LR-N03-0518, November 2003 Monthly Operating Report for Salem Unit 1
| ML033570223 | |
| Person / Time | |
|---|---|
| Site: | Salem |
| Issue date: | 12/15/2003 |
| From: | Fricker C Public Service Enterprise Group |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| LR-N03-0518 | |
| Download: ML033570223 (3) | |
Text
.
PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 DEC 1 5 2003 LR-N03-051 8
§ PSEG NuclearLLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:
MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT I DOCKET NO. 50-272 In compliance with Section 6.9, Reporting Requirements for the Salem Unit I Technical Specifications, the operating statistics for November 2003 are being forwarded.
Sincerely, Ca I J. Fricker Salem Plant Manager Attachments C Distribution 95-2168 REV. 7199
DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-272 Salem 1 12/11/03 F. Todd (856) 339-1316 Reporting Period November 2003 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)
Maximum Dependable Capacity (MWe-Net)
No. of hours reactor was critical No. of hours generator was on line (service hours)
Unit reserve shutdown hours Net Electrical Energy (MWH) 1130 1096 I
Month Year-to-date Cumulative 720 7734 149922 720 7658 145209 0
0 0
770870 8294908 148198874 UNIT SHUTDOWNS NO.
DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTIONI F=FORCED (HOURS)
(1)
SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2)
(1) Reason (2) Method A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
DOCKET NO.: 50-272 UNIT: Salem 1 DATE: 12/11/03 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience Salem 1 entered the month at approximately 100% power.
On November 15, power was reduced for a scheduled line outage. Power was restored to 100% later that day.
On November 25, power was reduced to approximately 76% due to circulator repairs and river grass intrusion. Salem 1 ended the month at this reduced power level.
At the end of the month, Salem 1 completed 42 days of continuous on-line operation.