P.O. Box 63 Lycoming, New York 13093 i
Constellation Generation Group Nine Mile Point Nuclear Station October 7, 2002 NMP2L 2074 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
Subject:
Nine Mile Point Unit 2 Docket No. 50-410; NPF-69 Monthly Operating Report for September 2002 Gentlemen:
Submitted herewith is the Operating Data Report, the Unit Shutdowns, and Summary of Operating Experience for September 2002.
Very truly yours, Lawrence A. Hopkins Plant General Manager LAH/jm Attachments cc:
Mr. H. J. Miller, NRC Regional Administrator, Region I Mr. G. K. Hunegs, NRC Senior Resident Inspector
A'GHME0NT PNRýG ORRESPONDENCE-APPROVAI ORM 0 Unit 1 0 Unit2
[1 Site Page
/
of Document
Title:
Qk a,'
2,,
Regulatory Due Date:
01//
0-2.
El N/R Applicability:
References:
DER NCTS Other____"
Prepared By: U Z
2 Print Ext Signature Dat6 Developmental Review Due By:
Name Department Name Department 7- *,--',<,.,.4
- ,o
/~-
r0s.
Technical/Safety Reviews Due By:
Technical Review: 0l N/R 0 Tech Spec 6.5.2 (Unit 1)
Tech Review Committee
[I NR QATR (Unit 2) or meeting #
Designee Department Designee Department Final Review Due By:.
Name Department Validation Reg Commitment*
Task*
E 0
E 0
03 I___
_o El 0]
_____E_
0___
0 l
- NCTS forms attached SORC" 9 N/R Meeting No.:
SRAB:
P N/R Meeting No or Poll Date:
Reviewer Comments and Approval A.
El Significant comments on this draft. Will need 0
B.
13 No Comments additional review or discussion before R
[E Minor/editorial comments (see attached markup) providing signature. (see attached markup)
El No further review required (sign below).
Reviewer Approval:
Date:
Post Signature Disposition LBD Change El N/R LDCR #
NCTS
[E N/R NCTS#
Correspondence Posting El NIR Completed per NLAP-RPR-O1 on (date)
Page 17 NIP-IRG-01 Rev 18
NINE MILE POINT NUCLEAR STATION UNIT #2
SUMMARY
OF OPERATING EXPERIENCE Nine Mile Point Unit Two operated with a capacity factor (MDC) of 101.57% and an availability factor of 100% for the month of September 2002.
On September 22, 2002, at 0800 hours0.00926 days <br />0.222 hours <br />0.00132 weeks <br />3.044e-4 months <br />, a planned power reduction was initiated to approximately 70% power for a control rod sequence exchange. Following satisfactory completion of this sequence exchange, full power operation was resumed on September 22, 2002 at 1926 hours0.0223 days <br />0.535 hours <br />0.00318 weeks <br />7.32843e-4 months <br />.
There were no challenges to the safety relief valves during this reporting period.
UNIT SHUTDOWNS APPENDIX B REPORTING PERIOD - SEPTEMBER 2002 DOCKET NO: 50-410 UNIT NAME: NMP#2 DATE: 10/02/02 Prepared by: T. McMahon TELEPHONE: (315) 349-4045 Duration Method of Cause & Corrective Actions No.
Date Type (Hours)
Reasons' Shutting Down 2 Comments F Forced S Scheduled
-- NONE--
Reason:
A-Equipment Failure (Explain)
B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training & License Exam F-Administrative G-Operational Error (Explain)
H-Other (Explain)
Method.
I-Manual 2-Manual Trip/Scram 3-Automatic Trip/Scram 4-Continuation 5-Other (Explain)
OPERATING DATA REPORT DOCKET NO DATE COMPLETED BY:
TELEPHONE 50-410 10/02/2002 T. P. McMahon (315) 349-4045 OPERATING STATUS Unit Name:
Reporting Period:
- 1. Design Electrical Rating (MWe)
- 2. Maximum Dependable Capacity (Net MWe) 3 Number of Hours Reactor was Critical:
4 Hours Generator On-Line:
5 Reactor Reserve Shutdown Hours:
6 Net Electrical Energy Gen (MWH)
Nine Mile Point Unit #2 September 2002 1,143.3 1,119.8 This Month 720.0 720.0 0.0 818,953.3 Yr-to-Date 5,827.2 5,775.1 0.0 6,549,293.3 Cumulative 101,030.5 98,156.0 0.0 102,607,626.0