (4 pages)
Attachment C:
Pilgrim Station RFO-14 In-Vessel Visual Inspection Scope (IVVI) (1 page) cc:
Mr. Travis Tate, Project Manager Office of Nuclear Reactor Regulation Mail Stop: 0-8B-1 U.S. Nuclear Regulatory Commission 1 White Flint North 11555 Rockville Pike Rockville, MD 20852 U.S. NRC, Region 1 475 Allendale Road King of Prussia, PA 19406 Senior Resident Inspector Pilgrim Nuclear Power Station 203045
ATTACHMENT A ASME Xi INSERVICE INSPECTION PLAN FOR 2003 ONLINE EXAMINATIONS Component 1 0-E207B-N3-2 10-E207B-N3-3 10-E207B-N4-2 10-E207B-N4-3 GB-10-12HL1 (4)
GB-10-19HL1 (4)
HB-10-28HL1 (2) 3-WSD-5 GB-10-12-2D GB-10-3002-2-2 GB-10-9-2E GB-10-F116 GB-10-Fl53R GB-10-F17 GB-10-F59A GB-14-F39 GB-14-F40 HB-13-2-i A HD-13-F35 HD-14-2-2D HD-14-F19 HE-26-F42A HL-23-F22 DB-23-VBW10-i DB-23-VBW10-2 29-P208A-HL 30-El 22A-HL Description SHELL REINF PLATE NOZZLE REINF PLATE SHELL REINF PLATE NOZZLE REINF PLATE SUPPORT LUGS SUPPORT LUGS 2 HANGER LUGS ELBOW TO PIPE WELDOLET TO PIPE ELBOW TO PIPE WELDOLET VALVE TO TEE PIPE TO VALVE PIPE TO ELBOW PIPE TO VALVE PIPE TO VALVE PUMP TO PIPE FLANGE TO ELBOW PIPE TO VALVE REDUCER TO FLANGE VALVE TO ELBOW ELBOW TO VALVE NOZZLE TO PIPE VALVE BODY WELD VALVE BODY WELD PUMP INTEGRAL ATTMT HX INTEGRAL ATTMT Category C-B C-B.
C-B C-B C-C C-C C-C C-F-2 C-F-2 C-F-2 C-F-2 C-F-2 C-F-2 C-F-2 C-F-2 C-F-2 C-F-2 C-F-2 C-F-2 C-F-2 C-F-2 C-F-2 C-F-2 C-G C-G D-B D-B Svstem RHR RHR RHR RHR RHR RHR RHR CRD RHR RHR RHR RHR RHR RHR RHR CS CS RCIC RCIC CS CS RCIC HPCI HPCI HPCI SSW RBCCW Isometric ISI-E207B ISI-E207B ISI-E207B ISI-E207B ISI-1-10-4BSH1 ISI-I-10-4BSH1 ISI-1-10-1 B ISI-1-3-1 ISI-1-10-5BSH1 ISI-1-10-4ASH2 ISI-I-1-0-4BSH1 ISI-1-10-3A IS-I-1-0-5BSH1 ISI-I-10-4BSH1 ISI-I-1-0-5BSH2 ISI-1-14-2B ISI-1-14-2B ISI-1-13-3 ISI-1-13-2 ISI-1-14-2B ISI-1-14-2B ISI-1-13-4 ISI-I-23-4 ISI-1-23-5 ISI-1-23-5 ISI-1-29-1 SH2 ISI-E122A Exam MT MT MT MT MT MT MT MT UT MT UT MT UT MT UT MT UT MT UT MT UT MT UT MT UT MT UT MT UT MT UT MT UT MT UT MT UT MT UT MT MT VT-3 VT-3 Page 1 of 3
