I*
SOUTHERN CALIFORNIA EDISON An EDISON h\\'TER,,VATIONALL' Company A Edward Scherer Manager of Nuclear Oversight and Regulatory Affairs May 13, 2002 U. S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555
Subject:
Docket Nos. 50-361 and 50-362 Monthly Operating Reports for April 2002 San Onofre Nuclear Generating Station, Units 2 and 3 Gentlemen:
As required by Technical Specification 5.7.1.4 of Facility Operating Licenses NPF-10 and NPF-1 5, this letter provides the Monthly Operating Report for San Onofre Nuclear Generating Station, Units 2 and 3. This report is required to provide the operating statistics, shutdown experience, and documentation of all challenges to pressurizer safety valves, for each unit. Attachments 1 and 2 provide the subject report for Units 2 and 3, respectively. There were no challenges to pressurizer safety valves for either Unit 2 or 3.
If you have any questions, please contact Mr. Clay E. Williams at (949) 368-6707.
Sincerely, Attachments 1 & 2 cc:
E. W. Merschoff, Regional Administrator, NRC Region IV A. B. Wang, NRC Project Manager, San Onofre Units 2 & 3 C. C. Osterholtz, NRC Senior Resident Inspector, San Onofre Units 2 & 3 P. 0. Box 128 San Clemente, CA 92674-0128 949-368-7501 Fax 949-368-6085
<
-x NRC Monthly Operating Report, April 2002 San Onofre Nuclear Generating Station, Unit 2
USNRC MONTHLY OPERATING REPORT SAN ONOFRE NUCLEAR GENERATING STATION UNIT 2 April 2002 Docket No:
Unit Name:
Date:
Completed by:
Telephone:
50-361 SONGS - 2 May 13, 2002 C. E. Williams (949) 368-6707 Page 2 of 4 OPERATING DATA REPORT I
Design Electrical Rating (Net MWe) 1070 2
Maximum Dependable Capacity (Gross MWe) 1127 3
Maximum Dependable Capacity (Net MWe) 1070 This Month Yr-to-Date Cumulative 4
Number of Hours in Period 719 2,879 163,944 5
Number of Hours Reactor Was Critical
- 719 2,879 132,267 6
Hours Generator On-line
- 719 2,879 130,520 7
Unit Reserve Shutdown Hours
- 0 0
0 8
Net Electrical Energy Generated (MWh)
- 813,260 3,257,830 139,150,846
- Rounded
USNRC MONTHLY OPERATING REPORT SAN ONOFRE NUCLEAR GENERATING STATION UNIT 2 April 2002 Docket No:
50-361 Unit Name:
SONGS - 2 Date:
May 13, 2002 Completed by: C. E. Williams Telephone:
(949) 368-6707 Page 3 of 4 UNIT SHUTDOWNS AND POWER REDUCTIONS (1) F-Forced S-Scheduled (2) Reason:
A-Equipment Failure (Explain)
B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training & Ucense Examination F-Administrative G-Operational Error (Explain)
H-Other (Explain)
(3) Method:
1-Manual 2-Manual Scram 3-Automatic Scram 4.-Continuation from Previous Month 5-Reduction in the Average Daily Power Level of more than 20% from the previous day 6-Other (Explain)
(4) IEEE Std 805-1984 (5) IEEE Std 803A-1983 Number N/A Date N/A Type (1)
N/A Duration (Hours)
N/A Reason (2)
N/A Method of shutting down reactor (3)
N/A LER No.
N/A System Code (4)
N/A Component Code (5)
N/A Cause and corrective action to prevent N/A recurrence
USNRC MONTHLY OPERATING REPORT SAN ONOFRE NUCLEAR GENERATING STATION UNIT 2 April 2002 Docket No:
Unit Name:
Date:
Completed by:
Telephone:
50-361 SONGS - 2 May 13, 2002 C. E. Williams (949) 368-6707 Page 4 of 4
SUMMARY
OF OPERATING EXPERIENCE FOR THE MONTH Date Time Event 04/01/02 I0001 Mode 1, 99.8%(1) Reactor Power, 1187 MWe.
