LR-N04-0061, January 2004 Monthly Operating Report for Salem, Unit 2

From kanterella
Jump to navigation Jump to search
January 2004 Monthly Operating Report for Salem, Unit 2
ML040550429
Person / Time
Site: Salem PSEG icon.png
Issue date: 02/17/2004
From: Fricker C
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N04-0061
Download: ML040550429 (3)


Text

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 FEB 1 7 2004 LR-N04-0061 O PSEG NuclearLLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 MONTHLY. PERATING REPORT SALEM GENERATING STATION UNIT 2 DOCKETNO. 50-311 In compliance with Section 6.9, Reporting Requirements fortke, Specifications, the operating statistics for Janua y'L004 'art-,beiUig forwarded.

Sincerely,

Sa ' Jrickeria M,,ne a

fl i;.

q

-niff.s' em lP ant M~anager,,R:t.A.'

a' I

I'

.j(.

.... 1 4.,

Attachments.

I I

X.,..

I,;

C Distribution

,I I'_1

  • '1

(

J

..)

G.

)

i:.

~

" t-r 95-2168 REV. 7199

I.

-.--'x.

'V DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-311 Salem 2 2/10/04 F. Todd (856) 339-1316 Reporting Period January 2004 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)

Maximum Dependable Capacity (MWe-Net)

No. of hours reactor was critical No. of hours generator was on line (service hours)

Unit reserve shutdown hours Net Electrical Energy (MWH) 1131 1116 Month Year-to-date Cumulative 744 744 128578 744 744 125057 0

0 0

842307 842307 128126894 UNIT SHUTDOWNS NO.

DATE J TYPE DURATION REASON METHOD OF CORRECTIVE ACTIONI F=FORCED (HOURS)

(1)

SHUTUING COMMENT S=SCHEDULED DOWN THE

______j REACTOR(2)

(1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H-Other 1-Manual 2 - Manual Trip/Scram 3-Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

DOCKET NO.: 50-311 UNIT: Salem 2 DATE: 2/10/04 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience

  • Salem 2 entered the month at approximately 99% power.
  • On January 16, Salem 2 reduced power to approximately 77% due to a planned line outage. Power was restored to approximately 99% on January 17 and remained there for the remainder of the month.
  • At the end of the month, Salem 2 completed 65 days of continuous on-line operation.