ATTACHMENT A Component Description 30-E209A-HL HX INTEGRAL ATTMT HE-30-104PS STANCHION HE-30-12HL HANGER LUG HE-30-238PS STANCHION HE-30-24HL HANGER LUG HE-30-26HL HANGER LUG HE-30-27PS STANCHION HE-30-346HL HANGER LUG IWE-LINERDRAINS LINER DRAINS AUGMENTED TORUS UT elev.-1 Ift 6in BAY IWE-TORUS-LOWER-B1 1
IWE-TORUS-LOWER-AUGMENTED TORUS UT elev.-1 lft 6in BAY B13 13 AUGMENTED TORUS UT elev.-11 ft 6in BAY IWE-TORUS-LOWER-B5 5 AUGMENTED TORUS UT elev.-11ft 6in BAY IWE-TORUS-LOWER-B9 9 IWE-TORUS-MWL-B1 AUGMENTED TORUS UT AT MWL BAY 1 IWE-TORUS-MWL-B13 AUGMENTED TORUS UT AT MWL BAY 13 IWE-TORUS-MWL-B5 AUGMENTED TORUS UT AT MWL BAY 5 IWE-TORUS-MWL-B9 AUGMENTED TORUS UT AT MWL BAY 9 H-10-1-106 RIGID HANGER H-10-1-107S RIGID HANGER H-10-1-131 RIGID HANGER H-10-1-179 SPRING HANGER H-10-1-5 SPRING HANGER H-10-1-54SH RIGID HANGER H-10-1-65 SPRING HANGER H-10-1 -94S RESTRAINT H-10-1-96S GUIDE H-10-1-P203A PUMP SUPPORT Category D-B D-B D-B D-B D-B D-B D-B D-B E-C E-C E-C E-C E-C E-C E-C E-C E-C F-A F-A F-A F-A F-A F-A F-A F-A F-A F-A Svstem RBCCW RBCCW RBCCW RBCCW RBCCW RBCCW RBCCW RBCCW CONT Isometric ISI-E209A ISI-1-30-1 SH2 ISI-1-30-1 SH2 ISI-I-30-2SH1 ISI-I-30-2SH1 ISI-I-30-2SH1 ISI-I-30-2SH1 ISI-I-30-2SH1 ISI-IWE-AUG-2 CONT ISI-IWE-AUG-1 CONT ISI-IWE-AUG-1 CONT ISI-IWE-AUG-1 Exam VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-2 UT UT UT UT UT UT UT UT VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 CONT CONT CONT CONT CONT RHR RHR RHR RHR RHR RHR RHR RHR RHR RHR ISI-IWE-AUG-1 ISI-IWE-AUG-1 ISI-IWE-AUG-1 ISI-IWE-AUG-1 ISI-IWE-AUG-1 ISI-I-10-5BSH1 ISI-I-1-0-4BSH1 ISI-1-10-4BSH1 ISI-1-10-4BSH1 ISI-1-10-1 B ISI-1-10-1 B ISI-I-1-0-4BSH2 ISI-1-10-3B ISI-1-10-3B ISI-P203A Page 2 of 3
ATTACHMENT A Component H-10-1-X51A H-1 2-1 -100 H-1 2-1-5 H-1 3-1 -P206 H-14-1-12 H-1 4-1-15 H-1 4-1 -P215A H-23-1 -X52 H-26-1 -194 H-26-1 -318 H-26-1-56 H-29-1 -36 H-29-1 -53 H-29-1 -P208A H-3-1 -22 H-3-1 -30 H-3-1 -38 H-30-1 -63SA H-50-1 -TORUSBAY5 Description ANCHOR RIGID HANGER GUIDE PUMP SUPPORT RIGID HANGER SPRING HANGER PUMP SUPPORT ANCHOR RIGID SUPPORT SPRING HANGER RIGID HANGER RIGID HANGER RESTRAINT PUMP SUPPORT RESTRAINT RESTRAINT RIGID SUPPORT ANCHOR Category F-A F-A F-A F-A F-A F-A F-A F-A F-A F-A F-A F-A F-A F-A F-A F-A F-A F-A System Isometric RHR ISI-1-10-1 RWCU ISI-1-12-2 RWCU ISI-1-12-2 RCIC ISI-1-13-2 CS ISI-1-14-2B CS ISI-1-14-2B CS ISI-P215A HPCI ISI-1-23-1 RCIC ISI-1-13-5 HPCI ISI-I-23-4 RCIC ISI-1-13-5 SSW ISI-1-29-1SH2 SSW ISI-1-29-lSH1 SSW ISI-1-29-1 SH2 CRD ISI-1-3-1 CRD ISI-1-3-1 CRD ISI-1-3-1 RBCCW ISI-1-30-2SH1 C1A175SH1 &
