MONTHYEARL-MT-04-036, License Amendment Request to Support 24-month Fuel Cycles2004-06-30030 June 2004 License Amendment Request to Support 24-month Fuel Cycles Project stage: Request L-MT-04-058, Schedule Change for 24-Month Fuel Cycles Amendment Request2004-09-16016 September 2004 Schedule Change for 24-Month Fuel Cycles Amendment Request Project stage: Other L-MT-04-067, Supplemental Submittal in Support of 24-Month Fuel Cycles License Amendment Request2004-11-0505 November 2004 Supplemental Submittal in Support of 24-Month Fuel Cycles License Amendment Request Project stage: Supplement ML0501807392005-01-26026 January 2005 1/26/05, Monticello - Request for Additional Information Related to Technical Specifications Change Request to Implement a 24-month Fuel Cycle Project stage: RAI ML0501807382005-01-31031 January 2005 Second Request for Additional Information Related to Technical Specifications Change Request to Implement a 24-hour Fuel Cycle Project stage: RAI ML0506704322005-03-0303 March 2005 Response to NRC Requests for Additional Information Regarding License Amendment Request Supporting 24-Month Fuel Cycles Project stage: Response to RAI ML0515300342005-05-27027 May 2005 Proposed Change Number (PCN) 561 Degraded Voltage Setpoints Project stage: Request L-MT-05-044, Response to NRC Guidance Regarding Mitigation Strategies2005-05-27027 May 2005 Response to NRC Guidance Regarding Mitigation Strategies Project stage: Other ML0512301572005-06-0303 June 2005 Third Request for Additional Information Related to Technical Specifications Change Request to Implement a 24-Month Fuel Cycle Project stage: RAI L-MT-05-075, Response to NRC Requests for Additional Information Regarding License Amendment Request Supporting 24-Month Fuel Cycles2005-07-0101 July 2005 Response to NRC Requests for Additional Information Regarding License Amendment Request Supporting 24-Month Fuel Cycles Project stage: Response to RAI L-MT-05-097, Additional Information to Support Technical Specification Changes for 24-Month Fuel Cycle License Amendment Request2005-09-27027 September 2005 Additional Information to Support Technical Specification Changes for 24-Month Fuel Cycle License Amendment Request Project stage: Request L-MT-05-088, 10 CFR 50.55a Request No. 13: Relief from Impractical Examination Coverage Requirements Pursuant to 10 CFR 50.55a(g)(5)(iii) for the Fourth Ten-Year Inservice Inspection Interval2005-09-27027 September 2005 10 CFR 50.55a Request No. 13: Relief from Impractical Examination Coverage Requirements Pursuant to 10 CFR 50.55a(g)(5)(iii) for the Fourth Ten-Year Inservice Inspection Interval Project stage: Other ML0527002522005-09-30030 September 2005 Issuance of Amendment Implementation of 24-Month Fuel Cycles Project stage: Approval ML0527803672005-09-30030 September 2005 Technical Specifications Pages Re Implementation of 24-Month Fuel Cycles Project stage: Other ML0535701612006-01-12012 January 2006 License Amendment, Issuance of Amendment Surveillance Test Intervals for Various Instruments Project stage: Approval ML0601700292006-01-12012 January 2006 Technical Specifications, Minimum Test and Calibration Frequency for Core Cooling, Rod Block and Isolation Instrumentation Project stage: Other 2005-03-03
[Table View] |
Text
Monticello Nuclear Generating Plant Operated by Nuclear Management Company, LLC September 16, 2004 L-MT-04-058 10 CFR Part 50 Section 50.90 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Monticello Nuclear Generating Plant Docket 50-263 License No. DPR-22 Schedule Change for 24-Month Fuel Cycles License Amendment Request (TAC No. MC3692)
Reference:
- 1) Letter from Nuclear Management Company, LLC to Document Control Desk, License Amendment Request To Support 24-Month Fuel Cycles, dated June 30, 2004.
In Reference 1 the Nuclear Management Company, LLC (NMC) requested U.S. Nuclear Regulatory Commission (NRC) approval of a License Amendment to the Monticello Nuclear Generating Plant (MNGP) Technical Specifications (TS). Specifically, the NMC proposed revisions to the MNGP TS Surveillance Requirements to support the implementation of 24-month fuel cycles. Further, the NMC requested approval of the amendment by March 1, 2005 with a 90 day implementation period.
NMC hereby modifies the requested approval date to June 30, 2005, with a 90 day implementation period.
The above schedule change is administrative in nature and has no impact on TS changes or justifications previously submitted. Further, the Determination of No Significant Hazards Consideration and the determination that the TS change meets the eligibility criterion for categorical exclusion and therefore, an Environmental Assessment is not required are also still applicable.
This letter makes no new commitments or changes to any existing commitments.
Thomas J. Palmisano Site Vice President, Monticello Nuclear Generating Plant Nuclear Management Company, LLC 2807 West County Road 75
- Monticello, Minnesota 55362-9637 Telephone: 763.295.5151
USNRC Page 2 cc:
Administrator, Region III, USNRC Project Manager, Monticello, USNRC Resident Inspector, Monticello, USNRC Minnesota Department of Commerce