LR-N03-0393, August 2003 Monthly Operating Report for Salem Unit 1

From kanterella
Jump to navigation Jump to search
August 2003 Monthly Operating Report for Salem Unit 1
ML032671035
Person / Time
Site: Salem PSEG icon.png
Issue date: 09/15/2003
From: Fricker C
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N03-0393
Download: ML032671035 (3)


Text

I PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 SEP 1 5 2003 LR-N03-0393 o PSEG Nuclear LLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT I DOCKET NO. 50-272 In compliance with Section 6.9, Reporting Requirements for the Salem Unit 1 Technical Specifications, the operating statistics for August 2003 are being forwarded.

Operations Director Attachments C Distribution 96-2168 REV. 7jgg

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-272 Salem 1 919/03 F. Todd (856) 339-1316 Reporting Period August 2003 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)

Maximum Dependable Capacity (MWe-Net)

No. of hours reactor was critical No. of hours generator was on line (service hours)

Unit reserve shutdown hours Net Electrical Energy (MWH) 1130 1096 A.

Month Year-to-aate oumulative 732 5761 147949 686 5714 143265 0

0 0

747523 6211583 146115549 UNIT SHUTDOWNS NO.

DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION!

F=FORCED (HOURS)

(1)

SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2) 1 811103 F

58 hrs.

A 4

500kv 1-5 Breaker Failure 813103 (1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator TraininglLicense Examination F - Administrative G - Operational Error (Explain)

H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-272 Salem 1 9/9/03 R. Ritzman (856) 339-1445 Summary Of Monthly Operating Experience Salem I was offline at the beginning of the month.

The unit was placed online on August 3, reaching 100% reactor power on August 4.

At the end of the month, Salem 1 completed 28 days of continuous on-line operation.