CONT Cl A-62-4 Exam VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 TORUS SUPPORTS F-A Page 3 of 3
ATTACHMENT B ASME XI INSERVICE INSPECTION PLAN FOR 2003 OUTAGE EXAMINATIONS Component RPV-L-1 -338A RPV-L-1 -338B RPV-L-1 -338C RPV-L-1-339A RPV-L-1 -339B RPV-L-1 -339C RPV-N2D-NIR RPV-N2D-NV RPV-N2E-NIR RPV-N2E-NV RPV-N2F-NIR RPV-N2F-NV RPV-N2J-NIR RPV-N2J-NV RPV-N4A-NIR RPV-N4A-NV RPV-N4B-NIR RPV-N4B-NV RPV-N4C-NIR RPV-N4C-NV RPV-N4D-NIR RPV-N4D-NV RPV-N9B-NIR RPV-N9B-NV 2R-N2D-1 Description LOWER INTERMEDIATE SHELL VERTICAL WELD LOWER INTERMEDIATE SHELL VERTICAL WELD LOWER INTERMEDIATE SHELL VERTICAL WELD UPPER SHELL VERTICAL WELD UPPER SHELL VERTICAL WELD UPPER SHELL VERTICAL WELD NOZZLE INNER RADIUS NOZZLE TO VESSEL NOZZLE INNER RADIUS NOZZLE TO VESSEL NOZZLE INNER RADIUS NOZZLE TO VESSEL NOZZLE INNER RADIUS NOZZLE TO VESSEL NOZZLE INNER RADIUS& BORE NOZZLE TO VESSEL NOZZLE INNER RADIUS& BORE NOZZLE TO VESSEL NOZZLE INNER RADIUS& BORE NOZZLE TO VESSEL NOZZLE INNER RADIUS& BORE NOZZLE TO VESSEL NOZZLE INNER RADIUS NOZZLE TO VESSEL SAFE END TO NOZZLE Categorv System Isometric B-A B-A B-A B-A B-A B-A B-D B-D B-D B-D B-D B-D B-D B-D B-D B-D B-D B-D B-D B-D B-D B-D B-D B-D B-F RPV RPV RPV RPV RPV RPV RPV RPV RPV RPV RPV RPV RPV RPV RPV RPV RPV RPV RPV RPV RPV RPV RPV RPV RPV IS1-1-54-1 1SI-1-54-1 ISI-1-54-1 1SI-1-54-1 1SI-1-54-1 1S1-1-54-1 IS1-1-54-1 IS1-1-54-1 ISI-1-54-1 ISI-1-54-1 ISI-1-54-1 IS1-1-54-1 ISI-I-54-1 ISI-1-54-1 ISI-1-54-1 ISI-1-54-1 IS1-1-54-1 ISI-1-54-1 ISI-1-54-1 ISI-1-54-1 ISI-1-54-1 1S1-1-54-1 1S1-1-54-1 ISI-1-54-1 ISI-1-2R-A Exam UT UT UT UT UT UT UT UT UT UT UT UT UT UT UT UT UT UT UT UT UT UT UT UT UT Page 1 of 4