04/30/02 2400 Mode 1, 99.9%(') Reactor Power, 1188 MWe.
(1) 100% power equals 3438 MWt as revised by License Amendment approved on July 19, 2001.
NRC Monthly Operating Report, April 2002 San Onofre Nuclear Generating Station, Unit 3
USNRC MONTHLY OPERATING REPORT SAN ONOFRE NUCLEAR GENERATING STATION UNIT 3 April 2002 Docket No:
Unit Name:
Date:
Completed by:
Telephone:
50-362 SONGS - 3 May 13, 2002 C. E. Williams (949) 368-6707 Page 2 of 4 OPERATING DATA REPORT 1
Design Electrical Rating (Net MWe) 1080 2
Maximum Dependable Capacity (Gross MWe) 1127 3
Maximum Dependable Capacity (Net MWe) 1080 This Month Yr-to-Date Cumulative 4
Number of Hours in Period 719 2,879 158,495 5
Number of Hours Reactor Was Critical
- 719 2,805 129,696 6
Hours Generator On-line
- 719 2,777 127,597 7
Unit Reserve Shutdown Hours
- 0 0
0 8
Net Electrical Energy Generated (MWh)
- 791,509 3,076,650 134,464,439
- Rounded
USNRC MONTHLY OPERATING REPORT SAN ONOFRE NUCLEAR GENERATING STATION UNIT 3 April 2002 Docket No:
Unit Name:
Date:
Completed by:
Telephone:
50-362 SONGS - 3 May 13, 2002 C. E. Williams (949) 368-6707 Page 3 of 4 UNIT SHUTDOWNS AND POWER REDUCTIONS (1) F-Forced S-Scheduled (2) Reason:
A-Equipment Failure (Explain)
B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training & License Examination F-Administrative G-Operational Error (Explain)
H-Other (Explain)
(3) Method:
1-Manual 2-Manual Scram 3-Automatic Scram 4-Continuation from Previous Month 5-Reduction in the Average Daily Power Level of more than 20% from the previous day 6-Other (Explain)
(4) IEEE Std 805-1984 (5) IEEE Std 803A-1983 Number 2002-02 Date 02/04/27 Type (1)
S Duration (Hours) 48.4 Reason (2)
B Method of shutting down reactor (3) 5 LER No.
N/A System Code (4)
BI Component Code (5)
MO Circulating Water Pump 3P-1 15 Cause and corrective action to prevent replaced due to elevated motor stator recurrence temperature. Evaluation in progress.
USNRC MONTHLY OPERATING REPORT SAN ONOFRE NUCLEAR GENERATING STATION UNIT 3 April 2002 Docket No:
Unit Name:
Date:
Completed by:
Telephone:
50-362 SONGS - 3 May 13, 2002 C. E. Williams (949) 368-6707 Page 4 of 4
SUMMARY
OF OPERATING EXPERIENCE FOR THE MONTH Date Time 04/01/02 0001 Mode 1, 99.9%(1) Reactor Power, 1172 MWe.
04/26/02 2113 Circulating Water Pump 3P-1 15 removed from service for motor replacement.
04/27/02 0108 Commenced down power to 75% Reactor Power 04/27/02 0525 Unit at 75% Reactor Power 04/27/02 2200 Commenced power ramp to 85% Reactor Power 04/28/02 0155 Unit at 85% Reactor Power 04/28/02 2110 Circulating Water Pump 3P-1 15 returned to service following motor replacement 04/28/02 2150 Commenced power ramp to 100% Reactor Power 04/29/02 0130 Unit at Full Power, 99.6% Reactor Power, 1171 MWe 04/30/02 2400 Mode 1, 99.8%(1) Reactor Power, 1169 MWe.
(1) 100% power equals 3438 MWt as revised by License Amendment approved on July 19, 2001.