ATTACHMENT B Component 2R-N2E-1 2R-N2F-1 2R-N2J-1 RPV-N9B-1 10-VB-1001 -33B 10-VB-1001 -68B 12-VB-1 201-80 13-VB-1 301-17 14-VB-1 400-6B 14-VB-1 400-91B 2-VB-202-5A 2-VB-63B 23-VB-2301 -5 23-VB-2301 -7 23-VB-2301 -8 2R-FB-BP-1A 2R-FB-BPA-1 2R-FB-N1 A-7BC-1 RPV-FB-CRD 10-0-24 10-0-25 1 OR-IA-3 1 OR-IA-4 1 OR-IA-6 1 OR-IA-7 12-1-26 12-1-27 12-0-28R 13-1-16 14-A-17 Description Category System Isometric Exam SAFE END TO NOZZLE SAFE END TO NOZZLE SAFE END TO NOZZLE NOZZLE TO SAFE END VALVE BOLTING VALVE BOLTING VALVE BOLTING VALVE BOLTING VALVE BOLTING VALVE BOLTING VALVE BOLTING VALVE BOLTING VALVE BOLTING VALVE BOLTING VALVE BOLTING FLANGE BOLTING FLANGE BOLTING FLANGE BOLTING CRD BOLTING PIPE TO PIPE PIPE TO PIPE PIPE TO ELBOW ELBOW TO PIPE PIPE TO VALVE VALVE TO PIPE ELBOW TO PIPE PIPE TO ELBOW PIPE TO ELBOW VALVE TO PIPE PIPE TO PENETRATION B-F B-F B-F B-F B-G-2 B-G-2 B-G-2 B-G-2 B-G-2 B-G-2 B-G-2 B-G-2 B-G-2 B-G-2 B-G-2 B-G-2 B-G-2 B-G-2 B-G-2 B-J B-J B-J B-J B-J B-J B-J B-J B-J B-J B-J RPV RPV RPV RPV RHR RHR RWCU RCIC CS CS RECIRC RECIRC HPCI HPCI HPCI RECIRC RECIRC RECIRC RPV RHR RHR RHR RHR RHR RHR RWCU RWCU RWCU RCIC CS ISI-I-2R-A ISI-1-2R-B ISI-I-2R-B ISI-1-54-4 ISI-1-10-1 ISI-1-10-1 ISI-1-12-2 ISI-1-13-1 ISI-1-14-1 ISI-1-14-1 ISI-1-2R-A ISI-1-2R-B ISI-1-23-1 ISI-1-23-1 ISI-1-23-1 ISI-I-2R-B ISI-I-2R-A ISI-I-2R-B N/A ISI-1-10-1 A ISI-1-10-1 A ISI-1-10-1 ISI-1-10-1 ISI-1-10-1 ISI-1-10-1 ISI-1-12-2 ISI-1-12-2 IS-I-i2-1 SH1 ISI-1-13-1 ISI-1-14-1 UT UT UT UT VT-i VT-1 VT-1 VT-i VT-i VT-i VT-i VT-i VT-i VT-i VT-i VT-i VT-1 VT-i VT-i UT UT UT UT UT UT UT UT UT UT UT 1
Page 2 of 4
ATTACHMENT B Component Description Category System Isometric Exam 14-A-18 14R-A-16 14R-B-1 6 2R-HA-1 2R-HA-4 6-N4C-2 6-N4D-2 6-N4B-5HL1 (4)
CLASS 1 HYDRO DC-10-Fl OR DC-1 O-F9 DC-1 4-Fl DE/DL-6-F68 EE-l-F138 DB-14-VBW24A-1 DB-14-VBW24A-2 1 -GE-X208A-HL IWE-GVWD-01 IWE-ANNDRN-080 IWE-ANNDRN-170 IWE-ANNDRN-260 IWE-ANNDRN-350 IWE-CB-GIBS135 IWE-CB-GIBS180 IWE-CB-X203D IWE-CB-X203E IWE-CB-X203F PIPE TO PIPE PENETRATION TO ELBOW PENETRATION TO ELBOW HEADER TO BEND HEADER TO BEND PIPE TO PIPE PIPE TO PIPE SUPPORT LUG CLASS 1 HYDRO PIPE TO VALVE PIPE TO VALVE PIPE TO VALVE REDUCER TO VALVE VALVE TO PIPE VALVE BODY WELD VALVE BODY WELD INTEGRAL ATTACHMENT GENERAL VISUAL WALKDOWN ANNULUS DRAINS(2) AT 80 AZ.
ANNULUS DRAINS(2) AT 170 AZ.
ANNULUS DRAINS(2) AT 260 AZ.
ANNULUS DRAINS(2) AT 350 AZ.
CONTAINMENT BOLTING CONTAINMENT BOLTING CONTAINMENT BOLTING CONTAINMENT BOLTING CONTAINMENT BOLTING B-J B-J B-J B-J B-J B-J B-J B-K-1 B-P C-F-1 C-F-1 C-F-1 C-F-2 C-F-2 C-G C-G D-B E-A E-C E-C E-C E-C E-G E-G E-G E-G E-G E-C F-A CS CS CS RECIRC RECIRC FW FW FW VARIOUS RHR RHR Cs FW MS CS CS MS CONT CONT CONT CONT CONT CONT CONT CONT CONT CONT CONT RHR ISI-1-14-1 ISI-1-1 4-1 ISI-1-1 4-1 ISI-1-2R-A ISI-1-21R-A ISI-1-6-1 ISI-1-6-1 ISI-1-6-1 VARIOUS ISI-1-10-4BSH1 ISI-I--0-4ASH2 ISI-1-14-1 ISI-1-6-i A ISI-I-1 -1 SH2 ISI-1-14-2A ISI-1-14-2A ISI-1-I-1 SH1 ISI-IWE-AUG-1 ISI-IWE-AUG-1 ISI-IWE-AUG-1 ISI-IWE-AUG-1 ISI-IWE-AUG-1 N/A N/A N/A N/A N/A UT UT UT UT UT UT UT MT VT-2 UT PT UT
MT UTr ;
MT -
MT VT-3 GV VT-2 VT-2 VT-2 VT-2 VT-i VT-i VT-i VT-i VT-1 IWE-LINERDRAINS LINER DRAINS H-10-1-175 SPRING HANGER ISI-IWE-AUG-2 ISI-I-1 0-1 VT-2 VT-3 Page 3 of 4
ATTACHMENT B Component Description Category System Isometric Exam H-2-1 -Hi0 H-2-1 -H-16 H-2-1 -SS5 H-1 204 H-1 205 H-1 45 H-6-1-59 H-6-1 -67 SPRING HANGER SPRING HANGER SNUBBER RIGID SUPPORT RIGID SUPPORT RIGID HANGER RIGID HANGER RIGID HANGER F-A F-A F-A F-A-CL4 F-A-CL4 F-A-CL4 F-A-CL4 F-A-CL4 RECIRC RECIRC RECIRC MS MS MS FW FW ISI-I-2R-A ISI-1-2R-A ISI-I-2R-A ISI-I-1-1 SH2 ISI-1-1-1 SH2 ISI-1-1 -1 SH2 ISI-1-6-1A ISI-1-6-1 A VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 VT-3 Page 4 of 4
ATTACHMENT C Pilgrim Station RFO-14 in Vessel Inspection Scope (IVVI)
- 1. Visual Feedwater sparger examination to NUREG 0619, attachment welds examined to ASME Xl and BWRVIP-48.
- 2. Visual Examination of Core Spray piping welds to BWRVIP-18.
- 3. Visual Examination of access hole covers to SIL 462 Rev 1.
5 RS-3 Welds.
50% of DF-2, DF-3 or AD 3ab, AD-1, and AD-2 welds.
- 5. Visual Examination of eight (8) guide tubes in accordance with BWRVIP-47
Page 1 of 1